The “Your Work” Exclusion—Is there a Trend against Coverage?
September 10, 2014 —
Craig Martin – Construction Contractor AdvisorTwo more courts have weighed in on the “your work” exclusion in commercial general liability (CGL) policies, finding that contractors did not have coverage for work performed improperly. These cases highlight that whether you have coverage for poor workmanship will depend on the state’s law applied. It now appears that if you are in South Carolina or Massachusetts, you will not have coverage.
The South Carolina case, Precision Walls, Inc. v. Liberty Mutual Fire Insurance Company, involved a subcontractor hired to tape insulation. After taping the insulation, a brick veneer was installed on the exterior. During the brick installation, the mason reported that the tape was losing its adhesion and the subcontractor was instructed to repair the problem. In order to access the tape, portions of the brick veneer had to be removed and re-installed. The subcontractor then sought coverage for the costs associated with repairing the tape.
The insurer denied coverage and the subcontractor sued its insurer. The court ruled in favor of the insurer, finding that the defective tape was “your work” because it was “material furnished in connection” with the subcontractor’s work. The policy specifically excluded from coverage damage to property caused by “your work”. Thus, there was no coverage for the subcontractor.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Practical Pointers for Change Orders on Commercial Construction Contracts
December 31, 2014 —
John E. Bowerbank - Newmeyer & DillionConstruction projects pose unique challenges, including keeping costs within budget, meeting project deadlines, and coordinating the work of numerous contractors and subcontractors in the wake of inevitable design revisions and changes to the plans. Anticipating potential project challenges and negotiating contract provisions before commencing work on a project is critical for all parties. Careful planning should reduce the number of contract disputes. This, in turn, can facilitate the completion of a project within budget and on schedule.
“Changes” Clauses in Construction Contracts
Most commercial construction contracts have a clause addressing changes to the contract. A “changes” clause typically requires the mutual agreement of the parties on the scope of any modifications to the contract, as well as the effect on the contract price and timeframe for the work to be performed. This results in what is generally referred to as a “change order.” Many projects have a large number of change orders, which can result in significant cost overruns and delays to the project if the contract contains a complicated change order process. Therefore, in order to minimize cost overruns and project delays, it is crucial to keep the change order process as simplified and streamlined as possible.
In the most basic terms, change orders memorialize modifications to the original contract, and typically alter the contract's price, scope of work, and/or completion dates. A typical change order is a written document prepared by the owner or its design professional, and signed by the owner, design professional, and affected contractors and subcontractors. An executed change order indicates the parties’ agreement as to what changes are taking place, including approval for additional costs and schedule impacts.
While the reasons for change orders and the parties initiating them may vary, all change orders have one feature in common. Effective change orders alter the original contract and become part of the contract. Therefore, from a legal standpoint, change orders must be approached with the same caution and forethought as the original contract.
Practice Pointers for Change Orders
In light of the foregoing, some practice pointers for change orders in commercial construction contracts are as follows:
- Carefully Negotiate and Draft Change Order Provisions in the Original Contract.
A carefully negotiated and drafted “changes” clause that accounts for “unexpected circumstances” or “hidden conditions” can protect the parties from downstream costly disputes.
- Immediately Address Changes by Following the Change Order Process, Including Obtaining Necessary Signatures.
Regardless if you are an owner, general contractor or subcontractor, you should address any proposed change order immediately. Even if a decision maker gives “verbal” approval to go ahead with changed work, the work should not proceed without following the change order process in the original contract. This includes making sure to obtain any necessary signatures for the change order, if at all possible.
- Analyze the Plans and Specifications to Determine Whether “Changes” are Within the Scope of the Original Contract, or Whether They are Extra Work.
Prior to entering an original contract, it is imperative that the parties review the plans and specifications for ambiguities regarding work included in the original contract, versus potential extra work that would require a change order. This is important because a careful review of the plans and specifications sometimes reveals that work believed to be a change order is, in fact, original work, or vice versa.
- Make Sure Requests and Approvals for Change Orders are Done by an Authorized Representative.
When a party requests or gives its approval to a change order, it is important to confirm the request or approval came from an authorized representative.
- Avoid Vague and Open-Ended Change Orders.
Indeed, the vaguer a change order, the more likely it can lead to a dispute. Vague and open-ended change orders, including change orders that provide for payment on a time and materials basis, can be difficult for an owner to budget and schedule. This can lead to disputes as to cost and/or time extensions.
- Oral Assurances for Payment Without a Signed Change Order May Not Be Recoverable.
When a party provides verbal assurances to another party for extra work without following the change order process, there is a much higher likelihood that disputes will occur. Although there is case law that may allow a contractor to recover for extra work in private contracts based on oral promises, the parties should avoid placing themselves in such a legal position. Notably, in public contracts, a contractor may not be able to recover for any extra work without a signed changed order, even with verbal assurances of payment from the owner.
About the Author:
John E. Bowerbank, Newmeyer & Dillion
Mr. Bowerbank is a partner in the Newport Beach office and practices in the areas of business, insurance, real estate, and construction litigation. You can reach John at john.bowerbank@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
The Four Forces That Will Take on Concrete and Make Construction Smart
September 17, 2018 —
Massimiliano Moruzzi - Construction ExecutiveWhen it comes to building a bridge, what prevents it from having the most enduring and sustainable life span? What is its worst enemy? The answer is, simply, the bridge itself—its own weight.
Built with today’s construction processes, bridges and buildings are so overly massed with energy and material that they’re inherently unsustainable.
While concrete is quite literally one of the foundations of modern construction, it’s not the best building material. It’s sensitive to pollution. It cracks, stainsand collapses in reaction to rain and carbon dioxide. It’s a dead weight: Take San Francisco’s sinking, leaning Millennium Tower as an example.
Reprinted courtesy of
Massimiliano Moruzzi, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Breach Of Duty of Good Faith And Fair Dealing Packaged With Contract Disputes Act Claim
March 27, 2023 —
David Adelstein - Florida Construction Legal UpdatesAn interesting opinion on a motion to dismiss came out of the United States Court of Federal Claims dealing with the claim that the government breached its duty of good faith and fair dealing in administering the prime contract. The contractor’s argument was that the government breached its duty of good faith and fair dealing by denying the contractor’s claim under the Contract Disputes Act (CDA). This was a creative claim and argument that deserves consideration because it tied in the contracting officer’s denial of the CDA claim for additional money with a breach of the duty of good faith and fair dealing.
In this case, Aries Construction Corp. v. U.S., 2023 WL 2146598 (Fed. Cl. 2023), a prime contractor was hired for a water pipeline construction project. The contractor encountered unexpected difficult site conditions that required additional equipment and labor. The contractor informed the contracting officer and alleged it was instructed to proceed with the additional equipment and labor. The contractor submitted a claim under the CDA but the contracting officer denied the claim. The contractor pursued the claim in the United States Court of Federal Claims arguing the government breached the contract and, of interest, breached its duty of good faith and fair dealing.
The government moved to dismiss the breach of good faith and fair dealing claim arguing that besides failing to state a cause of action the Court of Federal Claims had no jurisdiction because the breach of the duty of good faith and fair dealing was not properly presented to the contracting officer under the CDA. The Court of Federal Claims denied the government’s motion.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
How Philadelphia I-95 Span Destroyed by Fire Reopened in Just 12 Days
July 24, 2023 —
James Leggate - Engineering News-RecordLess than two weeks after a tanker truck crash and fire destroyed an Interstate-95 bridge in northeast Philadelphia, the highway reopened to traffic on a temporary road surface June 23. The hastened work to reopen the highway, which has an average daily traffic count of nearly 160,000 vehicles, including about 13,000 trucks, was the result of collaboration between contractors, material suppliers and union workers with local, state and federal officials, Pennsylvania Gov. Josh Shapiro (D) said.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Court Throws Wet Blanket On Prime Contractor's Attorneys' Fees Request In Prompt Payment Case
September 03, 2015 —
Steven M. Cvitanovic & Abigail E. Lighthart – Haight Brown & Bonesteel LLPPrompt payment penalty cases do not come around very often, but when they do, there is bound to be fireworks.
In James L. Harris Painting & Decorating, Inc. v. West Bay Builders, Inc., et al. (No. C072169, filed 8/27/15), the California Court of Appeal for the Third Appellate District upheld the trial court's discretion to not award prevailing party attorneys' fees to the party who won a prompt payment dispute. California Business and Professions Code §7108.5 and Public Contract Code §§7107 and 10262 are the mechanisms for obtaining prompt payment relief in California. As shown by the outcome, it is possible to win and lose at the same time.
West Bay Builders, Inc. (“West Bay”) was the prime contractor on a school construction project for Stockton Unified School District. West Bay entered into a subcontract agreement with James L. Harris Painting & Decorating, Inc. (“Harris”) on the project. During construction there were disagreements between West Bay and Harris regarding the contractual scope of work, and Harris performed work it believed was outside the contract, believing it would be paid for the additional work. After West Bay refused to pay for the additional work, Harris left the project, and West Bay hired another subcontractor to complete the work.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
Abigail E. Lighthart, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com
Ms. Lighthart may be contacted at alighthart@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Powering Goal Congruence in Construction Through Smart Contracts
February 22, 2021 —
Michael Matthews - Construction ExecutiveThe $814 billion U.S. commercial construction market requires a unique assembly of designers, contractors, subcontractors and suppliers to work together in a highly orchestrated manner to make sure that the right labor, material, equipment, tools and information all comes together at the right place and time. Alignment and coordination between companies is critical for a project to be successful; completed safely, on time, on budget and resulting in an asset that performs as designed.
Yet the industry is slowed by an operating model bogged down by transactional and informational barriers that destroys value across the construction supply chain. Companies are connected through contracts and purchase orders that are undercut by mistrust that yields adversarial relationships and conflicting priorities that result in restricted transparency, elongated payment cycles and an abundance of resource-sucking reconciliations, audits and disputes.
With margins already razor thin, company protectionism cascades down from owners, developers and operators to contractors, subcontractors and suppliers with each player focused on optimizing their piece at the expense of the whole. Perhaps this is part of the reason 98% of megaprojects experience cost overruns or delays, 95% of projects are unable to meet even one business objective; and 70% of all construction projects are not completed within 10% of the proposed budget.
Reprinted courtesy of
Michael Matthews, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
State Supreme Court Cases Highlight Importance of Wording in Earth Movement Exclusions
June 21, 2017 —
Hannah E. Austin - Saxe Doernberger & Vita, P.C.In Erie Insurance Property and Casualty Company v. Chaber, the West Virginia Supreme Court recently
held that an insurance policy’s earth movement exclusion was unambiguous and applied to both manmade
and natural earth movement. The Court also found that a narrow “ensuing loss” exception to the exclusion
that provided coverage for glass breakage resulting from earth movement could not be extended to cover the
entire loss.
The Erie Insurance Property and Casualty Company (Erie) insured five commercial buildings owned by
Dmitri and Mary Chaber. One of the properties was damaged by a landslide, and the Chabers filed a claim
with Erie. Erie asserted that the loss was excluded from coverage because the policy excluded coverage for
losses caused by earth movement, which was defined to include earthquakes, landslides, subsidence of
manmade mines, and earth sinking (aside from sinkhole collapse), rising or shifting. The exclusion stated
that it applied “regardless of whether any of the above . . . is caused by an act of nature or is otherwise
caused,” and also contained an anti-concurrent causation clause. However, there was an exception for glass
breakage caused by earth movement.
Read the court decisionRead the full story...Reprinted courtesy of
Hannah E. Austin, Saxe Doernberger & Vita, P.C.Ms. Austin may be contacted at
hea@sdvlaw.com