Homeowner Who Wins Case Against Swimming Pool Contractor Gets a Splash of Cold Water When it Comes to Attorneys’ Fees
February 05, 2024 —
Garret Murai - California Construction Law BlogLooking outside as of late it seems like the glorious, sun-drenched days of Summer are just a nostalgic memory of days long gone. So, to bring back some of those warm-weather memories, I have a swimming pool case for you. Although, like most of the things we write about here on the California Construction Law Blog it’s not all fun-in-the-sun.
The Lee Case
In Lee v. Cardiff, 94 Cal.App.5th 398 (2023), Homeowner Dianne Lee entered into a construction contact with contractor David Brian Cardiff doing business as Advantage Pools Bay Area for a swimming pool and landscaping project totaling $231,500. It must have been quite a pool.
As these things sometimes go, a dispute arose and Cardiff left the job before its was finished. Lee later sued alleging breach of contract, negligent construction and violation of the Contractor State License Law.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
U.S. Supreme Court Oral Arguments: Maritime Charters and the Specter of a New Permitting Regime
February 24, 2020 —
Anthony B. Cavender - Gravel2GavelEarlier this month, the Supreme Court heard oral arguments in two important environmental cases—one that could change the approach to routine maritime charters and another that could introduce a potentially punishing permitting regime via a CWA citizen suit.
Cleaning the Delaware: CITGO Asphalt Refining Company v. Frescati Shipping Company
The CITGO case involves a large oil spill into the Delaware River, and who bears financial responsibility for the cleanup. CITGO chartered an oil tanker to bring Venezuelan crude oil to CITGO’s New Jersey refinery located on the Delaware River. The tanker struck a submerged and abandoned anchor within yards of the refinery, and a large and expensive oil spill resulted. In accordance with the Oil Pollution Act, both the shipper, Frescati Shipping Company, and the United States, paid for the immediate oil spill response, and CITGO was later sued for a large share of these costs based on the fact that it entered into a charter with Frescati, which obliged CITGO to provide a “safe berth.” The U.S. Court of Appeals for the Third Circuit held that CITGO was liable under the principles of maritime law, meaning that CITGO was strictly liable for the spill even if no one knew that the anchor was present on the floor of the river or lurking in the waters of the Delaware River. CITGO has argued that this result is unfair and poses a threat to the maritime shipping industry if it is held to be strictly liable for this spill. It appears that this is may well be the majority rule that is applied when interpreting these routinely entered maritime charters. The Court’s decision will be immensely important to the shipping industry.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Crews Tested By Rocky Ground, Utility Challenges
September 03, 2019 —
Louise Poirier - Engineering News-RecordProblematic utility locations and difficult ground conditions required the project team to develop innovative solutions on the University of Texas at San Antonio’s $95-million Science and Engineering Building.
Reprinted courtesy of
Louise Poirier, Engineering News-Record
Ms. Poirier may be contacted at poirierl@enr.com
Read the court decisionRead the full story...Reprinted courtesy of
Keep It Simple: Summarize (Voluminous Evidence, That Is...)
October 02, 2023 —
Steve Swart - The Dispute Resolver"The most complex analyses grow beautifully simple as they become public objects.” Philip Rieff, Fellow Teachers (1973), quoted in JOHN BARTLETT, BARTLETT’S FAMILIAR QUOTATIONS 800 (Geoffrey O’Brien gen. ed., 18th ed. 2012)
In a recent ABA Forum on Construction Law Webinar, a panelist with substantial experience as an arbitrator explained that documents are the most important evidence in a construction dispute. Fact-finders, she said, focus on contemporaneous project records more than witness testimony to vet what happened.
But, even a small to mid-sized construction project can generate millions of pages of documents. That is particularly true when disputes involve loss of productivity, delay, acceleration, and disruption. The volume of records related to entitlement and damages (e.g., timesheets, accounting, equipment logs, schedule files, meeting minutes, etc.) can overwhelm and confuse — not to mention bore — the fact finder.
Read the court decisionRead the full story...Reprinted courtesy of
Steve Swart, Williams MullenMr. Swart may be contacted at
sswart@williamsmullen.com
Traub Lieberman Attorneys Recognized as 2022 New York – Metro Super Lawyers®
October 17, 2022 —
Traub LiebermanTraub Lieberman is pleased to announce that seven Partners from the Hawthorne, NY Office have been selected to the 2022 New York - Metro Super Lawyers list.
2022 New York – Metro Super Lawyers
- Copernicus Gaza – Insurance Coverage
- Jonathan Harwood – Professional Liability
- Lisa Rolle – Construction Litigation
- Christopher Russo – Professional Liability
- Lisa Shrewsberry – Professional Liability
- Stephen Straus – Insurance Coverage
- Richard Traub – Insurance Coverage
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman
Overtime! – When the Statute of Limitations Isn’t Game Over For Your Claim
August 07, 2022 —
Bradley E. Sands, Jones Walker LLP - ConsensusDocsStatutes of limitations establish the period of time within which a claimant must bring an action after it accrues. An action can be filing a lawsuit and, in some instances, filing a demand for arbitration. But a multi-year construction project could be longer than the applicable statute of limitations. For example, under Delaware or North Carolina law, the statute of limitations for a breach of contract is only three years.1 So a claim for breach of a construction contract that occurred (i.e. accrued) at the beginning of a four-year project under Delaware or North Carolina law may expire before the project is completed.
Generally, a claim accrues at the time of the breach (however, it is important to note that this is not always the case and claim accrual could be the subject of an entirely different article). During the course of a multi-year construction project, proposed change orders or claims for additional compensation can sit, unanswered or unpursued, for months. Or, the parties may informally agree as part of regular project communications to put off dealing with a claim head-on until the end of the project. On certain projects, slow-walking a claim is understandable, as a contractor may be hesitant to sue an owner in the middle of a multi-year project and risk upsetting an otherwise good working relationship. But a delay in formally asserting a put-off claim after it accrues could result in the claim falling subject to a statute of limitations defense.
Read the court decisionRead the full story...Reprinted courtesy of
Bradley E. Sands, Jones Walker LLP (ConsensusDocs)Mr. Sands may be contacted at
bsands@joneswalker.com
Preparing the Next Generation of Skilled Construction Workers: AGC Workforce Development Plan
November 08, 2017 —
David R. Cook Jr. - Autry, Hanrahan, Hall & Cook, LLPIn August, Associated General Contractors (AGC) and Autodesk released the results of their 2017 Construction Workforce Shortage Survey. Of the more than 1,600 survey respondents, 70 percent said they are having difficulty filling hourly craft positions. Craft worker shortages are the most severe in the West, where 75 percent of contractors are having a hard time filling those positions, followed by the Midwest where 72 percent are having a hard time finding craft workers, 70 percent in the South and 63 percent in the Northeast.
Tight labor market conditions are prompting firms to change the way they operate, recruit and compensate workers. Most firms report they are making a special effort to recruit and retain veterans (79 percent); women (70 percent), and African Americans (64 percent). Meanwhile, half of construction firms report increasing base pay rates for craft workers because of the difficulty in filling positions. Twenty percent have improved employee benefits for craft workers and 24 percent report they are providing incentives and bonuses to attract workers.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hanrahan, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Homeowner Has No Grounds to Avoid Mechanics Lien
September 01, 2011 —
CDJ STAFFThe California Court of Appeals has rejected a motion by a homeowner in a dispute with the contractor who built an extension to his home. In McCracken v. Pirvulete, Mr. McCracken filed a mechanics lien after Mr. Pirvulete failed to complete payment. The matter went to trial with a series of exhibits that showed “the contractual relationship was strained and the parties disagreed over performance and payment.” As a result of the trial, the court awarded Mr. McCracken, the contractor, $1,922.22.
Mr. Pirvulete appealed, contending that the court had not allowed his daughter to act as a translator, that the court had failed to give him sufficient time to present his case, that the mechanics lien should have been dismissed, and several other claims, all before a formal judgment was issued. After the court formalized its judgment and rejected the appeal, Mr. Pirvulete appealed again.
The appeals court found that Mr. Pirvulete did not provide an adequate record for review. The court dismissed Mr. Pirvulete’s claims. The court notes that Mr. Pirvulete claimed that a request for a discovery period was denied, however, he has provided neither the request nor the denial. The trial court has no record of either.
Nor was there a record of a request that Mr. Pirvulete’s daughter provide translation. The court notes, “so far as we can glean from the record provided, the Register of Actions states, ‘Trial to proceed without Romanian Interpreter for Defendant; Daughter present to interpret if needed.’” Additionally, the court found that “there has been no showing that his facility with the English language is or was impaired in any way or that there was any portion of any proceeding, which he did not understand.”
Further, the appeals court found there were no grounds for a new trial, despite Mr. Pirvulete’s filings. The court concluded, “The owner has failed to provide a record adequate for review of most, if not all, of the claims of error. Some issues are not cognizable because they relate to entirely separate proceedings, and not the trial below. To the limited extent that the claims are examinable, the owner has made no showing of error.” The court affirmed the judgment of the lower court against Mr. Pirvulete.
Read the court’s decision…