General Contractor Supporting a Subcontractor’s Change Order Only for Owner to Reject the Change
December 09, 2019 —
David Adelstein - Florida Construction Legal UpdatesThe opinion in Westchester Fire Ins. Co, LLC v. Kesoki Painting, LLC, 260 So.3d 546 (Fla. 3d DCA 2018) leads to a worthy discussion because it involves a common scope of work occurrence on construction projects involving a general contractor and subcontractor. The contractor submits a subcontractor’s change order request to the owner and the owner rejects the change order. What happens next is a scope of work payment dispute between the general contractor and subcontractor. Yep, a common occurrence.
In this case, a general contractor hired a subcontractor to perform waterproofing and painting. A scope of work issue arose because the specifications did not address how the window gaskets should be cut and then sealed. The owner wanted the window gaskets cut at a 45-degree angle and the subcontractor claimed this resulted in increased extra work. The general contractor agreed and submitted a change order to the owner to cover these costs. The owner rejected the change order claiming it was part of the general contractor’s scope of work even though the cutting of window gaskets at a 45-degree angle was not detailed in the specifications.
After the subcontractor filed a suit against the general contractor’s payment bond surety, the project architect further rejected the change order because gasket cutting was part of the specification requirements. (Duh! What else was the architect going to say? It was not going to concede there was an omission that resulted in a change order to the owner, right?)
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Reference to "Man Made" Movement of Earth Corrects Ambiguity
December 20, 2012 —
TRED EYERLY, INSURANCE LAW HAWAIIIn
Pioneer Tower Owners Assn. v. State Farm Fire & Cas. Co., 12 NY3d 302 (2009), the New York Court of Appeals found an "earth movement" exclusion was ambiguous when applied to an excavation. The court now considered whether a similar exclusion, expressly made applicable to "man made" movement of earth, eliminated the ambiguity when loss was created by excavation.
Bentoria Holdings, Inc. v. Travelers Indem. Co., 2012 N.Y. LEXIS 3087 (N.Y. Oct. 25, 2012).
Plaintiff's building suffered cracks due to an excavation being conducted on the lot next door. A claim was submitted to Travelers, plaintiff's insurer. Travelers rejected the claim, relying on the earth movement exclusion.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law Hawaii.Mr. Eyerly can be contacted at
te@hawaiilawyer.com
Construction Defect Claims Not Covered
May 10, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe court found that the insured's negligent acts causing damage to only the structure of the home it built were not covered under the CGL policy. Westfield Ins. Co. v. Zaremba Builders II LLC, 2022 U.S. Dist. LEXIS 36189 (N.D. Ill. March 2, 2022).
Zaremba contracted to build a house for the Vrdolyak Trust. After completion of the home, the occupants found many problems, including painting defects such as bubbling and peeling, leaving the basement full of water for months, causing damage to ductwork, framing and piping in the house, etc. The Trust sued and Westfield denied a defense.
Westfield filed a declaratory judgment action for a ruling that it had no duty to defend or indemnify. On Westfield's motion for summary judgment, the court determined there was no property damage. Property damage included "physical injury to tangible property." When the alleged damage occurred in the course of a construction project, tangible property had to be property outside the scope of the contract for project.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Will There Be Construction Defect Legislation Introduced in the 2019 Colorado Legislative Session?
March 18, 2019 —
David McLain - Colorado Construction Litigation BlogWith the 2019 Colorado legislative session well underway, the construction industry is waiting with bated breath to see what the Democrat controlled legislature might do with respect to construction defect legislation. In recent years, having a split legislature has prevented any attempts to roll back positive changes in the law, either from the legislature or Colorado courts, that have been hailed by the construction community.
This year, odds are good that we will see at least one bill similar to two introduced last year that would hinder the ability to have disputes decided by binding arbitration. While not full frontal assaults on the Colorado Supreme Court decision in the Vallagio case, HB18-1261, the “Colorado Arbitration Fairness Act,” and HB 18-1262, the “Arbitration Services Provider Transparency Act,” would have negatively impacted the ability to resolve any type of case through arbitration. Anything that prevents the resolution of construction defect cases through arbitration will increase the judgments and settlements in such cases, ultimately increasing the costs of construction and for insurance for those in the industry.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
When Coronavirus Cases Spike at Construction Jobsites
July 27, 2020 —
Richard Korman, Scott Judy & Jeff Rubenstone - Engineering News-RecordWhen Covid-19 took hold in several US states in early spring, Choate Construction responded, as many contractors did, by quickly adopting federal workplace safety guidelines for disinfecting surfaces and maintaining social distancing. Enhanced by various state lockdown measures for businesses and the general public, the new safety system seemed to work with only a handful of workers on Choate’s projects testing positive.
Reprinted courtesy of Engineering News-Record reporters
Richard Korman,
Scott Judy and
Jeff Rubenstone
Mr. Korman may be contacted at kormanr@enr.com
Mr. Judy may be contacted at judys@enr.com
Mr. Rubenstone may be contacted at rubenstonej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
2016 Updates to CEB’s Mechanics Liens and Retail Leasing Practice Books Now Available
November 10, 2016 —
Garret Murai – California Construction Law BlogFor a number of years we have been honored to be asked by California’s Continuing Education of the Bar (“CEB”) to serve as update authors for several of their well-regarded construction and real estate practice books. Updates to two of those books were published in October and November:
- The 2016 Update to the CEB’s California Mechanics Liens and Related Construction Remedies was published in October. Covering both private and public works, the practice guide details the statutory payment remedies for unpaid work, including, mechanics liens, stop payment notices and construction bonds. Wendel Rosen served as update author for Chapters 2 and 3 which covers private works projects.
Read the court decision
Read the full story...
Reprinted courtesy of Garret Murai, Wendel Rosen Black & Dean LLP
Mr. Murai may be contacted at gmurai@wendel.com
Construction Suit Ends with Just an Apology
February 10, 2012 — CDJ STAFF
After suing a contractor for failing to complete the remodeling of their home, an Orange County couple has settled for an apology. Douglas J. Pettibone represented the contractor, who had lost his business after a broken neck, multiple surgeries, and an addiction to pain medicine. Mr. Pettibone represented his client pro bone. The case was settled in arbitration by JAMS.
Mr. Pettibone noted that his client gave “a heartfelt and very moving apology.” The remodeling was completed by another contractor, two years after Thorp Construction stopped work on the project. After the apology, the case was dismissed.
Read the full story…
Read the court decision
Read the full story...
Reprinted courtesy of
The Private Works: Preliminary Notice | Are You Using the Correct Form?
August 20, 2019 — William L. Porter, Esq. - Porter Law Group
The Private Works – Preliminary Notice form which contractors, subcontractors and suppliers had become accustomed to using for many years changed in 2004. Despite this change in law, many in the construction industry have still not started using the correct new form. Changes in the law, championed by the American Subcontractors’ Association, gave a significant new benefit to subcontractors and suppliers by giving the subcontractor or supplier some expectation of actually receiving notice of when a Notice of Completion or a Notice of Cessation has been recorded on many private works projects. The law also changed the language of the California Preliminary Notice that subcontractors and suppliers must use to protect their mechanics’ lien, bond claim and stop payment notice rights. If Owners do not send out the Notice of Completion as required by law they incur a diminishing of the protections afforded to them when they record a Notice of Completion or Notice of Cessation on many private works projects.
The revised law requires private project owners to notify all subcontractors and suppliers within 10 days after recording a Notice of Completion or Notice of Cessation that a Notice of Completion or a Notice of Cessation has actually been recorded. In order to receive such notice, the subcontractor or supplier must properly serve the new form of Preliminary Notice. If this properly occurs and the private project owner provides the required notice, then the subcontractor or supplier will have 30 days to record a Mechanics’ Lien. However, if an owner under such circumstances fails to properly notify a subcontractor or supplier within 10 days after recording a Notice of Completion or Notice of Cessation, then the Subcontractor or supplier will have 90 days to record a Mechanics’ Lien. The details of the law can be found in California Civil Code sections 8190, 8414 and 8416. Read the court decision
Read the full story...
Reprinted courtesy of William L. Porter, Esq., Porter Law Group
Mr. Porter may be contacted at bporter@porterlaw.com