Appraisal Appropriate Despite Pending Coverage Issues
August 16, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe court granted the insured's motion for partial summary judgment, allowing an appraisal to go forward even with outstanding coverage issues in dispute. DC Plastic Products Corp. v. Westchester Surplus Lines Ins. Co., 2021 U,.S. Dist. LEXIS 95908 (D. N.J. May 19, 2021).
DC Plastic's property was damaged by Superstorm Sandy in October 2012. Claims submitted to Westchester resulted in a payment of $951,102.89 to DC Plastic. The parties disagreed on whether further payments were due. In 2017, DC Plastic sued Westchester for additional payments. DC Plastic moved to compel an appraisal for its claims, requesting that the court appoint an umpire for the appraisal process. Westchester cross-moved to dismiss the case in its entirety.
DC Plastic's complaint asked that the court appoint an umpire. The policy stated if the parties could not agree on the amount of loss, each party would select an appraiser, who would then agree upon an umpire. If they could not agree, either party could request the court to appoint the umpire. Therefore, the court was authorised to select the umpire here.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Five-Year Peak for Available Construction Jobs
December 11, 2013 —
CDJ STAFFThere are more job openings in construction now than there have been since 2008. The October jobs report from the Bureau of Labor Statistics reported 124,000 job openings in construction. With the demand for workers, some builders have experienced labor shortages, according to the National Association of Home Builders. The NAHB expects the trend to continue into 2014, “if firms can find workers with the right skills.”
Read the court decisionRead the full story...Reprinted courtesy of
Could This Gel Help Tame the California Fires?
November 28, 2018 —
Gordy Megroz - BloombergIn 2009, Jeff Denholm was making a living as an adventure athlete, competing in stand-up paddleboard races and riding giant waves at Mavericks, the famous surf break near his home in Santa Cruz, Calif. Denholm was sponsored by Patagonia Inc., but to generate extra cash—“Adventure athletes don’t make a ton of money,” he says—he had a side gig leasing a fire truck to state and county crews that had run out of equipment battling wildfires.
One firefighting tool that Denholm kept onboard was retardant, which helps tamp down existing fires and can prevent them; he used a type known as a foam suppressant. Last year the U.S. Forest Service spent about $72 million on retardants, but in researching them, Denholm discovered some discouraging information.
Read the court decisionRead the full story...Reprinted courtesy of
Gordy Megroz, Bloomberg
Demonstrating A Fraudulent Inducement Claim Or Defense
May 18, 2020 —
David Adelstein - Florida Construction Legal UpdatesIn a recent case, Florida’s Fourth District Court of Appeal reversed a trial court’s denial of a motion for a temporary injunction sought by an employer due to an independent contractor’s violation of a non-compete and non-solicitation provision in an employment / independent contractor agreement (“employment agreement”). You can find more on this case and the enforcement of the non-compete and non-solicitation clause
here.
A worthy discussion in this case centers on the independent contractor’s fraudulent inducement defense. Specifically, the independent contractor, as a defense to the injunction, claimed that he was fraudulently induced into entering into the employment agreement because the employer promised he would make a certain amount of money and he would work predominantly in one geographic location. The employment agreement contained NO such representations. Instead, the employment agreement contained a fee and services schedule and the independent contractor would be compensated based on that schedule. It stated nothing as to the independent contractor only having to work, or predominantly working, in one geographic location, or that the independent contractor would be guaranteed “X” amount of money working in that location. Why is this important?
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Washington State Supreme Court Issues Landmark Decision on Spearin Doctrine
September 29, 2021 —
Cameron Sheldon - Ahlers Cressman & Sleight PLLCThe Washington State Supreme Court’s recent decision in Lake Hills Invs., LLC v. Rushforth Constr. Co. No. 99119-7, slip op. at 1 (Wash. Sept. 2, 2021) marks the first time in over 50 years that it has ruled on the Spearin doctrine. The Court’s opinion clarified the contractor’s burden when asserting a Spearin defense and affirmed the jury’s verdict in favor of contractor AP Rushforth Construction Company (AP). The decision is a major win for Ahlers Cressman & Sleight PLLC attorneys Scott Sleight, Brett Hill, and Nick Korst, who represented AP throughout its long-running dispute with Lake Hills Investments, LLC (LH), including the two-month jury trial and the appeal. Leonard Feldman of Peterson | Wampold | Rosato | Feldman | Luna and Stephanie Messplay of Van Siclen Stocks & Firkins also represented AP on appeal.
At trial, the owner—Lake Hills Investments, LLC (LH)—asserted it was entitled to $3 million in liquidated damages and $12.3 million for defects it alleged were caused by AP’s deficient workmanship. AP denied responsibility for the delays and most of the defects and requested payment of $5 million. Regarding LH’s defect claims, AP argued as an affirmative defense that the defects were caused by deficiencies in the plans and specifications provided by LH. This affirmative defense was rooted in the Spearin doctrine, which states that when the contractor follows plans and specifications provided by the owner, the contractor is not responsible for defects caused by the plans and specifications.
Read the court decisionRead the full story...Reprinted courtesy of
Cameron Sheldon, Ahlers Cressman & Sleight PLLCMs. Sheldon may be contacted at
cameron.sheldon@acslawyers.com
South Carolina Court of Appeals Diverges from Damico Opinion, Sending Recent Construction Defects Cases to Arbitration
October 24, 2023 —
Laura Paris Paton - Gordon Rees Construction Law BlogCould the latest opinion from the South Carolina Court of Appeals be the distant ringing of a death knell for runaway construction defects verdicts? On the heels of the Damico ruling earlier this year, the courts have issued several opinions distinguishing various arbitration agreements from the one analyzed in Damico and have sent subsequent cases to arbitration.
This summer, the Supreme Court and Court of Appeals compelled arbitration in Cleo Sanders v. Savannah Highway Automotive Company, et al. Appellate Case No. 2021-000137 / Opinion No. 28168 (petition for rehearing pending) and Joseph Abruzzo v. Bravo Media Productions, et al. Appellate Case No. 2020-001095 / Opinion 6004. Now, in the matter of Jonathan Mart, on behalf of himself and others similarly situated, Respondent, v. Great Southern Homes, Inc., Appellant, Appellate Case No. 2018-001598, the Court of Appeals reversed the circuit court’s order denying a homebuilder’s motion to dismiss and compelled arbitration in this action, which was brought by the homeowner, individually and on behalf of other similarly situated homeowners.
Read the court decisionRead the full story...Reprinted courtesy of
Laura Paris Paton, Gordon Rees Scully MansukhaniMs. Paton may be contacted at
lpaton@grsm.com
The Rise of Modular Construction – Impacts for Consideration
December 04, 2023 —
Chad V. Theriot - ConsensusDocsModular construction is not new. However, over the last several years, modular construction has seen significant growth with no signs of slowing down. In 2021, global modular construction represented a market of approximately $130 billion and is projected to reach upwards of $235 billion by 2031. Modular construction growth in the US is largely due to the technological advances and globalization.
In general, modular construction involves the manufacturing and fabrication of standardized components of a structure in an off-site, controlled environment. Once those components are fabricated, they are then transported to the project site and assembled by an installer or contractor. Moving these fabrication and construction activities off-site allows the fabricator to control the quality standards over the fabrication process and gain the economic advantage of an assembly line and manufacturing process. This leads to a reduction in cost. This cost savings is then passed on to the owner, thereby driving down the overall price of construction.
Read the court decisionRead the full story...Reprinted courtesy of
Chad V. Theriot, Jones Walker (ConsensusDocs)Mr. Theriot may be contacted at
ctheriot@joneswalker.com
Court finds subcontractor responsible for defending claim
May 18, 2011 —
CDJ STAFFIn an unpublished decision, the California Fourth Appellate District Court has reversed the judgment of Judge Linda B. Quinn of the Superior Court of San Diego. In the case Inland California, Inc. v. G.A. Abell, Inland, a general contractor had subcontracted with Apache Construction and Precision Electric Company (G.A. Abell).
Apache alleged that extra demolition and drywall work was needed due to Precision’s electrical work. Inland tendered a defense of Apache’s claims. However, Precision did not provide any defense. Inland withheld payment from Precision.
At trial, Inland “conceded Precision earned the $98,000 in progress payments Inland withheld.†They were obligated to additionally pay Precision’s costs and attorney fees.
The Fourth Appellate District court has overturned this and remanded the case back to the lower court. The judges determined that Precision was obligated to defend itself against the claims raised by Apache and therefore vacated the judgment against Inland.
Read the court’s decision…