Mississippi Sues Over Public Health Lab Defects
October 29, 2014 —
Beverley BevenFlorez-CDJ STAFFThe state of Mississippi “is suing architects and designers of a new Public Health Lab, saying the $28 million lab wasn't up to containing deadly diseases, biohazards and chemicals,” reported The Clarion-Ledger.
Dale Partners Architects, Earl Walls Associates, Eldridge and Associates, and Environmental Management Plus have been named as defendants.
"The estimated damages are $3 million," attorney Dorsey Carson told The Clarion-Ledger. "This building is where they test tuberculosis, or where they would test anthrax or any other (biohazards). You don't have a choice – it has to meet rigorous standards."
Charlie Alexander, a partner with Dale Partners, stated that “any allegations of design defects by his company and its team ‘are unfounded,’” reported The Clarion-Ledger.
Read the court decisionRead the full story...Reprinted courtesy of
Sometimes You Get Away with Unwritten Contracts. . .
January 20, 2020 —
Christopher G. Hill - Construction Law MusingsI have spoken often regarding the need for a well written construction contract that sets out the “terms of engagement” for your construction project. A written construction contract sets expectations and allows the parties to the contract to determine the “law” of their project. An unwritten “gentleman’s agreement” can lead to confusion, faulty memories, and more money paid to construction counsel than you would like as we lawyers play around in the grey areas.
One other area where the written versus unwritten distinction makes a difference is in the calculation of the statute of limitations. In Virginia, a 5 year statute of limitations applies to written contracts while a 3 year statute of limitations applies to unwritten contracts. This distinction came into stark relief in the case of M&C Hauling & Constr. Inc. v. Wilbur Hale in the Fairfax, Virginia Circuit Court. In M&C Hauling, M&C provided hauling services to the defendant through a subcontract with Hauling Unlimited in 2014, the last of which was in July. M&C provided over 2000 hours of hauling and provided time tickets (that were passed to Mr. Hale on Hauling Unlimited letterhead and signed by Mr. Hale or his agent) and an invoice stating the price term of $75.00 per hour. No separate written contract between M&C and Hauling Unlimited or Mr. Hale existed.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
John Paulson’s $1 Billion Caribbean Empire Faces Betrayal
November 27, 2023 —
Jim Wyss & Tom Maloney - BloombergIn the decade since hedge fund billionaire John Paulson took a grand gamble on Puerto Rico, he’s faced the wrath of the markets and mother nature.
He’s navigated hurricanes, earthquakes, the pandemic and the largest municipal bankruptcy in US history to amass a portfolio of luxury hotels and resorts, high-end office blocks, and auto dealerships catering to the island’s rich.
Now, just a few months after breaking ground on one of San Juan’s tallest and most exclusive residential towers, Paulson is facing a new wave of threats: lawsuits that strike at the heart of his Caribbean empire.
Reprinted courtesy of
Jim Wyss, Bloomberg and
Tom Maloney, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Not If, But When: Newly Enacted Virginia Legislation Bans “Pay-If-Paid” Clauses In Construction Contracts
August 22, 2022 —
Joseph A. Figueroa & Thomas E. Minnis - ConsensusDocsRecently passed legislation in Virginia is likely to dramatically change contractual relationships between prime contractors and subcontractors in the Commonwealth. Abrogating well-established common-law principles set forth by the Supreme Court of Virginia, on April 27, 2022, the Virginia General Assembly, after receiving input from Virginia Governor Glenn Youngkin, passed Senate Bill 550 banning “pay-if-paid” clauses in public and private construction contracts. Contractors performing work in Virginia should take note of the new law, which goes into effect next year and will apply to any contracts executed after January 1, 2023.
The History Of Pay-if-Paid Clauses In Virginia
Broadly speaking, “pay-if-paid” clauses are a commonly used tool by prime contractors on construction projects to shift the risk to subcontractors in the event that the owner does not pay the prime contractor for work. Such clauses usually include language creating an express condition precedent to the subcontractor’s right to be paid for work under a subcontract, stating that the prime contractor shall be under no obligation to pay the subcontractor for work unless and until the prime contractor first receives payment for that work by the project owner. The “pay-if-paid” clause also has a less extreme cousin, the “pay-when-paid” clause, which merely delays the time in which the prime contractor is obligated to pay the subcontractor to the time in which the prime contractor is paid by the owner. It does not, however, extinguish the prime contractor’s ultimate obligation to pay the subcontractor.
Reprinted courtesy of
Joseph A. Figueroa, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs) and
Thomas E. Minnis, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs)
Mr. Figueroa may be contacted at jfigueroa@watttieder.com
Read the court decisionRead the full story...Reprinted courtesy of
The Connecticut Appellate Court Decides That Construction Contractor Was Not Obligated To Continue Accelerated Schedule to Mitigate Its Damages Following Late Delivery of Materials by Supplier
April 11, 2022 —
Robert M. Barrack - Gordon & ReesIn United Concrete Prods. v. NJR Constr., LLC, 207 Conn. App. 551, 263 A.3d 823 (2021), the Connecticut Appellate Court has issued a decision that should be of interest to the Connecticut construction industry and the construction bar. The lawsuit arose out of the late delivery of materials on a construction project, which is a frequent problem on construction projects. In United Concrete Products, the defendant general contractor, NJR Construction, LLC (“NJR”) was retained by the State of Connecticut Department of Transportation (“DOT”) to replace a bridge over the Hockanum River (“Project”). Id. at 555-58 (2021). The Prime Contract provided that NJR with an eight-week time-frame to perform the work, at which time the road would be closed to traffic. Id. The Prime Contract also provided for a bonus of $3,000 for each day the road was opened to traffic prior to the eight week deadline of August 8, 2016, and for liquidated damages of $3,000 for each day the road remained closed beyond the deadline. Id.
NJR subsequently entered into a purchase order (“Subcontract”) with the plaintiff, United Concrete Products, Inc. (“United”), whereby United agreed to provide certain concrete components for the Project, including ten pre-stressed concrete beams. Id. The Subcontract required that United deliver the concrete beams by June 7, 2016, but, NJR did not actually schedule the delivery until June 29, 2016. Id. Nevertheless, even with that schedule NJR could have reopened the road by July 19, 2016, which would have allowed it to receive the full $60,000 incentive bonus. However, United did not deliver the concrete beams until July 26, 2016, which caused NJR to lose the incentive bonus, be assessed liquidated damages by the DOT, and to incur additional delay damages. Id. After deducting the amount of $179,500 in damages that it incurred due to United’s late delivery of the beams, NJR paid United the balance of $66,074.75. Id.
Read the court decisionRead the full story...Reprinted courtesy of
Robert M. Barrack, Gordon Rees Scully Mansukhani, LLPMr. Barrack may be contacted at
rbarrack@grsm.com
Wharf Holdings to Sell Entire Sino-Ocean Stake for $284 Million
December 10, 2015 —
Bloomberg News – BloombergWharf Holdings Ltd., a Hong Kong-based real-estate developer, said it has agreed to sell its entire stake in Sino-Ocean Land Holdings Ltd. for HK$2.2 billion ($284 million) to an undisclosed buyer, three days after Anbang Insurance Group Co. purchased about a fifth of the Chinese builder’s shares.
Wharf will sell 445 million shares, or 5.93 percent of Sino-Ocean Land’s stake, for HK$5 each, the company said in a statement on its website on Thursday. It expects to complete the transaction next week.
Read the court decisionRead the full story...Reprinted courtesy of
Bloomberg News
New Mandatory Bond Notice Forms in Florida
December 16, 2019 —
Brian A. Wolf & Miles D. Jolley - Smith CurrieSubcontractors and suppliers must now use new, statutory notice of nonpayment forms to preserve payment bond claims, and sign each notice of nonpayment under oath.
The State of Florida instituted changes to the statutes governing public-project payment bonds (section 255.05, Florida Statutes) and private-project payment bonds (section 713.23, Florida Statutes). The changes went into effect on October 1, 2019. Previously, notices of nonpayment were not required to be signed under oath. Now, the law requires the use of specific statutory notice forms that claimants must sign under oath. Previously, there were no statutory penalties for claimants who exaggerated the amount claimed against a payment bond. Now there are specific statutory penalties against a claimant who willfully or negligently signs a notice of nonpayment that includes a claim for work not performed or materials not furnished, or who is guilty of signing a notice prepared with willful or gross negligence.
Public construction payment bonds are governed by section 255.05, Florida Statues, also known as Florida’s Little Miller Act. This statute requires all payment bond claimants who don’t have a direct contract with the general contractor to serve both the bonding company and the general contractor with a notice of nonpayment no later than 90 days after their last date of work or last delivery of materials. The amended statute now requires that the claimant use the statutory notice form and sign the form under oath. If the claimant includes exaggerated claims, or intentionally makes a claim for work or materials not provided, or otherwise prepares a notice with gross negligence, then the bonding company and the general contractor will be able to use such as a complete defense to an otherwise valid bond claim.
Reprinted courtesy of
Brian A. Wolf, Smith Currie and
Miles D. Jolley, Smith Currie
Mr. Wolf may be contacted at bawolf@smithcurrie.com
Mr. Jolley may be contacted at mdjolley@smithcurrie.com
Read the court decisionRead the full story...Reprinted courtesy of
ASCE Joins White House Summit on Building Climate-Resilient Communities
October 09, 2023 —
The American Society of Civil EngineersRESTON, Va. – The White House Climate Policy Office hosted the Summit on Building Climate Resilient Communities today and unveiled its
National Climate Resilience Framework for communities to build more resiliently as they face increasingly severe weather events. The framework features comprehensive recommendations and opportunities for action, including partnerships between federal agencies and leading standards development organizations such as the
American Society of Civil Engineers (ASCE), to improve the resilience of buildings and other infrastructure. ASCE president Maria Lehman, P.E., was in attendance for the Summit.
ASCE's most widely adopted standard,
ASCE 7-22, is the primary reference of structural design requirements in all U.S. building codes and is updated every six years to reflect the latest data and trends presented by an ever-changing climate. Its most recent update, published in 2022, includes updates to environmental hazards used for building design including new wind speeds along the hurricane coastline, a completely new chapter for tornado loads, and the most substantial update to its chapter on flood loads since the inception of ASCE 7-22 – calling for structures to be built to withstand 500-year floods rather than the previous standard of 100-year flood mitigation.
Although modern codes and standards, such as ASCE 7-22, can mitigate climate hazards, many communities throughout the U.S. have not yet adopted these practices. The new White House framework calls for ensuring federal funding requires climate-resilient infrastructure investments by encouraging government at all levels to adopt consensus-based engineering standards, which would go a long way towards addressing vulnerabilities posed by future climate impacts.
ASCE, in conjunction with industry leaders represented at the Summit, supports federal efforts to improve climate data, enforce the most stringent codes and standards, and provide technical assistance to building and infrastructure stakeholders. To learn more about environmental hazard mitigation resources, follow
ASCE's Pathways to Resilient Communities Toolkit, a plain-language guide for federal, state, and local leaders as they seek out standards, best practices, data, and strategies that can be implemented to safeguard communities across the country from increasingly severe weather events.
ABOUT THE AMERICAN SOCIETY OF CIVIL ENGINEERS
Founded in 1852, the American Society of Civil Engineers represents more than 150,000 civil engineers worldwide and is America's oldest national engineering society. ASCE works to raise awareness of the need to maintain and modernize the nation's infrastructure using sustainable and resilient practices, advocates for increasing and optimizing investment in infrastructure, and improve engineering knowledge and competency. For more information, visit www.asce.org or www.infrastructurereportcard.org and follow us on Twitter, @ASCETweets and @ASCEGovRel.
Read the court decisionRead the full story...Reprinted courtesy of