Holly A. Rice - Saxe Doernberger & Vita, P.C.Florida’s newly formed Sixth District Court of Appeal (“Sixth DCA”) recently certified conflict with Florida’s Fourth District Court of Appeal on the issue of retroactive application of the pre-suit notice requirement contained in Florida Statute §627.70152.1 Earlier this year, the Fourth District Court of Appeal (“Fourth DCA”) held that the pre-suit notice provision applies retroactively, meaning, it applies to all suits filed after July 1, 2021, regardless when the insurance policy was issued.2 The Sixth DCA, in
Hughes v. Universal Property & Casualty Insurance Company,3 directly rejected the Fourth DCA’s interpretation and instead found a retroactive application of the pre-suit notice to be unconstitutional under Florida law. Prior to the Fourth DCA’s ruling, most trial courts had found no retroactive application for the pre-suit notice provision.4
In August 2021, shortly after Florida Statutes Section 627.70152 went into effect on July 1, 2021, Rebecca Hughes (“Hughes”) sued Universal Property & Casualty Insurance Company (“Universal Property”) for breach of contract after Universal Property denied her insurance claim. Hughes did not file a pre-suit notice under Section 627.70152. Universal Property moved to dismiss based on Hughes’ failure to file the pre-suit notice, arguing that the pre-suit notice requirement applies to all lawsuits filed after July 1, 2021, even if the claimant’s insurance policy was issued before the statute’s effective date. The trial court agreed with Universal Property and dismissed the lawsuit.
Read the court decisionRead the full story...Reprinted courtesy of
Holly A. Rice, Saxe Doernberger & Vita, P.C.Ms. Rice may be contacted at
HRice@sdvlaw.com
Remand of Bad Faith Claim Evidences Split Among Florida District Courts
September 04, 2018 —
Michael S. Levine & Daniel Hentschel - Hunton Insurance Recovery BlogWhether an insurance bad faith claim, joined by amendment to an underlying insurance coverage action, may be removed more than a year after the original action was begun has divided federal judges in the state of Florida but has not yet been considered by the Eleventh Circuit. Now, a new opinion out of the Middle District of Florida (Jacksonville Division) has added to the debate.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Daniel Hentschel, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Hentschel may be contacted at dhentschel@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Consider the Risks Associated with an Exculpatory Clause
November 24, 2019 —
David Adelstein - Florida Construction Legal UpdatesAn exculpatory clause in a contract is a clause aimed at relieving another party from certain liability. A disclaimer and insulation from liability. Obviously, if you are the party relieving the other party from liability, you want to consider this risk including the potential enforceability of this risk if something goes wrong. If you are the party asking for the insulation from liability, you do not want to create an exculpatory provision that disclaims and insulates you of all liability arising from the contract as it may create an illusory effect – that the agreement is nothing but a naked promise on your end because your promise is fully disclaimed and you are insulated from liability if you break your promise. This could result in an unenforceable contract.
The validity of such an exculpatory clause was at-issue in Pier 1 Cruise Experts v. Revelex Corp., 2019 WL 3024618 (11thCir. 2019). Although not a construction dispute, the exculpatory clause in this case was with two fairly sophisticated parties and expressly insulated one of the contracting parties from “any…damages regardless of kind or type…whether in contract, tort (including negligence), or otherwise.” Pier 1 Cruise Experts, 2019 WL at *7. This is a powerful exculpatory clause because it could be broadly construed to insulate that party from its own breaches of the contract.
In Florida:
[A]n exculpatory clause is enforceable so long as (1) the contracting parties have equal bargaining power and (2) the clause’s provisions are clear and unambiguous. With respect to the latter requirement, ‘the intention to be relieved from liability [must be] made clear and unequivocal and the wording must be so clear and understandable that an ordinary and knowledgeable person will know what he is contracting away.” In the same vein, exculpatory clauses are ‘strictly construed against the party seeking to be relieved of liability.’
Pier 1 Cruise Experts, 2019 WL at *7 (internal citations omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
California’s Skilled and Trained Workforce Requirements: Public Works and AB 3018, What You Need to Know
December 09, 2019 —
Brenda Radmacher & Nicholas Krebs - Gordon & Rees Construction Law BlogDo you have the proper skilled and trained workforce for your construction projects? If you take on public works projects in California, you may not be in compliance with the new changes in the law. To avoid civil penalties or nonpayment and potentially being precluded from future bids on public works contracts, you must critically review your team and proposal prior to accepting an award. Once awarded a public contact requiring a skilled and trained workforce, diligent reporting practices and oversight are required to maintain compliance.
Compliance with California’s skilled and trained workforce requirements for contractors, engineers, architects, design professionals, and suppliers competing for public works construction projects in California is mandated through enforcement with the enactment of AB 3018. Signed by Governor Brown in his last legislative session, AB 3018 dramatically increased the penalties for non-compliance with the existing skilled and trained workforce requirements in California. The new penalties include civil fines by the Labor Commissioner up to $10,000 per month per non-compliant contractor, disqualification from bidding on future public works contract, and withholding of payment for delinquent contractors. This update provides information on California’s skilled and trained workforce requirements, identifies key issues on compliance to avoid penalties, and discusses the impact of enforcement on construction professionals’ business practices.
Reprinted courtesy of
Brenda Radmacher, Gordon & Rees Scully Mansukhani and
Nicholas Krebs, Gordon & Rees Scully Mansukhani
Ms. Radmacher may be contacted at bradmacher@grsm.com
Mr. Krebs may be contacted at nkrebs@grsm.com
Read the court decisionRead the full story...Reprinted courtesy of
Preservationists Want to Save Penn Station. Yes, That Penn Station.
December 20, 2021 —
Kriston Capps - BloombergIn November, as one of her first major acts since taking office, New York Governor Kathy Hochul pared back development plans for New York City’s Pennsylvania Station set in place by her predecessor, disgraced former governor Andrew Cuomo.
The Cuomo plan would have greatly expanded Penn Station and upscaled the neighborhood; Hochul’s vision narrows the scope of work, but it still stands to dramatically transform the subterranean transportation hub, which has been the focus of various unrealized redesign dreams for decades. On Dec. 8, critics and supporters sounded off on the Penn Station scheme in a public hearing. More than 200 people registered to weigh in on how the 10 new skyscrapers coming to the area (shrunk down a bit under Hochul) would affect the scale and character of the community, and the historic buildings that would need to be razed to make way for new development.
Read the court decisionRead the full story...Reprinted courtesy of
Kriston Capps, Bloomberg
Transition Study a Condo Board’s First Defense against Construction Defects
December 04, 2013 —
CDJ STAFFAccording to the advice provided by T. Allen Mott and Nicholas D. Cowie, condominium boards would be well advised to “hire an engineer or architect to perform a transition study,” since it would be preferable to repair any problems while warranties are still in effect. They also caution that the board must “determine whether the developer-created budget and reserve fund are adequate to cover the cost of maintaining the condominium’s construction over time.”
They note that discovered in time, some problems are easy to fix, but left unrepaired, they can result in “extensive, hidden property damage requiring associations to borrow money and assess unit owners to cover the entire cost of repairing the developer’s construction defects and resulting property damage. The goal, as they point out, is “an amicable repair resolution.”
Read the court decisionRead the full story...Reprinted courtesy of
Mark Van Wonterghem To Serve as Senior Forensic Consultant in the Sacramento Offices of Bert L. Howe & Associates, Inc.
March 01, 2012 —
CDJ STAFFSacramento, CA — Bert L. Howe and Associates, Inc., is pleased to announce that Mark Van Wonterghem - General Contractor, has joined the firm as Senior Forensic Consultant. Mark will be responsible for leading the firm’s expansion in the newly formed Sacramento headquarters.
His focus will continue to be working with construction practice groups and claims professionals in the Sacramento and Bay Area markets. He will utilize the resources of the Construction Experts Group at Bert L. Howe & Associates in furthering the litigation support needs attendant to the firm’s Northern California clientele.
Mr. Van Wonterghem possesses extensive consulting and testimony experience. Through 32 years of experience in the construction industry he leverages extensive practical experience with multiple trades including concrete foundations, walls and flatwork, structural wood and steel framing, finish carpentry, drywall, lath & plaster/stucco, window & door installations, deck coating systems, metal and membrane flashings and above/below grade waterproofing. This trade experience encompasses both the commercial and residential construction sectors and has been vital in his ability to provide concise explanation of construction industry standards, as well as trade-specific standards of care.
Mr. Van Wonterghem has broad experience with all types of building construction ranging from concrete and steel commercial construction to high-end custom residential construction.
In connection with the Construction Experts Group at BHA, Mr. Van Wonterghem provides construction consulting and litigation support services to a wide variety of recognized construction claims professionals, owners, and publicly traded builders.
The firm’s Sacramento offices are located at the Gateway Oaks III office complex, 2520 Venture Oaks Way, Suite 435, Sacramento, CA 95833. Mr. Van Wonterghem can be reached via e mail at mvanwonterghem@berthowe.com or at (800) 783-1822.
Read the court decisionRead the full story...Reprinted courtesy of
Colorado Trench Collapse Kills Two
July 30, 2019 —
Engineering News-RecordFederal safety officials are investigating the April 16 collapse of a trench that killed two construction workers in northern Colorado. The two men—Cristopher Lee Ramirez, 26, and Jorge Baez Valadez, 41—were installing utilities at a site being developed by D.R. Horton Express Homes in Windsor, Colo., when they were trapped by soil and rocks in the 15-ft-deep trench. The rescue attempt lasted seven hours and involved small shovels because of fears of a second collapse.
Read the court decisionRead the full story...Reprinted courtesy of
Engineering News-RecordENR may be contacted at