Insurer's Motion for Summary Judgment to Reject Collapse Coverage Denied
November 24, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer unsuccessfully moved for summary judgment seeking to reject the insured's collapse claim. Gnannn v. United Servs. Auto, Ass'n, 2019 Conn. Super. LEXIS 1955 (Conn. Super Ct. July 11, 2019).
The insureds' home was built in 1985 and they purchased their home in 1993. A home inspection reported that some settlement and curing related cracks existed in the slab floor, but no signs of abnormal settlement were noticed. The concrete walls were in overall good condition.
In 2015, the insureds became aware of abnormal cracking in the basement. USAA was informed of the claim but denied coverage in October 2015. The insureds sued USAA. After suit was filed, the insureds hired an engineer, David Grandpre, to inspect their home. He observed severe cracking in the basement walls caused by an expansive chemical reaction within the concrete. The structure was not in imminent peril of falling down, and it continued as insureds' residence. But Mr. Grandpre noticed bulging and bowing, evidence that the concrete basement walls had failed and had begun to move inward due to the lateral pressure of the soil outside the home.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Florida Accuses Pool Contractor of Violating Laws
June 28, 2013 —
CDJ STAFFOne customer said that after his pool was finished, he started having problems with the concrete and tiles. He’s still waiting for the $7,300 he was awarded at arbitration. Others have complained that Nationwide Pools dug up their back yards and didn’t finish the work. Construction defects were not repaired, despite promises. And even after the company stopped doing any work anywhere, they continued to charge their customers “progress payments.”
The State of Florida has stepped into this, seeking restitution for homeowners who were charged for partially built or defective pools, and preventing the company officials from ever working in the pool construction industry. According to the suit, customers who complained about delays were told “a series of lies and misrepresentations about ‘supply shortages’ and ‘damaged items’ in order to string them along.”
Read the court decisionRead the full story...Reprinted courtesy of
English v. RKK- There is Even More to the Story
May 17, 2021 —
Christopher G. Hill - Construction Law MusingsJust when you thought that the litigation between W. C. English and RKK had no more to give (after all, there have been posts with wisdom from this case
here,
here, and
here), it keeps on giving. A
relatively recent opinion from this litigation involved, among other pre-trial motions, motions by English to exclude expert witness testimony. English sought to exclude Defendant CDM Smith, Inc’s expert testimony relating to CDM’s standard of care, the replacement of the bridge deck, English’s failure to fire CDM, and additional contributing factors regarding the spacing of the reinforcing steel. English sought to exclude RKK’s expert opinion regarding English’s owed standard of care vis a vis VDOT.
In evaluating these motions, the Court applied the following standard:
An expert qualified “by knowledge, skill, experience, training, or education, may testify “as to scientific, technical, or other specialized knowledge if it will assist the trier of fact. However, such testimony is only admissible if (1) “the testimony is based upon sufficient facts or data,” (2) “the testimony is the product of reliable principles and methods,” and (3) “the expert has reliably applied the principles and methods to the facts of the case.” [citations excluded here but stated in the opinion]
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Construction Defects Are Occurrences, Says South Carolina High Court
December 20, 2012 —
CDJ STAFFThe South Carolina Supreme Court has left the legislature’s new, expanded definition of “occurrence” in place, declining to declare it unconstitutional. South Carolina included faulty workmanship as an occurrence in response to a Supreme Court decision, which the court later reversed. One of the parties in that earlier decision, Harleysville Insurance, challenged the new law, claiming that the legislature didn’t have the power to pass a law to overturn a court ruling. The court did not concur.
However, the court did determine that the law was not retroactive and covered only claims filed after the law became effective in May 2011. The Chief Justice of South Carolina noted that “insurance coverage for construction liability lacks clarity, particularly with respect to whether construction defects constitute ‘occurrences’ under construction general insurance policies.”
Read the court decisionRead the full story...Reprinted courtesy of
Unfinished Building Projects Litter Miami
November 18, 2011 —
CDJ STAFFBuildings born in ambitious development plans that were never brought to completion form a grim reminder of the building bust in Miami, according to an article in the Miami Herald. One project started in 2007 as a residential project, later there were hopes to develop it as a hotel. These plans are ten months old with no work done.
Another project was projected as a 30-story office and commercial tower. Four were built before the project was abandoned. The article describes the site as “squalid.” Another project completed the planned 17 stories, but no work has been done beyond constructing the shell. Once planned as luxury condos, the owner owes more than $30,000 in property taxes.
Each of the three sites profiled in the Miami Herald have become dumping grounds for trash. The building skeletons have also become damaged by the elements. Some abandoned projects have been taken over by homeless people. Businesses near the abandoned properties have been hurt. The buildings also represent failed obligations to subcontractors who have put liens on the properties for work they performed but were never paid for.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Insuring Lease/Leaseback Projects
August 19, 2024 —
David G. Jordan & Jeffrey J. Vita - Saxe Doernberger & Vita, P.C.Overview
Several states utilize a unique statutory mechanism to allow school districts to finance the construction of public-school facilities. This arrangement (known as a “lease-leaseback agreement”) allows a school district to lease property to a contractor/developer, who then constructs or renovates a school facility on the property. Once the work is completed, the contractor/developer leases the school building back to the school district. The school district then makes lease payments over time, often many years, which can be structured in various ways to spread out the cost of construction. The arrangement typically requires a site lease for the land leased to the contractor/developer, a facilities lease for the lease-back of the school building to the school district and a traditional construction agreement. In some ways, the arrangement resembles a Public-Private Partnership (PPP) whereby a public entity collaborates with a private entity for the purpose of financing and delivering a project traditionally provided solely by the public sector.
Reprinted courtesy of
David G. Jordan, Saxe Doernberger & Vita, P.C. and
Jeffrey J. Vita, Saxe Doernberger & Vita, P.C.
Mr. Jordan may be contacted at DJordan@sdvlaw.com
Mr. Vita may be contacted at JVita@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
What to Expect From the New Self-Retracting Devices Standard
November 29, 2021 —
Andre Pelland - Construction ExecutiveOne of the latest and most anticipated changes to occur this year relevant to fall protection is the publishing of the ANSI/ASSP Z359.14 2021 revision. Although the effective date isn’t until August 2022, this change is prompting the need for end user to prepare for using and understanding the new terminology performance requirements that will ultimately alter equipment selection criteria.
The reason for its relevance is mostly due to its industry dependence and the increasing popularity of these types of devices. This voluntary consensus standard accounts for a vast portion of the fall protection market equipment and has been adopted as the industry standard, even though it is not the legal requirement. To assure a smooth transition, the immediate priority should be to understand the changes and what it means from a usability standpoint. A clear understanding of what changes devices need to comply will allow users to proceed with a comprehensive transition plan.
What Are the Most Relevant Changes for the User?
Classes
The most significant changes are for Class A and B devices used to designate arrest distances and forces and the introduction of the Class 1 and 2 devices. These classes were known as designators for arresting falls at 24 inches and under with higher forces (Class A), and 54 inches and under with lower forces (Class B). Class 1 devices allow anchoring on overhead anchorages only and limitg freefall to no more than two feet.
Reprinted courtesy of
Andre Pelland, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Pelland may be contacted at
andre.pelland@puresafetygroup.com
The Final Nail: Ongoing Repairs Do Not Toll the Statute of Repose
November 07, 2022 —
Kyle Rice - The Subrogation StrategistIn Venema v. Moser Builders, Inc., 2022 PA Super. 171, 2022 Pa. Super. LEXIS 414, the Superior Court of Pennsylvania (Superior Court) upheld an award of judgment on the pleadings from the Court of Common Pleas of Chester County (Trial Court). The Superior Court found that Pennsylvania’s 12-year Statute of Repose for improvements to real property (Statute of Repose) began to run upon the issuance of the certificate of occupancy following original construction of the home in 2003—not from the completion of repairs to the home that continued through 2008.
The underlying cause of action involved a home constructed by Moser Builders, Inc. (Moser) in 2003. The certificate of occupancy for the home was issued on August 13, 2003. Matthew Venema and Liza Squires (collectively, Venema) purchased the property from the original owners in 2004.
Read the court decisionRead the full story...Reprinted courtesy of
Kyle Rice, White and WilliamsMr. Rice may be contacted at
ricek@whiteandwilliams.com