Ninth Circuit Finds No Coverage for Construction Defects Under California Law
April 05, 2017 —
Tred R. Eyerly – Insurance Law HawaiiThe Ninth Circuit, applying California law, affirmed the district court's decision finding there was no coverage for construction defects. Archer W. Contractors v. Nat'l Union Fire Ins. Co., 2017 U.S. App. LEXIS 3796 (9th Cir. March 2, 2017).
Archer Western Contractors (AWC) was the general contractor for the San Diego County Water Authority's emergency water storage project. The pump house and turbine generators suffered property damage. The damage flowed from AWC's allegedly defective work on the property.
After settling a construction defect lawsuit brought against it by the Water Authority, AWC filed this case against National Union for failing to indemnity portions of the settlement agreement.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
NY Attorney General to Propose Bill Requiring Climate Adaptation for Utilities
May 21, 2014 —
Gerald B. Silverman – BloombergBloomberg BNA — New York Attorney General Eric T. Schneiderman (D) has proposed legislation to require that New York's electricity and gas utilities assess their vulnerability to the impacts of climate change and prepare a plan for adapting to severe weather.
Schneiderman May 19 said the proposed legislation would build on a February decision by the state Public Service Commission (PSC), which approved a plan by Consolidated Edison to spend $1 billion over the next four years for storm hardening and resiliency projects.
A spokeswoman for the attorney general told Bloomberg BNA that he is working with members of the Legislature to have the bill formally introduced.
The PSC decision also required that all New York utilities integrate the potential impacts of climate change into their system planning and construction forecasts and budgets.
Read the court decisionRead the full story...Reprinted courtesy of
Gerald B. Silverman, Bloomberg
Avoid a Derailed Settlement in Construction
March 28, 2022 —
Patrick Barthet - Construction ExecutiveMore and more construction cases are settling because lawyers know juries can prove to be unpredictable. The litigation process, as well as any actual trial, can be stressful, expensive and quite lengthy. Settlements are, for the most part, private while suits are public. Current reports find more than 90% of civil cases filed in state circuit courts are disposed of before trial. When that doesn't happen, things could go very poorly, as the case below illustrates.
The Case
Adam was seriously injured in a collision with a dump truck owned by Bang and driven by Tomas. While suit by Adam against Bang and Tomas was pending, Adam suggested they settle by having Bang pay him. Upon receipt of the offer, Bang's lawyer reached out confirming that his client was okay with the settlement amount but wished to add that the settlement also include the satisfaction of a lien filed by Adam's workers' compensation carrier. Adam's attorney refused that additional request, but that didn't stop Bang's lawyer. Based on the fact that Adam had agreed to the settlement amount, the lawyer filed a boiler plate notice of acceptance of settlement and had Bang issue a settlement check payable to Adam in the amount Adam had requested. Adam remained unwilling to compromise. He continued to resist the modified terms, which added satisfaction of the worker’s compensation lien. Bang then filed a motion to enforce settlement, arguing that since there was agreement on the settlement amount, Adam was required to do the deal.
Reprinted courtesy of
Patrick Barthet, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Barthet may be contacted at
pbarthet@barthet.com
Opoplan Introduces Generative AI Tools for Home-Building
February 06, 2023 —
Aarni Heiskanen - AEC BusinessOpoplan introduces its suite of generative AI architectural tools for builders and real estate brokers. The initiative intends to bridge the technological gap in custom home planning and building.
The tools introduced by the company also aim to reduce the overdependence on manual efforts and limited design options when it comes to lot analysis, design briefing, design planning, and many other pre-build tasks.
Through its AI-powered tools, Opoplan assists builders and home designers in saving time, money, and energy and more successfully close contracts, managing plans, and delivering single-family homes.
A series of tools for the home-building industry
Opoplan is headquartered in Dublin, Ireland, with a new US office in Raleigh, North Carolina, and was established in 2019. They provide pre-build house planning and design tools for custom builders, real estate brokers, and house designers.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Federal Court Predicts Coverage In Nevada for Damage Caused by Faulty Workmanship
April 03, 2013 —
Tred Eyerly - Insurance Law HawaiiMethodically analyzing the damage claims, the federal district court largely denied the insurers' motions for summary judgment for coverage of construction defect claims. Big-D Constr. Corp. v. Take It for Granite Too, 2013 U.S.Dist. LEXIS 8377 (D. Nev. Jan. 22, 2013).
Big-D was the general contractor for a remodeling project of International Gaming Technologies' (IGT) building. Big-D subcontracted with Take it for Granite Too (TIFGT) to install various tiling and stonework on the interior and exterior of the building.
After TIFGT began its stonework, a stone tile fill from an exterior wall. Over the next several months and after completion of TIFGT's work, two additional stones fell from exterior walls. IGT directed Big-D to replace TIFGT's stonework on the walls. Big-D notified TIFGT and requested that it make immediate repairs. TIFGT did not respond and eventually went out of business.
Experts opined that the cause of the stones falling was efflorescence between the tile and the wall. Efflorescence occurred when the stone started to deteriorate, spall, and become soft. It was caused by water entering through an open joint and getting behind the stone tile.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
Trial Court’s Grant of Summary Judgment On Ground Not Asserted By Moving Party Upheld
December 17, 2015 —
Laura C. Williams & R. Bryan Martin – Haight Brown & Bonesteel LLPIn Marlton Recovery Partners, LLC v. County of Los Angeles, et al. (filed 11/20/15), the California Court of Appeal, Second Appellate District, affirmed summary judgment in favor of the defendants County of Los Angeles, the County Treasurer-Tax Collector and Board of Supervisors (collectively the “County”) despite the fact summary judgment was granted on grounds not raised by the County. The Court of Appeal determined that because the plaintiff could not have shown a triable issue of material fact on the ground of law relied upon by the trial court, summary judgment was proper.
In the underlying case, plaintiff sought cancellation of penalties on delinquent property taxes for 26 parcels under Revenue and Taxation Code §4985.2, which allows the tax collector to cancel such penalties under certain circumstances. The County denied the request prompting plaintiff to challenge the denial on a petition for peremptory writ of mandate to the trial court.
Reprinted courtesy of
Laura C. Williams, Haight Brown & Bonesteel LLP and
R. Bryan Martin, Haight Brown & Bonesteel LLP
Ms. Williams may be contacted at lwilliams@hbblaw.com
Mr. Martin may be contacted at bmartin@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Equities Favor Subrogating Insurer Over Subcontractor That Performed Defective Work
August 04, 2015 —
Christopher Kendrick and Valerie A. Moore – Haight Brown & Bonesteel LLPIn Valley Crest Landscape v. Mission Pools (No. G049060, filed 6/26/15, ord. pub. 7/2/15), a California appeals court held that equities favor an insurer seeking equitable subrogation over a subcontractor that agreed to defend and indemnify claims arising out of its performance of work under the subcontract.
Valley Crest contracted to build a pool at the St. Regis Hotel in Dana Point. Valley Crest subcontracted with Mission Pools to perform the work. The master contract contained an indemnity clause in favor of St. Regis, and the subcontract contained an indemnity clause in favor of Valley Crest. An intoxicated guest who was rendered quadriplegic after diving in the shallow end of the pool sued the hotel, Valley Crest, Mission and others involved in the design, construction and operation of the pool. The suit included allegations that the pool depth was improperly marked; there was inadequate warning signage; and the pool finish caused the pool to appear deeper than it was. Valley Crest tendered its defense to Mission Pools under the subcontract’s indemnity agreement. When Mission did not respond, Valley crest filed a cross-complaint for indemnity. All parties ultimately reached a settlement with the injured plaintiff, leaving Valley Crest’s cross-complaint against Mission Pools.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com; Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Couple Claims ADA Renovation Lead to Construction Defects
December 30, 2013 —
CDJ STAFFA couple in Mercer County, West Virginia have claimed that the renovations done to their home not only failed to meet the requested ADA standards, but lead to construction defects, as reported by The West Virginia Record. Ray and Sherry Price are suing Lamberts Construction Company of Bluefield, West Virginia, claiming breach of contract and infliction of emotional distress. The couple hired to company to construct a bathroom addition, a bedroom addition, and a new driveway. In addition to other damages, they are also seeking the cost to repair the renovations.