4 Ways to Mitigate Construction Disputes
March 20, 2023 —
Bill Shaughnessy - ConsensusDocsResolving construction disputes in litigation (court or arbitration) can be expensive and may drag on for years. Most disputes could have been avoided, or at least mitigated, had the parties (both owners and contractors) identified contract risks during negotiations and been more proactive in communicating the risks during execution of the work. This article highlights four practical risk management approaches that help all parties focus on their mutual interest in close coordination and clear communication at the beginning of the project as well as throughout performance:
- Identifying and allocating risks;
- Accurate scheduling;
- Clear project documentation and communication; and
- Real-time dispute resolution.
The intent of these techniques is not to shift legal obligations or risks. Rather, the intent is to keep project personnel and project management for all the participants focused on communicating and working together, including responsibly confronting real problems to avoid or mitigate their impact. Allocating risks, scheduling, project documentation and communication, and real-time dispute resolution are independently relevant on a bilateral basis between the owner, designer, and the various contractors. These approaches and their diligent execution by the parties during construction contribute far more to a successful project than anything lawyers and claims consultants can contribute in after-the-fact legal proceedings.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Shaughnessy, Jones Walker LLP (ConsensusDocs)Mr. Shaughnessy may be contacted at
bshaughnessy@joneswalker.com
Time To “Construct” New Social Media Policies
March 28, 2022 —
Aaron C. Schlesinger, Lauren Rayner Davis & Jennifer Harris - ConsensusDocs1. The Social Media Dilemma
Social media has significantly impacted all facets of society, especially the way people communicate. Its impact and application to the construction industry is no different. TikTok, the video-sharing platform, is one of the world’s most popular platforms today, with over one billion active users monthly. From just one video, users can gain thousands—if not millions—of followers overnight. Social media has been used to present a narrative that the workplace can be fun, or that employees are enjoying working together. Social media can also, however, serve as a tool to document a perfect storm of events, such as a building collapse or crane malfunction, which can then be misconstrued and smeared throughout the internet, all with your company’s logo in the background.
So, what happens when an incident on your jobsite is branded across social media as a #constructionfail, and the project owner ultimately initiates legal action? Can this video be used against your company? Can employers limit or otherwise restrict employees’ social media activity to avoid potential liability? How does the existence of social media posts affect dispute resolution procedures?
Reprinted courtesy of
Aaron C. Schlesinger, Peckar & Abramson, P.C. (ConsensusDocs),
Lauren Rayner Davis, Peckar & Abramson, P.C. (ConsensusDocs) and
Jennifer Harris, Peckar & Abramson, P.C. (ConsensusDocs)
Mr. Schlesinger may be contacted at aschlesinger@pecklaw.com
Ms. Davis may be contacted at ldavis@pecklaw.com
Ms. Harris may be contacted at jharris@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Maybe California Actually Does Have Enough Water
September 06, 2021 —
Francis Wilkinson - BloombergIt’s hard to know how much to panic over California’s dwindling water supplies. The state has never really had enough water, after all, yet lawns in Beverly Hills somehow remain perpetually green. Earlier this month, however, came a sign that life might soon be getting more uncomfortable for more Californians.
On Aug. 3, the State Water Resources Control Board voted 5 to 0 to issue an “emergency curtailment” order for the Sacramento-San Joaquin Delta watershed. Last week the order was submitted to the state’s Office of Administrative Law, which is likely to approve it.
The watershed covers about 40% of the state, stretching roughly from Fresno to Oregon, and is California’s largest source of surface water. About 5,700 holders of water rights, largely in agriculture and business, will be affected by the reduction in water access. Although many farms have already drawn most of the water they need for the season, the board’s move was a sign that ancestral water rights won’t be a guarantee of actual water if drought persists.
Read the court decisionRead the full story...Reprinted courtesy of
Francis Wilkinson, Bloomberg
Leaning San Francisco Tower Seen Sinking From Space
November 30, 2016 —
The Associated Press (Jocelyn Gecker) – BloombergSan Francisco (AP) -- Engineers in San Francisco have tunneled underground to try and understand the sinking of the 58-story Millennium Tower. Now comes an analysis from space.
The European Space Agency has released detailed data from satellite imagery that shows the skyscraper in San Francisco's financial district is continuing to sink at a steady rate — and perhaps faster than previously known.
The luxury high-rise that opened its doors in 2009 has been dubbed the Leaning Tower of San Francisco. It has sunk about 16 inches into landfill and is tilting several inches to the northwest.
A dispute over the building's construction in the seismically active city has spurred numerous lawsuits involving the developer, the city and owners of its multimillion dollar apartments.
Engineers have estimated the building is sinking at a rate of about 1-inch per year. The Sentinel-1 twin satellites show almost double that rate based on data collected from April 2015 to September 2016.
Read the court decisionRead the full story...Reprinted courtesy of
Bloomberg
Business Risk Exclusions Bar Coverage for Construction Defect Claims
August 27, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe homeowners' assigned claims against the general contractor's insurer were barred by business risk exclusions in the CGL policies. W. Heritage Ins. Co. v. Cannon, 2014 U.S. Dist. LEXIS 101382 (E.D. Wash. July 24, 2014).
The Cannons contracted with Cook Custom Homes to build their home. Cook never hired a soil engineer. The lot was excavated and the basement foundation was back-filled. When the Cannons moved in, they noticed cracks throughout the foundation, basement slab, ceilings and driveway. The Cannons' home was rendered uninhabitable.
The Cannons sued Cook. Cook agreed to a confession of judgment and assignment of its rights against Western Heritage, who defended Cook under a reservation of rights. Western Heritage filed an action for declaratory judgment.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Corrective Action Protest Grounds for GSA Schedule Federal Construction Contractors
September 09, 2024 —
Marissa L. Downs - The Dispute ResolverA contract awarded, protested, terminated, appealed, then reinstated. It’s no secret that federal construction procurements are plagued with uncertainty. From delays, constructive suspensions, compromised supply chains, the litigation-laden critical path method, and the mandate for all construction materials used in federally funded projects for infrastructure to be produced in the United States under the Build America, Buy America Act (BABAA) (to name just a few traditional and emerging favorites), just one of these issues could fill the rest of anyone’s month with substantive research. To add one more, which is entirely unique to bid protests, federal contractors–including construction contractors–listed in a General Service Administration (GSA) Schedule may have new grounds to have a contract award reinstated that was terminated by a federal agency pending a GAO decision.
GAO Protest
An initial GAO protest filed by Deloitte & Touche LLP (Deloitte) argued that the National Geo-Spatial Intelligence Agency (Agency) wrongfully made an award to Kearney & Company, P.C. (Kearney) when the Agency: (1) improperly evaluated quotes; and (2) failed to conduct a proper best-value tradeoff analysis. At issue was a competed task order with Kearney under a GSA FSS multiple-award contract. Before the GAO issued an opinion, however, it held an unrecorded predictive-outcome conference with Deloitte and Kearney where the only mutual consensus was the likely ineligibility of all offerors for the relevant award. The Agency subsequently elected to take corrective action, terminating Kearney’s contract award for convenience, amending the solicitation to avoid issues (including undisputed issues) addressed in the GAO protest. After the Agency adopted their corrective action, the GAO protest was dismissed as academic and moot.
Read the court decisionRead the full story...Reprinted courtesy of
Marissa L. Downs, Laurie & Brennan, LLPMs. Downs may be contacted at
mdowns@lauriebrennan.com
Consulting Firm Indicted and Charged with Falsifying Concrete Reports
August 17, 2011 —
CDJ STAFFThe New York Times reports that a company paid to inspect concrete at major public works projects in New York has been charged with falsifying results. They had been hired by the city three years ago after their predecessor was found to have falsified results.
According to the Times, investigators found nothing legitimate in nearly three thousand reports. The owner and five employees of American Standard Testing and Consulting Laboratories have been indicted on twenty-nine counts, including charges under New York’s racketeering law. Prison terms could be up to twenty-five years.
Prior to the city’s contract with American Standard, the city employed a firm called Testwell. Testwell was found in 2008 to have falsified its test results.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Bill would expand multi-year construction and procurement authority in Georgia
March 06, 2023 —
David R. Cook Jr. - Autry, Hall & Cook, LLPA bill introduced in the General Assembly would modify the authority of state and local governments, as well as school systems, to enter multi-year contracts for construction and procurement. In many prior posts, we have addressed state and local governments’ authority to enter guaranteed energy savings performance contracts and multi-year contracts.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hall & Cook, LLPMr. Cook may be contacted at