Defense Victory in Breach of Fiduciary Action
February 26, 2015 —
Beverley BevenFlorez-CDJ STAFFEarlier this month, Scott Calkins and Anthony Gaeta of Collinsworth, Specht, Calkins & Giampaoli, LLP obtained a defense verdict in a breach of fiduciary duty action involving a high-rise condominium in downtown San Diego, California. The Association asked for excess of over $3 million, however, the jury returned with a 10-2 defense verdict in favor of K. Hovnanian.
Cortez Blu Community Association, Inc. v. K. Hovnanian at Cortez Hill, LLC, et al. initially involved construction defect claims against the developer, K. Hovnanian, and the general contractor, Turner Construction, as well as a claim of breach of fiduciary duty. However, the construction defect claims settled prior to trial leaving only the breach of fiduciary claim.
“While it is now becoming ever more common for attorneys representing homeowners associations to allege a breach of fiduciary duty by the developer, there has been little actual litigation of the issues surrounding those claims which test the viability of the allegations or the defenses to them,” defense attorney Anthony Gaeta stated. “A breach of a fiduciary duty by a developer, which is demonstrated to damage the viability of an HOA either to perform regularly scheduled maintenance, or replace building components from its reserves, has the potential in economic terms to surpass the damages from purported construction defects.
The Plaintiff argued that K. Hovnanian breached its fiduciary duty to the Association by failing to set adequate reserves within the initial Department of Real Estate budget (“DRE”) for painting, caulking, and power washing the exterior of the building, referencing Raven’s Cove Townhomes, Inc. v. Knuppe Development Co., Inc. (1981) 114 Cal. App. 3d 783. In response, K. Hovnanian stated that in part, the initial reserves as set forth in the DRE budget were adequate, good faith estimates and, therefore, there was no liability for breach of fiduciary duty.
“Our case was exclusively concerned with the duties of the developer when forming the initial HOA, preliminary budgets, and reserves,” Gaeta said. “We litigated the duties and responsibilities of the initial board and whether a developer may rely on reports prepared by third-parties during the formation of a common interest development. The jury found our client’s actions and reliance on third-parties was reasonable and, thus, no breach of fiduciary duty occurred.”
Collinsworth, Specht, Calkins & Giampaoli is a general civil litigation firm representing clients throughout California and Arizona. You may learn more about the firm at www.cslawoffices.com
Read the court decisionRead the full story...Reprinted courtesy of
OSHA’s COVID-19 Emergency Temporary Standard Is in Flux
December 06, 2021 —
Megan E. Baroni & Jonathan H. Schaefer - Construction ExecutiveOn Friday, Nov. 5, 2021, Occupational Safety and Health Administration’s COVID-19 Vaccination and Testing Emergency Temporary Standard was issued, with most requirements set to go into effect on Dec. 5. The ETS applies to employers with a total of 100 or more employees company-wide. Employers covered by the ETS would be required to develop, implement and enforce a mandatory vaccination policy, subject to limited exemptions, or allow unvaccinated employees to test regularly and be subject to a mask policy, among other associated recordkeeping, reporting and training requirements.
Almost immediately, the ETS was hit with a number of legal challenges in various courts across the country. On November 6, just a day after the ETS was issued, the U.S. Circuit Court of Appeals for the Fifth Circuit issued an order staying the implementation of the ETS until further notice. The Court’s order was not a final ruling on the validity of the ETS but has halted implementation of the ETS, at least for the time being. Other legal challenges are already in process, further complicating the issue of if and when the ETS will become effective.
As of November 2021, the ETS is on hold, at least temporarily. That could change any day and the ETS could be back in effect, in whole or in part, or permanently halted. The legal challenges to the ETS are unlikely to end, or diminish, until the Supreme Court has weighed in, making for a few uncertain months ahead.
Reprinted courtesy of
Megan E. Baroni and Jonathan H. Schaefer, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Ms. Baroni may be contacted at mbaroni@rc.com
Mr. Schaefer may be contacted at jschaefer@rc.com
Read the court decisionRead the full story...Reprinted courtesy of
Ensuing Losses From Faulty Workmanship Must be Covered
May 10, 2012 —
Tred R. Eyerly - Insurance Law HawaiiCoverage for damages resulting from faulty workmanship in the construction of an apartment complex was at issue in The Bartram, LLC v. Landmark Am. Ins. Co., 2012 U.S. Dist. LEXIS 44535 (N.D. Fla. March 30, 2012).
The owner of the apartments, Bartram, had primary coverage and three layers of excess coverage. Each contract excluded loss from faulty workmanship. The policies provided, however, "if loss or damage by a Covered Cause of Loss results, we will pay for that resulting loss or damage."
Bartram contended water intrusion occurred because of faulty workmanship, which caused damage to the buildings’ exterior and interior finishes, wood sheathing, framing, balcony systems, drywall ceilings and stucco walls. This damage was separate from the work needed to simply fix the faulty workmanship. Therefore, Bartram argued, the ensuing losses that resulted from the water intrusion was covered.
The insurer argued the ensuing loss exception was not applicable if the ensuing loss was directly related to the original excluded loss.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
A Recap of the Supreme Court’s 2019 Summer Slate
September 16, 2019 —
Anthony B. Cavender - Gravel2GavelAs usual, the last month of the Supreme Court’s term generated significant rulings on all manner of cases, possibly presaging the new directions the Court will be taking in administrative and regulatory law. Here’s a brief roundup:
An Offshore Dispute, Resolve – Parker Drilling Management v. Newton
On June 10, 2019, the Court held, in a unanimous ruling, that, under federal law, California wage and hour laws do not apply to offshore operations conducted on the Outer Continental Shelf (OCS). Newton, the plaintiff, worked on drilling platforms off the coast of California, and alleged that he was not paid for his “standby time” which is contrary to California law if not federal law. He filed a class action in state court, which was removed to federal court, where it was dismissed on the basis of a 1969 decision of the U.S. Court of Appeals for the Fifth Circuit, which held that state law applies on the OCS only to the extent that it is necessary to use state law to fill a significant gap or void in federal law, and this is not the case here. On appeal to the Ninth Circuit, that court disagreed with the Fifth Circuit, and ruled that state law is applicable on the OCS whenever it applies to the matter at hand. The Supreme Court, in an opinion written by Justice Thomas, conceded that “this is a close question of statutory interpretation,” but in the end the Court agreed with the argument that if there was not a gap to fill, that ended the dispute over which law applies on the Outer continental Shelf. This ruling, recognizing the preeminent role that federal law plays on the OCS, may affect the resolution of other offshore disputes affecting other federal statutes.
Preemption Prevention – Virginia Uranium, Inc. v. Warren. et al.
On June 17, 2019 the Court decided important cases involving federal preemption and First Amendment issues. In a 6-to-3 decision, the Court held that the Atomic Energy Act does not preempt a Virginia law that “flatly prohibits uranium mining in Virginia”—or more precisely—mining on non-federal land in Virginia. Virginia Uranium planned to mine raw uranium from a site near Coles, Virginia, but acknowledging that Virginia law forbade such an operation, challenged the state law on federal preemption grounds, arguing that the Atomic Energy Act, as implemented by the Nuclear Regulatory Commission, preempts the ability of the state to regulate this activity. However, the majority, in an opinion written by Justice Gorsuch, notes that the “best reading of the AEA does not require us to hold the state law before us preempted,” and that the1983 precedent that Virginia Uranium cites, Pacific Gas & Electric Company v. State Energy Resources Conservation and Development Commission, can easily be distinguished. Justice Gorsuch rejected arguments that the intent of the Virginia legislators in passing the state law should be consulted, that the Court’s ruling should normally be governed by the exact text of the statute at hand. However, both the concurring and dissenting opinions suggest that the what the legislators intended to do is important in a preemption context.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
AIA Releases State-Specific Waiver and Release Forms
September 05, 2022 —
Garret Murai - California Construction Law BlogThe American Institute of Architects (AIA) has released a new series of state-specific waiver and release forms including forms for California. The new
California-specific forms are:
- G901CA-2022 – California Conditional Waiver and Release on Progress Payment
- G902CA-2022 – California Unconditional Waiver and Release on Progress Payment
- G903CA-2022 – California Conditional Waiver and Release on Final Payment
- G904CA-2022 – California Unconditional Waiver and Release on Final Payment
California is one of twelve states – including Arizona, Florida, Georgia, Massachusetts, Michigan, Mississippi, Missouri, Nevada, Texas, Utah and Wyoming – which regulate waiver and release forms on construction projects. California’s waiver and release statute, which is codified at Civil Code section 8120 et seq., sets forth specific language which should be used in waivers and releases. While the exact language set forth under California’s waiver and release statutes does not need to be used, the statute provides that the language must be “in substantially” the same form, and most people follow the statutory language exactly.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Wisconsin Court of Appeals Holds Economic Loss Doctrine Applies to Damage to Other Property If It Was a Foreseeable Result of Disappointed Contractual Expectations
January 15, 2019 —
Gus Sara - The Subrogation StrategistIn Kmart Corp. v. Herzog Roofing, Inc., 2018 Wisc. App. Lexis 842, the Court of Appeals of Wisconsin considered whether the economic loss doctrine barred the plaintiff’s negligence claims against the defendant roofer for damages resulting from the collapse of a roof. The Court of Appeals held that, while some of the plaintiff’s property damages were unrelated to the scope of the contract, the economic loss doctrine still applied to those damages because they were a foreseeable result of the defendant’s breach of the contract. This case establishes that in Wisconsin, the economic loss doctrine bars tort claims for damage to property unrelated to the contract if those damages were a reasonably foreseeable risk of disappointed expectations of the contract.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and Williams LLPMr. Sara may be contacted at
sarag@whiteandwilliams.com
Key Legal Issues to Consider Before and After Natural Disasters
November 25, 2024 —
Patrick Kelly - Construction ExecutiveWhile legal considerations are often the last thing on the minds of project owners and contractors during an emergency, construction industry stakeholders should bear in mind the impact of natural disasters on their legal rights, remedies and potential exposure to claims.
For all stakeholders, two of the most pressing considerations are: (1) what provisions in their contracts are impacted by a natural disaster and (2) do they have any potential exposure to price-gouging claims?
Reprinted courtesy of
Patrick Kelly, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Kelly may be contacted at
pkelly@grayreed.com
National Infrastructure Leaders Visit Dallas' Able Pump Station to Tout Benefits of Water Infrastructure Investment
September 25, 2023 —
American Society of Civil EngineersDALLAS, TX. — An award-winning pump station in south downtown Dallas that protects residents from the Trinity River today was showcased by the
national Engineering and Public Works Roadshow as an example of how infrastructure investment can improve the resilience of a community, protect residents, and encourage economic growth.
The Able Pump Station in downtown Dallas, Texas won awards from both the American Council of Engineering Companies and the American Society of Civil Engineers since its completion in 2019 and has been credited with providing 100-year flood protection to approximately three square miles of high-profile land that was historically vulnerable to severe flooding events from the Trinity River.
The Engineering and Public Works Roadshow is a joint project of the
American Council of Engineering Companies (ACEC), the
American Public Works Association (APWA), and the
American Society of Civil Engineers (ASCE).
The properties adjacent to the previous Able sump complex had experienced frequent flooding. The sump complex included nine separate and interconnected ponds that store stormwater, as well as two existing pump stations, constructed in the 1930s and 1950s, with a combined capacity of 220,000 gallons per minute. To help prevent the loss of life as a result of flooding, the City of Dallas hired HDR to design the new Able Pump Station, which increases the pumping capacity nearly fourfold, to 875,000 gallons per minute. It also lowers the 100-year flood elevation from 399.0 to a design elevation of 392.5 feet.
As the federal government continues to implement this monumental legislation, the second year of the Bipartisan Infrastructure Law will not be fully realized without an expanded and robust workforce. It is imperative that students nationwide are educated on the rewarding careers of civil engineering and public works so that these professions have the necessary staffing to complete transformative projects.
Read the court decisionRead the full story...Reprinted courtesy of