Design-Build Contracting: Is the Shine Off the Apple?
March 09, 2020 —
John P. Ahlers - Ahlers Cressman & Sleight PLLCThe design-build delivery method offers many benefits to owners. Among the cited benefits are that projects are generally completed faster, at a lower cost, by allowing innovative approaches through early and continual contractor involvement in the design process. The design contractor serves as a single point of contact responsible for both the design and construction of the project.
The Washington State Department of Transportation (“WSDOT”) utilized the design-build procurement method on the largest project ($2 billion) of its type in the state of Washington: the Highway 99 Tunnel, which was finished almost three years late after the tunnel-boring machine (“Bertha”) broke down six years ago. The sorted tale of the SR-99 Tunnel Project was the source of many of this firm’s blog articles.[1] The State of Washington staunchly maintained that the design-build contract protected its taxpayers from covering the repair costs to the tunnel-boring machine when it broke down in 2013. Bertha did not resume tunneling for almost two years, putting on hold removal of the Alaska Way viaduct and rebuilding of the Seattle Waterfront without an elevated highway.
In December 2013, the contractor for the project, Seattle Tunnel Partners (“STP”), contended that a 110-foot long 8” steel pipe which Bertha hit caused the breakdown. That pipe had been installed for groundwater testing by WSDOT in 2002 during its preliminary engineering for the viaduct replacement project. The project’s Dispute Review Board (“DRB”) composed of three tunneling experts found that the pipe constituted a “differing site condition” for which the State was responsible to disclose to contractors. The Board, whose views were non-binding, did not opine about how much damage the undisclosed pipe cost.[2] In other words, the mere fact that a differing site condition occurred did not establish that there was a causal connection between the damages which STP was seeking (in excess of $600 million) and the differing site condition (the 8” steel pipe which WSDOT lawyers at trial derisively referred to as “nothing more than a toothpick for Bertha’s massive cutter head”). STP maintained that Bertha had made steady progress except for three days immediately after hitting the pipe. It didn’t help the contractors’ case that during the discovery phase of the two-month trial, WSDOT lawyers uncovered documents showing that the contractor’s tunnel workers encountered and logged the pipe before digging began.[3]
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers Cressman & Sleight PLLCMr. Ahlers may be contacted at
john.ahlers@acslawyers.com
What To Do When the Government is Slow to Decide a Claim?
October 02, 2015 —
Craig Martin – Construction Contractor AdvisorYou may know this situation all too well. You’ve submitted your certified claim to the contracting officer and there it sits. You ask for a decision and they say soon, but it’s not soon. And pretty soon, several months have gone by. Since the Court of Federal Claims’ decision in Rudolph and Sletten, Inc. v. U.S., the government may have to decide in 60 days or your claim will be deemed denied which would allow you to file your claim in the Court of Federal Claims.
Background
Rudolph and Sletten (R&S) were awarded a contract to construct the La Jolla Laboratory. On August 20, 2013, R&S submitted a certified claim seeking $26,809,003 as compensation for costs due to alleged government-caused delays and disruption, additional consultant costs and extra work.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Hundreds of Coronavirus Coverage Cases Await Determination on Consolidation
September 21, 2020 —
Tred R. Eyerly - Insurance Law HawaiiOn July 30, 2020, the Judicial Panel on Multi-District Litigation (JPML) heard oral argument on the potential consolidation of all federal cases involving business interruption coverage relating to coronavirus and shut-down orders. A decision will be rendered in the near future.
Meanwhile, many cases are on hold, waiting for a determination on consolidation. One such case is Pigment Inc. v. Hartford Fin. Servs. Group, 2020 U.S. Dist. LEXIS 133230 (S.D. Cal. July 27, 2020), where the court granted a stay pending a decision by the JPML. The case is a class action based on denial of coverage under business interruption insurance. Plaintiff's case alleged a bad faith denial that risked the permanent closure of its business due to unexpected temporary shutdowns from the COVID-19 pandemic. Plaintiff sought a stay pending the decision of the JPML.
The court considered the possible damage which could result from granting a stay, the hardship which a party could suffer in being required to go forward, and the orderly course of justice measured by the simplifying or complicating of issues, proof, and questions of law which could be expected to result from a stay.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Alleged Serious Defects at Hanford Nuclear Waste Treatment Plant
August 26, 2015 —
Beverley BevenFlorez-CDJ STAFFAccording to the Los Angeles Times, “A team of nuclear waste experts has found hundreds of serious defects at an Energy Department plant designed to turn millions of gallons of highly radioactive sludge into more stable solid glass at the former weapons facility in Hanford, Wash.” The report from 2014 was leaked, and stated that the “partially built facility is riddled with 362 ‘significant design vulnerabilities’ that could affect safety and future operations.” Thirty-seven experts led by two senior managers created the report.
The Los Angeles Times reported that the report findings “are significant because the plant is part of the Energy Department’s 2013 initiative to fix earlier problems that stalled construction of other parts of the treatment system at Hanford, the site of the nation’s worst radioactive contamination.”
Read the court decisionRead the full story...Reprinted courtesy of
Lease-Leaseback Fight Continues
June 01, 2020 —
Garret Murai - California Construction Law BlogIt’s like the rematch between Rocky Balboa and Apollo Creed.
In the right corner we have the California Taxpayers Action Network. In the left corner, Taber Construction, Inc. The title in contention: Construction of California’s Lease-Leaseback Program and, specifically, whether a construction firm can provide both pre-construction services as well as perform construction or, whether doing so, would be an impermissible conflict of interest under the Lease-Leaseback Law.
In their first appellate court match, California Taxpayers Action Network argued that a lease-leaseback arrangement between Taber Construction and the Mount Diablo Unified School District, whereby the District agreed to lease the site to Taber Construction one dollar (which is permissible) and to pay Taber a “guaranteed project cost” of $14,743,395 comprised of “tenant improvement payments” totaling $13,269,057 prior to the District taking delivery of the project (which was the issue in dispute) and six “lease payment amount[s]” of $345,723 plus interest paid in 30-day intervals, violated the Lease-Leaseback Law because the bulk of the payments by the District to Taber Construction occurred during construction rather than during the lease-term which could only “truly” occur after the District took delivery of the project. The 1st District Court of Appeal sided with Taber Construction, and in doing so created an appellate court split with the 5th District Court of Appeal’s decision in Davis v. Fresno Unified School District, 237 Cal.App.4th 261 (2015), which held that contractor who received all payments prior to turnover of the project to the district violated the Lease-Leaseback Law.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Hawaii Appellate Court Finds Agent May Be Liable for Failing to Submit Claim
November 01, 2022 —
Tred R. Eyerly - Insurance Law HawaiiAfter the agent informed the insured there was no coverage and submitting a claim would be a useless effort, the Hawaii Intermediate Court of Appeal reversed the trial court's dismissal of the insured's suit against the agent. Pflueger, Inc. v. AIG Holdings, Inc., 2022 Haw. App. LEXIS 279 (Haw. Ct. App. Sept. 2, 2022).
In May 2008, Pflueger notified its agent, Noguchi & Associates, Inc., that it had received federal grand jury subpoenas. Noguchi informed Pflueger that the subpoenas did not qualify as a "claim" under two policies issued by National Union. Consequently, Noguchi did not forward a claim or the subpoenas to National Union and did not seek clarification as to whether the grand jury subpoenas were covered under the policies. Pflueger relied upon Noguchi's representations and took no further action until its attorney submitted a demand letter tendering Pflueger's defense to Nation Union nine months later, in February 2009.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
It’s a Jolly Time of the Year: 5 Tips for Dealing with Construction Labor Issues During the Holidays
December 18, 2022 —
Matthew DeVries - Best Practices Construction LawIt’s that time of year again – the holiday season is upon us, and for those in the construction industry, that can mean a few extra challenges when it comes to maintaining efficiency on the job site.
Here are five best practices for dealing with labor during the holiday season:
- Communicate early and often: Make sure to clearly communicate any changes to the schedule or workload to your team as early as possible. This will give them time to plan and prepare, and help prevent any potential issues from arising.
- Offer incentives: Consider offering incentives to encourage your team to stay focused and productive during the holiday season. This could be something as simple as a bonus or extra time off, or something more creative like a gift card or other prize.
- Stay organized: The holiday season can be a busy time, so it’s important to stay organized and on top of your schedule. This means keeping track of deadlines, delegating tasks effectively, and staying in close communication with your team.
Read the court decisionRead the full story...Reprinted courtesy of
Matthew DeVries, Burr & Forman LLPMr. DeVries may be contacted at
mdevries@burr.com
Will Colorado Pass a Construction Defect Reform Bill in 2016?
December 17, 2015 —
Beverley BevenFlorez-CDJ STAFFAccording to blogger Jill Jamieson-Nichols of the Colorado Real Estate Journal, another construction defects bill may be debated in Colorado next year. Representative Dan Pabon told Jamieson-Nichols that “the answer lies in ‘thinking about the insurance piece’ so condominium developers can afford insurance against litigation that might arise.” She also stated that the city of Denver is considering ways to increase funding to increase affordable housing in the area.
Read the court decisionRead the full story...Reprinted courtesy of