Retaining Wall Contractor Not Responsible for Building Damage
July 20, 2011 —
CDJ STAFFThe Court of Appeals of Indiana ruled on July 8 in the case of Rollander Enterprises, Inc. v. H.C. Nutting Co. Judge Baily wrote the opinion affirming the decision of the trial court.
The case involved an unfinished condominium complex, the Slopes of Greendale, in Greendale, Indiana. Rollander is a real estate development company incorporated in Ohio. One of the issues in the case was whether the case should be settled in the Indiana courts or be tried in Ohio. The project was owned by a special purpose entity limited liability corporation incorporated in Indiana.
Rollander hired Nutting to determine the geological composition of the site. Nutting’s report described the site as “a medium plastic clay containing pieces of shale and limestone.” The court summarized this as corresponding with “slope instability and landslides.” Rollander then hired Nutting to design the retaining walls, which were constructed by Scherziner Drilling.
After cracking was discovered on State Route 1, the walls were discovered to be inadequate. More dirt was brought in and a system of tie-backs was designed to anchor the walls. Not only were the tie-backs unsightly, local officials would not approve the complex for occupancy. Further, the failure of the wall below one building lead to damage of that building.
The court concluded that since almost all events occurred in Indiana, they rejected Rollander’s contention that the case should be tried in Ohio. Further, the court notes “the last event making Nutting potentially liable on both claims was an injury that occurred in Indiana and consequently, under the lex loci delicti analysis, Indiana law applies.”
Nor did the court find that Nutting was responsible for the damage to the rest of the project, citing an Indiana Supreme Court ruling, that “there is no liability in tort to the owner of a major construction project for pure economic loss caused unintentionally by contractors, subcontractors, engineers, design professionals, or others engaged in the project with whom the project owner, whether or not technically in privity of contract, is connected through a network or chain of contracts.”
The court concluded:
Because Rollander was in contractual privity with Nutting, and Indy was connected to Nutting through a chain of contracts and no exception applies, the economic loss rule precludes their recovery in tort. Damage to Building B was not damage to "other property," and the negligent misrepresentation exception to the economic loss rule is inapplicable on these facts. The trial court therefore did not abuse its discretion by entering judgment on the evidence in favor of Nutting on the Appellants' negligence and negligent misrepresentation claims.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
‘Hallelujah,’ House Finally Approves $1T Infrastructure Funding Package
November 15, 2021 —
Tom Ichniowski - Engineering News-RecordAfter nearly three months in a holding pattern and a long day of back-and-forth negotiations among House Democrats, the chamber approved a sweeping, multi-year infrastructure funding package late on Nov. 5 that will provide an estimated $1 trillion for a wide range of infrastructure categories, including highways, transit, rail, water, power and broadband.
Reprinted courtesy of
Tom Ichniowski, Engineering News-Record
Mr. Ichniowski may be contacted at ichniowskit@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Construction Defect Case Not Over, Despite Summary Judgment
November 07, 2012 —
CDJ STAFFThe Supreme Court of Oregon has concluded in an en banc decision that a motion to reconsider a summary judgment is not a motion for a new trial. In coming to their conclusion the court overturned an earlier Oregon Supreme Court case, Carter v. U.S. National Bank. Although the decision does not bear on construction defects, the underlying case did. Due to the decision, these claims can now be evaluated in a trial.
The case, Association of Unit Owners of Timbercrest Condominiums v. Warren, came about after an apartment complex was converted into condominium units. The developers hired Big Al’s Construction for some of the remodeling work. The condominium association later sued the developer and the contractor over claims of construction defects. The defendants filed a motion for summary judgment, which the court granted.
But that wasn’t the end of things. The plaintiff soon filed a “motion to reconsider,” noting that the summary judgment seemed to be in conflict with both law and other recent rulings, and additionally, the grounds for the decision were not in the order. The judge then notified the parties that the court had “pulled the trigger too quickly” and had seven questions for the parties to answer.
The court dismissed all claims against the defendants. The defendants filed their responses, objecting that that “‘there is no such thing’ as a motion for reconsideration.” Further, while “the rules do allow for post-judgment review of pre-judgment rulings through a motion for a new trial,” the plaintiffs had not filed for a new trial. But did they need one? They did file an appeal.
The judge in the case admitted that there was no such thing as a motion to reconsider, and felt bad about prematurely signing the judgment. The case was sent to the Court of Appeals to determine if the motion to reconsider was a request for a new trial. The Court of Appeals concurred.
In reviewing the decision, the Oregon Supreme Court concluded that there were a maximum of three questions to address. Was the motion for reconsideration a motion for a new trial? If so, was the later notice of appeal premature? And if so, was the plaintiff required to file a new appeal? The court determined that the answer to the first question was no.
Prior decisions pointed to the conclusion “that a motion for reconsideration of a summary judgment amounts to a motion for a new trial,” but here the court concluded that “our prior cases erred,” and turned to the summary judgment rule for clarification. The court noted that “the rule contemplates that summary judgment and trial are separate and distinct events.” With this conclusion, the Oregon Supreme Court remanded the case to the Court of Appeals for further proceedings.
Read the court decisionRead the full story...Reprinted courtesy of
Lasso Needed to Complete Vegas Hotel Implosion
February 18, 2015 —
Beverley BevenFlorez-CDJ STAFFThe Miami Herald reported that “demolition workers used an Old West method on Tuesday to finish an incomplete casino implosion in Las Vegas.”
The Clarion Hotel and Casino owner Lorenzo Doumani told the Miami Herald that “[t]hey lassoed the building with steel cables, got a crane, and pulled and pulled and pulled.”
Burke Construction used a 2-ton explosive punch to bring the structure down, however, the concrete building dropped four stories but remained upright.
Burke Construction’s corporate safety coordinator, Anthony Schlect, told the Miami Herald that he was investigating the incident.
Read the court decisionRead the full story...Reprinted courtesy of
Treble Damages Awarded After Insurer Denies Coverage for Collapse
July 03, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe Fourth Circuit upheld the district court's decision that a collapse was covered, but reversed the denial of treble damages to the insured. DENC, LLC v. Phila. Indem. Ins. Co., 2022 U.S. App. LEXIS 10443 (4th Cir. April 18, 2022). The district court decision was summarized
here.
DENC owned The Crest, an apartment building leased to Elon University for student housing. Philadelphia Indemnity Company insured the property. In January 2018, students gathered on a second-floor breezeway for a party. Partygoers began jumping in the breezeway, which caused an abrupt collapse. Observers noticed that the breezeway was hanging down by more that a foot.
DENC filed a claim with Philadelphia the next day. An adjuster was sent to inspect the breezeway. By that time, the city had condemned The Crest. The adjuster said that undiscovered "water damage which occurred over an extended period of time" caused the loss.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Connecticut’s New False Claims Act Increases Risk to Public Construction Participants
April 02, 2024 —
Fred Hedberg & William Stoll - Construction Law ZoneAfter several decades, Governor Ned Lamont signed a bill into law, effective July 1, 2023, An Act Concerning Liability for False and Fraudulent Claims, Public Act No. 23-129, eliminating language that previously limited enforcement of Connecticut’s False Claims Act to claims relating to a state-administered health or human services program. The revisions dramatically expanded potential liability under the False Claims Act, allowing both private citizens and the Attorney General to bring actions under the Act in any context, including the construction industry. Consequently, contractors, subcontractors, suppliers and design professionals on public construction projects in Connecticut must be familiar with this newly enacted law and take steps to reduce the risks of doing business on such projects.
Reprinted courtesy of
Fred Hedberg, Robinson & Cole LLP and
William Stoll, Robinson & Cole LLP
Mr. Hedberg may be contacted at fhedberg@rc.com
Mr. Stoll may be contacted at wstoll@rc.com
Read the court decisionRead the full story...Reprinted courtesy of
Home Builders Wear Many Hats
May 10, 2013 —
CDJ STAFFGeorge McMahan, the president of the West Texas Home Builders Association, writes in the Lubbock Avalanche-Journal about what it takes to be a home builder. He notes that “a home builder guides dozens of skilled artisans and professionals,” and must “understand all of the home’s complex systems and know enough about each contractor’s trade in order to coordinate this skilled team to build and sell a quality product.”
Additionally, home builders must “serve as liaisons with their communities and local government officials.” After the site is selected and homes are being built, “a home builder acts as an inspector.” McMahan notes that “a professional home builder will make certain the home meets both code and warranty guidelines long before and after the officials show up.”
“Home builders,” he says, “are schedulers and record keepers.” They have to “tackle multiple tasks simultaneously in order to keep the construction process moving forward.” They “wear many, many hats,” so that they can “deliver a home where the new owners can hang their own hats, raise a family and build lifelong memories.”
Read the court decisionRead the full story...Reprinted courtesy of
What is the Effect of an Untimely Challenge to the Timeliness of a Trustee’s Sale?
April 13, 2017 —
Ben Reeves - Snell & Wilmer Real Estate Litigation BlogEver wonder what happens if a person challenges the timeliness of a trustee’s sale after the sale already occurred? Waiver of the argument of course! And, in the case of Wells Fargo Bank, N.A. v. Waltner, the affirmance of an eviction judgment.
In the Waltner case, Wells Fargo Bank, N.A., as Trustee for WaMu Mortgage Pass-Through Certificates, Series 2005-PR4 Trust (the “Bank”), purchased a residential property at a trustee’s sale in September 2015. The Bank gave the occupant of the house, Sarah Waltner (“Waltner”), notice to vacate the property, but she did not do so. Accordingly, the Bank filed a summary action to evict Waltner, which the trial court ultimately granted.
After the trial court granted the Bank relief, Waltner filed a motion to dismiss and a motion to vacate the eviction judgment arguing, among other things, that the judgment was void because the Bank conducted the trustee’s sale after the statute of limitations expired. Both motions were denied, and Waltner appealed.
Read the court decisionRead the full story...Reprinted courtesy of
Ben Reeves, Snell & WilmerMr. Reeves may be contacted at
breeves@swlaw.com