Michigan Court Waives Goodbye to Subrogation Claims, Except as to Gross Negligence
March 13, 2023 —
Lian Skaf - The Subrogation StrategistIn Ace American Insurance Company, et. al. v. Toledo Engineering Co., Inc., et. al., No. 18-11503, 2023 U.S. Dist. LEXIS 15222 (Ace American), the United States District Court for the Eastern District of Michigan determined whether insurers could pursue their subrogation claims against the defendants despite a waiver of subrogation in each of the contracts the insured had with the respective defendants. Based on the language of the contracts and the circumstances leading up to the loss, the court held that the insurers could not pursue their subrogation claims – other than their claims for gross negligence – due to waivers of subrogation in the applicable contracts.
In Ace American, the insured, Guardian Industries, LLC (Guardian), retained Toledo Engineer Co., Inc. (TECO) and Dreicor, Inc. (Dreicor) to renovate a glass furnace in the insured’s glass manufacturing plant. Guardian and TECO entered into a contract on December 6, 2016. Guardian and Dreicor entered into a contract on September 29, 2013, that the parties later updated on June 3, 2016. Both defendants began work on the project in the spring of 2017 and were finished with the portion of the work known as the “Cold Tank Repair” prior to the loss.
On June 3, 2017, there was an explosion and fire at the plant that caused significant property damage. The plaintiff insurers (Plaintiffs) made payments in the amount of $80 million and became subrogated to its insured’s rights. Plaintiffs then initiated this action.
Read the court decisionRead the full story...Reprinted courtesy of
Lian Skaf, White and Williams LLPMr. Skaf may be contacted at
skafl@whiteandwilliams.com
No Coverage for Property Damage That is Limited to Work Completed by Subcontractor
April 25, 2012 —
Tred R. Eyerly - Insurance Law HawaiiThe issue before the 11th Circuit was whether, under Florida law, a general contractor had coverage for a property damage claim limited to the defective work performed by a subcontractor, and not affecting any other portion of the project. The court found no coverage in Amerisure Mut. Ins. Co. v. Auchter Co., 2012 U.S. App. LEXIS 5412 (11th Cir. March 15, 2012).
Amelia Island Company contracted with Auchter Company, a general contractor, for construction of an inn and conference room. Auchter subcontracted with Register Contracting Company to install the Inn’s roof. Pursuant to the Florida Building Code, installation of the roof required that it be able to withstand 110 m.p.h. winds.
Register completed installing the roof tiles in January 1998. Beginning in 2002, the tiles began dislodging from the roof. During the 2004 hurricane season, three hurricanes caused more tiles to come off the roof. Some of these tiles hit other tiles, cracking them.
In 2006, the parties went to arbitration over the costs of repairs for the roof.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
Title II under ADA Applicable to Public Rights-of-Way, Parks and Other Recreation Areas
June 29, 2017 —
Richard E. Morton - Haight Brown & Bonesteel LLPPlaintiff Ivana Kirola, who suffers from cerebral palsy, sued the City and County of San Francisco, in a class action contending certain public areas, including rights-of-way, pools, parks and other recreation areas, did not meet the mandate of Title II of the American With Disabilities Act (Kirola v. City and County of San Francisco, 9th Circuit Court of Appeals, No. 14-17521, 2017 DJDAR 5982). Title II provides that no qualified individual with a disability “shall, by reason of such disability, be excluded from participation in or be denied the benefits of the services, programs, or activities of a public entity, or be subjected to discrimination by any such entity.”
Title II’s implementing regulations mandate that each facility constructed after January 26, 1992 be “readily accessible to and usable by individuals with disabilities.” And, for each facility “altered after January 26, 1992,” the altered portion must, “to the maximum extent feasible,” be likewise accessible. The Federal Architectural and Transportation Barriers Compliance Board creates nonbinding Americans With Disabilities Act Accessibility Guidelines (ADAAG) to ensure compliance with Title II, and that the Department of Justice (DOJ) adopt its own binding regulations, consistent with the ADAAG standards. Here, the District Court interpreted ADAAG standards as not applying to public rights-of-way, parks, and playground facilities. The District Court concluded that none of Kirola’s experts were reliable in their interpretation of the standards and how the standards applied to the public rights-of-way, etc. Conversely, the District Court concluded that all of the city’s experts were reliable. It thus disregarded and discarded every ADAAG violation identified by Kirola’s experts, accepting only the small number of violations identified by the city’s experts.
Read the court decisionRead the full story...Reprinted courtesy of
Richard E. Morton, Haight Brown & Bonesteel LLPMr. Morton may be contacted at
rmorton@hbblaw.com
US Homes Face Costly Retrofits for Induction Stoves, EV Chargers
May 20, 2024 —
Kendra Pierre-Louis - BloombergBuyers of new homes in the US may find themselves saddled with electrical systems better suited to the 20th century than the 21st.
The International Code Council, which sets model construction standards for new homes, was expected to include building electrification measures in its 2024 energy code on March 20. But following appeals lodged by industry groups, the ICC board moved the measures to the code’s appendices, effectively making them optional, as first reported by the Huffington Post.
If new homes aren’t wired for increasing power needs from electric appliances and car chargers, it will bump the effort and cost of making such upgrades onto homeowners — a deterrent to going electric. Energy efficiency advocates say this could slow the pace of the energy transition, costing both jobs and the planet.
Read the court decisionRead the full story...Reprinted courtesy of
Kendra Pierre-Louis, Bloomberg
Gordie Howe Bridge Project Team Looks for a Third Period Comeback
September 26, 2022 —
Jeff Yoders - Engineering News-RecordThe late Detroit Red Wings hockey great Gordie Howe was beloved in his native Canada and in his adopted U.S. home. A new international bridge connecting both places is trying to create similar goodwill for border traffic, but the project’s public-private partnership team and the Canadian government authority it is working for will have to join together to shift lines and mount a comeback in the third period of its construction.
Reprinted courtesy of
Jeff Yoders, Engineering News-Record
Mr. Yoders may be contacted at yodersj@enr.com
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
COVID-19 Could Impact Contractor Performance Bonds
March 30, 2020 —
Ben Williams & MG Surety - Construction ExecutiveAs COVID-19 continues to expand around the United States and the world, it may only be a matter of time before U.S. construction projects are affected by the virus. Performance bonds guarantee that a project will be completed by a contractor according to the contract. However, what if a contractor cannot complete a project on time due to widespread disease? What, if any, impact could the virus have on a contractor’s surety bond program?
Risk Factors
Several risks associated with the virus could trigger a performance bond claim.
1. Materials. The Chinese account for a large supply of construction materials, including steel, copper, cabinetry, etc. An inability to obtain these materials could significantly delay or stop a project all together. Even if a contractor is able to obtain them from other sources, it may be at a significantly higher cost than they put into the bid.
2. Labor. There is already a shortage of qualified labor in the construction industry. Additionally, construction already lends itself to the spreading of viruses; workers are often in close proximity, handling common materials, and they may not have an easily accessible place to wash their hands. Furthermore, even though many now have paid sick leave, there is often pressure not to use it. These things could magnify the labor shortage and make it difficult to complete projects on time.
3. Safety. Finally, the world is having a serious shortage of respirators. Because of widespread panic, many people have been purchasing N95 respirators—so much that the Surgeon General has asked people to stop buying them. It has created a shortage for people who really need them, like contractors. If contractors can’t get these safety masks, certain trades will either be unable to work, or risk continuing the project without masks, which would endanger workers and open them up to OSHA penalties.
Reprinted courtesy of
Ben Williams and MG Surety, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Williams may be contacted at
benw@mgsuretybonds.com
Recent Regulatory Activity
October 25, 2021 —
Anthony B. Cavender - Gravel2GavelSelected federal regulatory actions taken or proposed by several federal agencies, including the Environmental Protection Agency:
EPA Actions.
On September 15, 2021, EPA’s Water Office issued a memo rescinding a January 2021 guidance document that purported to provide the regulatory community with EPA’s understanding of the Supreme Court’s Clean Water Act ruling in the case of County of Maui v. Hawaii Wildlife Fund. That case involved a discharge of pollutants to groundwater which eventually made their way to the Pacific Ocean. Was an NPDES permit required to authorize this discharge, which was not initially made to a navigable body of water? The text of the Clean Water Act provided little guidance, and the matter has become very controversial. The Court held that if the discharge was the “functional equivalent” of a direct discharge, a permit may be required, and the Court described some factors that could influence a determination that there was the functional equivalent of a direct discharge. However, EPA has rescinded the January 2021 guidance, opining that EPA’s earlier analysis was inconsistent the Court’s opinion, and that the guidance was issued without proper deliberation within EPA or with its federal partners. Until new guidance is prepared, EPA will continue to apply “site-specific, science-based evaluations” to resolve these questions. On October 1, 2021, EPA released its “Climate Adaption Action Plan.” Briefly, EPA will take steps to ensure that its programs and policies consider current and future impacts of climate change and how the impacts disproportionately affect certain underserved or environmental justice communities. The agency’s air and water quality programs, contaminated sites activities and chemical safety and pollution prevention programs will be analyzed to determine their impact. Also on October 1, 2021, EPA released its draft FY 2022-2026 Strategic Plan to protect health and the environment. The plan, essentially an internal directive to all offices and regions, reflects a new “foundational principle”—to advance justice and equity by taking on the climate crisis and taking decisive action to advance civil rights and environmental justice.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Washington Trial Court Narrows Definition of First Party Claimant, Clarifies Available Causes of Action in Commercial Property Loss Context
January 04, 2021 —
Kathleen A. Nelson & Jonathan R. Missen - Lewis BrisboisThe law in the State of Washington, albeit clear on issues regarding first party claimants, was recently challenged in the matter of Eye Associates Northwest, P.C. v. Sedgwick et. al. However, despite this challenge of first impression, the court limited the application of the term “first party claimant” (a term of art akin to “insured”) based upon the wording of a loss payee clause, as well as taking into consideration and harmonizing the wording of the leases, other provisions in the policy regarding tenant improvements, and the simple fact that Eye Associates was not named in the policy whatsoever.
In Eye Associates, the plaintiff leased office space in a high-rise medical office building, insured by three separate insurance companies. A water loss caused damage to the plaintiff’s leased space, and the plaintiff brought suit against the owner of the building, its insurers, the property manager, a third-party administrator (TPA), and two individual adjusters assigned to inspect and adjust the water loss claim.
Reprinted courtesy of
Kathleen A. Nelson, Lewis Brisbois and
Jonathan R. Missen, Lewis Brisbois
Ms. Nelson may be contacted at Kathleen.Nelson@lewisbrisbois.com
Mr. Missen may be contacted at Jonathan.Missen@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of