Christopher G. Hill – Construction Law MusingsAfter the last two weeks’ analyses of a couple of big construction decisions that came out recently, I thought I’d keep this week’s post practical and short for those that are not construction lawyers. So without further ado, here is a short checklist of the top things (aside from calling their local experienced construction attorney) a construction subcontractor should do or look for when reviewing a construction contract from a general contractor (and for a couple of these that a general contractor can look for in its prime contract).
- ALWAYS get a copy of the Prime Contract between the Owner and the General Contractor. This contract will contain terms that will “flow down” to you through the incorporation clause that almost every subcontract contains. You can’t do much to change these terms, but you will need to know them as the job progresses.
- READ every provision of the subcontract. I know this sounds simple, but not all subcontracts hide the red flags in the same places. Remember the details of a subcontract can sink you later if you aren’t prepared.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
3M PFAS Water Settlement Could Reach $12.5B
July 16, 2023 —
Jim Parsons, Debra K. Rubin3M Co. has offically moved to settle claims of fouled drinking water stemming from the use of so-called “forever chemicals,” striking a deal with U.S. public water systems that could total $10.5 billion to $12.5 billion over 13 years, it said in a June 22 federal filing.
Reprinted courtesy of
Jim Parsons, Engineering News-Record and
Debra K. Rubin, Engineering News-Record
Ms. Rubin may be contacted at rubind@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Leonard Fadeeff v. State Farm General Insurance Company
September 21, 2020 —
Michael Velladao - Lewis BrisboisIn Fadeeff v. State Farm Gen. Ins. Co., 50 Cal.App.5th 94 (May 22, 2020), the California Court of Appeal reversed the entry of summary judgment in favor of State Farm General Insurance Company (“State Farm”) in connection with a smoke and soot damage claim made by Leonard and Patricia Fadeeff (the “Fadeeffs”) for damage sustained by their home due to the 2015 Valley Fire. The parties’ dispute arose out of the Valley Fire, which took place in Lake County, California. The Fadeeffs’ home was located in Hidden Valley Lake.
The Fadeeffs submitted a claim to State Farm under their homeowners policy. Initially, after an adjuster inspected the home and noted that it was “well maintained” with no apparent maintenance issues, State Farm made a series of payments and arranged for ServPro to clean the smoke and soot damage. Subsequently, the Fadeeffs retained an independent adjuster and submitted a supplemental claim in the amount of $75,000. State Farm retained a different unlicensed adjuster to investigate the claim and retained expert, Forensic Analytical Consulting Services (FACS) to inspect the Fadeeffs’ home, and another company referred to as HVACi, to inspect the Fadeeffs’ HVAC system.
The independent adjuster used to investigate the Fadeeffs’ supplemental claim failed to follow company guidelines in connection with using experts, which required specific questions to be addressed by the expert. In addition, FACS only took surface samples of the walls in the Fadeeffs’ home. Ultimately, the reports prepared by FACS and HVACi concluded that no additional work was required to remediate the damage sustained by the Fadeeffs’ home. Thereafter, State Farm denied the Fadeeffs’ supplemental claim.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Velladao, Lewis BrisboisMr. Velladao may be contacted at
Michael.Velladao@lewisbrisbois.com
As Recovery Continues, Home Improvement Stores Make Sales
August 27, 2013 —
CDJ STAFFNeed another sign of the housing recovery? Lowe’s stock price is up. Bloomberg News reports that the home-improvement retailer rose by 88 cents a share in the last quarter. Analysts had predicted gains of 79 cents a share, and the same quarter last year saw profits of 64 cents a share. The increase in profits come from more purchases and higher spending per purchase. While Lowe’s negotiated some better prices with vendors and dropped some items that weren’t selling, none of the profits came from staff reduction; the retailer actually increased staffing.
Home Depot, the largest such chain (Lowe’s is number 2), also saw profits that exceeded analysts’ projections. They, too, have decided to focus on assisting customers. Their increase in profits was attributed to greater spending by contractors and homeowners.
Read the court decisionRead the full story...Reprinted courtesy of
How Technology Reduces the Risk of Façade Defects
March 20, 2023 —
Ori Aphek - Construction ExecutiveThe shell of the building is an onlooker’s first impression and crafts the architectural aesthetic, but it also plays a crucial role in enabling energy efficiency and protecting against the elements. Because façades are in direct contact with the elements, issues with water intrusion are the most common problem and the costliest to remedy, with anywhere from 30% to 70% of lawsuits related to water intrusion, half of it through the façade. Additionally, improperly installed façades pose significant safety risks because unsecured parts can fall and hit people below.
All these factors contribute to the façade being one of the most complex and costly aspects of a building to construct and inspect, making up 205 of the total project cost. Installing these systems correctly the first time is the most effective way to mitigate these threats. Teams should utilize data-informed technology that ensures plan adherence, reducing risk and avoiding errors during installation.
The Challenges of Façade Installation
Façade installation and subsequent inspection are inherently challenging, particularly for high-rise buildings. When performing post-installation verification manually, inspectors must review every element, joint by joint, window by window, stone by stone and brick by brick, which can take months to complete. Inspections of the entire building system are limited by this process, as inspectors can only access one portion of the building façade at a time and often have to inspect from indoors, on balconies or at the ground level, which doesn’t paint a complete picture. As a result, teams typically only perform spot checks on the façade and are rarely inspected to their fullest. This leaves many installation errors and defects, which serve as ticking bombs for future water intrusion or safety hazards.
Reprinted courtesy of
Ori Aphek, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
What are Section 8(f) Agreements?
July 02, 2018 —
Wally Zimolong – Supplemental Conditions Like many areas of federal labor law, there are different rules for construction industry employers. One major difference is in how employers become unionized. Typically, under Section 9(a) of the National Labor Relations Act, a union becomes a collective bargaining agent of employees only after a majority of employees show support for union representation. In other words, the employees chose whether to be represented by a particular union. However, under Section 8(f) of the NLRA, construction industry employers can choose to become union without any showing of majority support by employees. In fact, construction industry employers don’t need to have any employees at all to sign a “8(f) agreement.” Thus, these agreements have become known as pre-hire agreements.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
LEEDigation: A Different Take
June 22, 2020 —
Christopher G. Hill - Construction Law MusingsThis weeks Guest Post Friday at Musings is a real treat. Sara Sweeney is a registered architect, LEED AP and GreenFaith Fellow in religious environmental leadership. Her 18-year architectural career reflects her passion and commitment to sustainable building design and stewardship of our natural environment. She is the founder of EcoVision LLC, a solutions-based research and consulting firm, grounded in sustainable design practices, environmental stewardship, and building science.
Dude
Every so often I come across a word that drives me nuts. A few years ago it was ‘Dude.’ Lately, it is ‘LEEDigation.’ It’s a new term to “describe green building litigation” coined by Chris Cheatham, a fine person and very knowledgeable attorney in construction law and a LEED AP as well. Per his definition, LEEDigation “could involve disputes arising from green building certification, could arise if a project fails to obtain government incentives or satisfy mandates for green building construction, or could simply result from improperly designed or constructed green building strategies. It all makes sense. So why does it drive me nuts?
Round Peg. Square Hole.
Although I fully understand why the term was coined, such a term keeps us in flat world, that is, the world of conventional design and construction. Designing and building to LEED standards, or rather, just designing and building sustainably in general, whether to meet a third party standard or not, is a different way than what we have been used to. Period. Whereas our conventional way is focused on first costs, and sees the building more as a commodity than the human imprint and legacy on Earth, sustainable design and building is a process which, at its best, considers the economic impacts of NOT building responsibly. It is a more holistic way of building and balances long-term costs and implications with short term costs.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Eyerly may be contacted at
te@hawaiilawyer.com
Brazil Builder Bondholders Burned by Bribery Allegations
October 22, 2014 —
Paula Sambo and Sabrina Valle – BloombergBrazil’s biggest construction companies are leaving bondholders with losses in the wake of allegations they bribed Petroleo Brasileiro SA to win contracts.
Queiroz Galvao SA’s $700 million of notes due 2019 have dropped 2.5 percent since Oct. 9, when the Department of Justice made available video in which former Petrobras head of refining Paulo Roberto Costa alleged that builders formed a cartel to overcharge for projects and divert money to politicians. OAS SA’s $875 million of 2019 notes have slumped 1.9 percent in that span, versus a 0.1 percent loss for emerging markets.
Ms. Sambo may be contacted at psambo@bloomberg.net; Ms. Valle may be contacted at svalle@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Paula Sambo and Sabrina Valle, Bloomberg