When OSHA Cites You
April 22, 2024 —
Michael Metz-Topodas - Construction ExecutiveWith the strong bonds that form among construction project teams, workers looking out for each other helps keep safety foremost in everyone’s mind. But sometimes, even the very best intentions alone can’t prevent an occasional misstep—a forgotten hard hat, a sagging rope line—which can and often does result in an OSHA citation. These regulatory reminders can bring unfortunate consequences: penalties, higher insurance premiums, potential worker injury claims, loss of bidding eligibility, loss of reputation and even public embarrassment, because citations are published on OSHA’s website.
Due to citations’ adverse effects, contractors have incentives to minimize them. They can do this by asserting available defenses, because a citation is only an alleged violation, not a confirmed one. But making defenses available begins well before a citation is issued, well before OSHA arrives to a construction site and well before a violation even occurs. Instead, contractors’ ongoing safety programs should incorporate the necessary measures to preserve OSHA citation defenses in three key areas: lack of employee exposure, lack of employer knowledge and impossibility.
EMPLOYEE EXPOSURE
To sustain a citation against an employer, OSHA must not only identify an applicable standard that the company violated but also show that the violation exposed employees to hazards and risk of injury. Absent evidence of actual exposure, OSHA often makes this showing by asserting that performing job functions necessarily exposes employees to the cited hazard.
Reprinted courtesy of
Michael Metz-Topodas, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Metz-Topodas may be contacted at
michael.metz-topodas@saul.com
Federal District Court Declines Invitation to Set Scope of Appraisal
January 18, 2021 —
James M. Eastham - Traub LiebermanIn Mt. Hawley Ins. Co. v. Harrods Eastbelt, Ltd., No. CV H-20-2405, 2020 WL 7632250 (S.D. Tex. Dec. 22, 2020), the United States District Court for the Southern District of Texas addressed a request to set the scope of an appraisal by requiring the appraisers to use a specific format for the appraisal. At issue was a claim for damages to three insured buildings allegedly damaged during Tropical Storm Imelda. The insurer had denied coverage based on the asserted lack of wind-created openings as required for coverage under the policy. Rather, the insurer took the position that the interior leaks were caused by a number of excluded causes including long-term weathering, wear and tear, age-related deterioration, ponding, and long-term leaks.
In response to the denial of coverage, the insured invoked the appraisal provision of the policy which provided, among other things, that the “appraisers will state separately the value of the property and amount of loss.” Despite the language of the appraisal provision, the Insurer sought an order requiring the appraisers to state the amount of loss separately for each portion of the property in dispute and for each major building component including separate amounts of loss for roofs, exterior walls, windows, and interior water damage.
Read the court decisionRead the full story...Reprinted courtesy of
James M. Eastham, Traub LiebermanMr. Eastham may be contacted at
jeastham@tlsslaw.com
Dealing with Abandoned Property After Foreclosure
April 10, 2019 —
Bremer Whyte Brown & O'Meara LLPCalifornia landlords must follow very specific steps before disposing of property that is clearly abandoned, left on real estate which has been the subject of court proceedings such as eviction or foreclosure, or otherwise left behind. Following the statutory procedures relating to abandoned property protects landlords from potential liability for an improper “conversion.”
Former tenants/owners and others “reasonably believed” to be owners of the apparently abandoned personal property must be given proper written notice of the right to reclaim the abandoned property. The tenant is presumed to be the owner of any “records” remaining on the property. The California Code of Civil Procedure provides a template for such notice. The notice to be provided to former tenants/owners must be in “substantially” the same form provided in the California Code of Civil Procedure and must contain the following information:
- A description of the abandoned property in a manner reasonably adequate to permit the owner of the property to identify it;
- The location where the tenant can claim the property;
- The time frame that the tenant has to claim the property. The date specified in the notice shall be a date not less than fifteen (15) days after the notice is personally delivered or, if mailed, not less than eighteen (18) days after the notice is deposited in the mail;
- A statement that reasonable storage costs will be charged to the tenant/owner and the tenant/owner must pay those costs before claiming the property; and
Read the court decisionRead the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara LLP
Home Builder Doesn’t See Long Impact from Hurricane
November 07, 2012 —
CDJ STAFFNo one needs to tell Toll Brothers about the impact of Hurricane Sandy. The Wall Street Journal reports that the home building company lost power as a result of the storm. Martin Connor, the company’s CFO, told the Journal that he did not expect the hurricane to have a big effect on sales. Luckily for the company, many of its large projects are either sufficiently completed to provide shelter or too early in the process to be affected by the storm. “This type of weather event has limited impact on the market. It may move settlements later, and may defer people a weekend or two until they go out shopping. But it doesn’t have a long impact.”
Read the court decisionRead the full story...Reprinted courtesy of
Ensuring Efficient Arbitration of Construction Disputes Involving Mechanic’s Liens
February 18, 2020 —
Robert G. Campbell & Trevor B. Potter - Construction ExecutiveThere may be tension between the enforcement of statutory mechanic’s lien claims when a contractual dispute resolution provision calls for arbitration. Once the parties are in arbitration, it may not be clear whether the arbitrator has authority to make factual determinations regarding amount and validity of mechanic’s liens, and whether courts are bound by these determinations. This uncertainty stems from the fact that in most states a mechanic’s lien can only be enforced by a court of competent jurisdiction. Indeed, many mechanic’s liens statutes define foreclosure as a “judicial process,” and courts generally have exclusive jurisdiction to issue orders foreclosing on real property1.
The risk for contractors and owners is that they will spend time and money re-litigating factual issues related to proving elements of a mechanic’s lien claim, including the proper lien amount, timeliness and other prerequisites. Without a clear understanding of what issues and elements are arbitrable, the parties run the risk that an arbitrator will rule on certain elements only to find out during post-arbitration lien foreclosure proceedings that the arbitrator lacked authority to make determinations on those elements. Questions therefore arise whether a court will enforce the arbitrator’s determinations and whether the parties must relitigate mechanic’s lien issues creating a further risk of inconsistent rulings.
These risks can be minimized through arbitration provisions which address these issues, express requests in arbitration demands and by ensuring that arbitration awards contain explicit determinations of mechanic’s liens issues.
Reprinted courtesy of
Robert G. Campbell & Trevor B. Potter, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Potter may be contacted at tpotter@coxcastle.com
Mr. Campbell may be contacted at rcampbell@coxcastle.com
Read the court decisionRead the full story...Reprinted courtesy of
Shutdowns? What A Covid-19-Safe Construction Site Looks Like
April 20, 2020 —
ENR Editors - Engineering News-RecordThere’s no end to published opinions about construction project shutdowns where the widely different types of jobsites are reduced to a single Dickensian nightmare crying out to be closed during this COVID-19 pandemic.
ENR Editors
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Pensacola Bridge Halted Due to Alleged Construction Defects
July 21, 2018 —
David Suggs – Bert L. Howe & Associates, Inc.The Pensacola News Journal reported that cracks were discovered again in the Pensacola Bay Bridge, which caused construction of said bridge to be halted once more: “Cracks found in a portion of the concrete in the Pensacola Bay Bridge project have twice halted construction in the last several months, raising concerns about oversight and disclosure from the state, particularly in light of the Miami bridge collapse earlier this year.”
The Florida Department of Transportation stated “that the cracks were found during a routine visual inspection of newly placed concrete in March,” according to the Pensacola News Journal. The $400 million project began in 2017 and was scheduled to be completed by 2020.
Read the court decisionRead the full story...Reprinted courtesy of
Critical Materials for the Energy Transition: Of “Rare Earths” and Even Rarer Minerals
September 12, 2022 —
Robert A. James, Ashleigh Myers, Shellka Arora-Cox & Amanda G. Halter - Gravel2Gavel Construction & Real Estate Law BlogAs the world pursues ambitious net-zero carbon emission goals, demand is soaring for the critical materials required for the technologies leading the energy transition. Lithium may be the most well-known of these inputs due to its usage in batteries for vehicles and consumer electronics, but roughly 50 other minerals are central to energy transition technologies. During the coming years, producers, manufacturers and end-users will be increasingly exposed to the roles played by “rare earth” elements (roughly, atomic numbers 57 to 71), platinum group metals, and other materials.
The reasons for this heightened interest are simple—even if the underlying environmental, political and technological forces at play are complex:
- Lower-carbon technologies use different materials than carbon-intensive technologies.
The mineral requirements of power and mobility systems driven by renewable, nuclear, hydrogen and fusion energy are profoundly different from those forming the backbone of fossil fuel systems. Minerals such as lithium, nickel, copper, cobalt, and rare earth elements are vital for electric vehicles (EVs), batteries, fuel cells, electricity grids, wind turbines, smart devices, and many other essential and proliferating civilian and military technologies. For example, an offshore wind plant needs 13 times more mineral resources than a gas power plant of a similar size.
Reprinted courtesy of
Robert A. James, Pillsbury,
Ashleigh Myers, Pillsbury,
Shellka Arora-Cox, Pillsbury and
Amanda G. Halter, Pillsbury
Mr. James may be contacted at rob.james@pillsburylaw.com
Ms. Myers may be contacted at ashleigh.myers@pillsburylaw.com
Ms. Arora-Cox may be contacted at shellka.aroracox@pillsburylaw.com
Ms. Halter may be contacted at amanda.halter@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of