Florida’s Statute of Limitations / Repose for Actions Founded on Construction Improvement Modified
April 25, 2023 —
David Adelstein - Florida Construction Legal UpdatesOn April 13, 2023, Florida’s all-important four-year statute of limitations–Florida Statute s. 95.11(3)(c)–relating to actions founded on construction of an improvement of real property was modified. This is a key statute of limitations for ALL construction practitioners because it also includes the statute of repose for latent construction defects.
At the bottom of this posting is the current version fo s. 95.11(3)(c) with the underlined section being recent additions. (They hyperlink above will identify the deletions and additions.) Important things to note:
- Statute of Repose. The statute of repose has been reduced from 10 years to 7 years. There is now an objective date for when the repose period commences: “within 7 years after the date the authority having jurisdiction issues a temporary certificate of occupancy, a certificate of occupancy, or a certificate of completion, or the date of abandonment of construction if not completed, whichever date is earliest.”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Connecticut Supreme Court to Review Several Issues in Asbestos Coverage Case
November 08, 2017 —
Ciaran Way & Robert F. Walsh – White and Williams LLPOn October 18, 2017, in R.T. Vanderbilt Company v. Hartford Accident & Indemnity Company, the Connecticut Supreme Court certified four issues for appeal, which relate to trigger, allocation, pollution exclusions, and the occupational disease exclusion in the context of asbestos bodily injury claims. This post identifies the issues the Connecticut Supreme Court will decide on appeal and sets forth the Appellate Court’s ruling on each issue.
Issue 1: Whether a “continuous trigger” theory of coverage applies to asbestos-related disease claims and whether expert medical testimony on the timing of injury should be precluded
The Appellate Court applied a continuous trigger, and found that the trial court properly excluded testimony from medical experts the insurers had proffered to prove that the asbestos disease process did not support a continuous trigger.
Reprinted courtesy of
Ciaran Way, White and Williams LLP and
Robert Walsh, White and Williams LLP
Ms. Way may be contacted at wayc@whiteandwilliams.com
Mr. Walsh may be contacted at walshr@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Near-Zero Carbon Cement Powers Sustainable 3D-Printed Homes
August 07, 2023 —
Aarni Heiskanen - AEC BusinessEco Material Technologies and Hive 3D have unveiled the first 3D-printed homes using near-zero carbon cement as part of a housing project called The Casitas @ The Halles.
The homes, ranging from 400 to 900 square feet, are constructed using Eco Material’s durable, longer-lasting cement called PozzoCEM Vite®. The cement replaces 100% of traditional Portland cement, has 92% lower emissions, and sets much faster.
Hive 3D has developed a system to mix Eco Material’s cement replacement products with locally-sourced aggregates on-site, enabling cost-efficient and affordable construction. The collaboration aims to offer sustainable housing solutions and transition the construction industry away from high-carbon materials.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Design-Assist, an Ambiguous Term Causing Conflict in the Construction Industry[1]
December 02, 2019 —
John P. Ahlers - Ahlers Cressman & Sleight PLLC“Design-Assist” is one of the recent cost-saving trends being touted for construction projects and, in particular, construction projects utilizing alternative procurement methods. If an internet search for the term, “design-assist” is made, the result will be numerous construction industry articles and white papers lauding “design-assist” as a recent cost-saving trend in construction procurement. From a legal perspective, however, the term “design-assist” is notably absent from court opinions and most state licensing laws. With the exception of the ConsensusDocs, few standard form contracts even include the term “design-assist” in their text.
The ConsensusDocs agreement provides examples of the Constructor’s obligations to perform “assisting activities” (the term “design-assist” is not used) and states that, notwithstanding the performance of such “assisting activities” by the Constructor, the responsibility of the design remains with the Designer unless otherwise stated in the Contract:
- Article 4.5 DESIGN PROFESSIONAL’S RESPONSIBIITIES The Designer shall furnish or provide all design and engineering services necessary to design the Project in accordance with the Owner’s objectives … the Designer shall draw upon the assistance of Constructor and others in developing the design, but the Designer shall retain overall responsibility for all design decisions….
- Article 4.6 CONSTRUCTOR’S RESPONSIBILITIES [T]he Constructor shall assist the Designer in the development of the Project Plan and Project Design but shall not provide professional services which constitute the practice of architecture or engineering unless the Constructor needs to provide such services in order to carry out its responsibilities … or unless specifically called for by the Contract Documents.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers Cressman & Sleight PLLCMr. Ahlers may be contacted at
john.ahlers@acslawyers.com
First Trump Agenda Nuggets Hit Construction
January 26, 2017 —
Pam Radtke Russell, Mary B. Powers & Debra K. Rubin - Engineering News-RecordPresident Donald J. Trump began making good on campaign promises to put Americans back to work and reduce the size of government, as he signed orders and memoranda setting in motion approval of the Obama administration-halted Keystone XL and Dakota Access pipelines and streamlining of infrastructure and manufacturing permitting processes. But firms and watchdog groups are concerned how an announced freezing of government hiring and contracting will play out, as well as the future of environmental protection.
Reprinted courtesy of Engineering News-Record staff
Pam Radtke Russell,
Mary B. Powers and
Debra K. Rubin Read the court decisionRead the full story...Reprinted courtesy of
Ms. Rubin may be contacted at
rubind@enr.com
2016 California Construction Law Upate
December 10, 2015 —
Garret Murai – California Construction Law BlogThe California State Legislature saw the introduction of 2,297 bills during the first half of the 2015-2016 legislative session of which 1,010 bills were signed into law.
For contractors, the bill (now law), having the most immediate effect is SB 467, which increases the license bond amount required of all contractors from $12,500 to $15,000. In addition to licensing changes, 2015 saw the enactment of a number of bills providing for alternative project delivery methods from design-build, to CM at risk, to public-private partnerships, and even the expanded use of enhanced infrastructure financing districts as the state enters its fourth year since the abolishment of redevelopment agencies.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Evaluating Smart Home Technology: It’s About More Than the Bottom Line
May 03, 2021 —
James W. McPhillips & Rachel Newell - Gravel2Gavel Construction & Real Estate Law BlogOutfitting a commercial real estate space with smart technology can be a significant cost. While the long-term benefits and strategic improvements we’ve discussed previously can make that investment worthwhile, the evaluation period is critical to ensure an impactful ROI. Property developers, owners, and managers should undertake a rigorous evaluation process to ensure the technology procurement aligns with the project’s overall financial plan. And this is not just about getting the cost right. If the technology does not meet the needs of the space, then all the smart technology in the world will not prevent the project from being a sunk cost.
Do the Research so You Know …
The Technology. While the RFP is a key step of the procurement process, a more informal research phase should be undertaken first. Smart technology is a rapidly evolving field, and before reaching out to vendors, the business should ensure that it understands what is available—both in terms of the kinds of technology that can be implemented, and the various companies that offer solutions. Gathering this information early will yield results that align more closely with a particular building’s needs.
Reprinted courtesy of
James W. McPhillips, Pillsbury and
Rachel Newell, Pillsbury
Mr. McPhillips may be contacted at james.mcphillips@pillsburylaw.com
Ms. Newell may be contacted at rachel.newell@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
New 2021 ALTA/NSPS Land Title Survey Standards Effective February 23, 2021
March 01, 2021 —
Emily K. Bias & Josh D. Morton - Gravel2Gavel Construction & Real Estate BlogThe “Minimum Standard Detail Requirements for ALTA/NSPS Land Title Surveys” is a document jointly promulgated by the American Land Title Association (ALTA), representing the title insurance industry, and the National Society of Professional Surveyors (NSPS), representing professional land surveyors, which describes the uniform minimum standards with which surveyors must comply when preparing a survey to be used by a title insurance company for the purpose of deleting the general survey exception from ALTA title policy forms. The first such set of standards was developed in 1962 and has since been revised 10 times. The standards are currently updated every five years and are relied on by real estate professionals, including purchasers, lenders, title insurers and their attorneys, nationwide. In October 2020, a joint committee comprising representatives of both ALTA and NSPS adopted the “2021 Minimum Standard Detail Requirements for ALTA/NSPS Land Title Surveys,” which will become effective on February 23, 2021. The significant changes between the 2021 standards and the previous 2016 standards are summarized below.
Survey Matters
The 2021 standards clarify that only survey-related matters must be summarized on the survey. This revision was intended to foreclose a practice common among some institutional lenders to require that the survey list all items shown in Schedule BII of the title commitment on the face of the survey regardless of whether those items may in fact be survey related. The 2021 standards also add a requirement that the surveyor include a note specifying whether the location of a right of way, easement or other survey-related matter is shown on the survey. This change incorporates common lender and purchaser requirements that were not previously enumerated in the survey standards.
Reprinted courtesy of
Emily K. Bias, Pillsbury and
Josh D. Morton, Pillsbury
Ms. Bias may be contacted at emily.bias@pillsburylaw.com
Mr. Morton may be contacted at josh.morton@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of