Contractual Waiver of Consequential Damages
January 21, 2019 —
David Adelstein - Florida Construction Legal UpdatesContractual waivers of consequential damages are important, whether they are mutual or one-sided. I believe in specificity in that the types of consequential damages that are waived should be detailed in the waiver of consequential damages provision. Standard form construction agreements provide a good template of the types of consequential damages that the parties are agreeing to waive.
But, what if there is no specificity in the waiver of consequential damages provision? What if the provision just states that the parties mutually agree to waive consequential damages or that one party waives consequential-type damages against the other party? Let me tell you what would happen. The plaintiff will argue that the damages it seeks are general damages and are NOT waived by the waiver of consequential damages provision. The defendant, on the other hand, will argue that the damages are consequential in nature and, therefore, contractually waived. FOR THIS REASON, PARTIES NEED TO APPRECIATE WHAT DAMAGES ARE BEING WAIVED OR LIMITED, AND POTENTIALLY THOSE DAMAGES NOT BEING WAIVED OR LIMITED, WHEN AGREEING TO A WAIVER OF CONSEQUENTIAL DAMAGES PROVISION!
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Supreme Court Eliminates Judicial 'Chevron' Deference to Federal Agency Statutory Interpretations
July 31, 2024 —
Jane C. Luxton - Lewis BrisboisWashington, D.C. (July 1, 2024) – In a much-anticipated decision, on June 28, 2024, the Supreme Court issued a sweeping opinion “overrul[ing]” a 40-year old precedent that required judges to defer to federal agency interpretations of their governing statutes when those laws were ambiguous or silent. Loper Bright Enterprises v. Raimondo, et al. No. 22-451 (2024), overruling Chevron U.S.A., Inc. v. Natural Resources Defense Council, Inc., 467 U.S. 837 (1984).
The decision means that courts will no longer give special weight to an agency’s view of the scope of its regulatory powers but must apply independent judgment in deciding “whether an agency has acted within its statutory authority.” Loper Bright, slip op. at 35. Taking pains to explain that the new ruling would not allow for reversals of cases previously decided under the Chevron doctrine, the Court left no doubt that, in the words of Justice Neil Gorsuch, “[t]oday, the Court places a tombstone on Chevron no one can miss.” Id., Gorsuch Concurring Opinion at 1.
Writing for a 6-2 majority, Chief Justice Roberts forcefully condemned the Chevron-based principle that courts should defer to a federal agency’s interpretation of the scope of its legal authority, rejecting the concept that agencies have any special expertise in statutory interpretation, a field reserved to the courts, not the executive branch, under Article III of the Constitution and the Administrative Procedure Act, 5 U.S.C. § 551 et seq.
Read the court decisionRead the full story...Reprinted courtesy of
Jane C. Luxton, Lewis BrisboisMs. Luxton may be contacted at
Jane.Luxton@lewisbrisbois.com
Reminder: In Court (as in life) the Worst Thing You Can Do Is Not Show Up
September 28, 2017 —
Christopher G. Hill - Construction Law MusingsAs long time (and possibly recent) readers of Construction Law Musings know, I am a Virginia Supreme Court Certified Mediator. In that capacity, I spend quite a bit of time sitting in general district court courtrooms in places like Goochland and Caroline Counties “court sitting” awaiting a referral from the judge of a case with parties ready and willing to take advantage of the mediation process.
As I sit there wearing my mediator “hat,” I see case after case be called for the first return date. Without fail, several cases are called where the defendant fails to appear after being served with process. There are even a case or two where the plaintiff (the party that picked the return date in the first place) fails to appear. In the first instance, where the defendant doesn’t appear, the judge almost inevitably enters a judgment for the amount sued for by the plaintiff. In the latter instance, the case is dismissed without prejudice to the plaintiff with a shake of the head by the judge at the wasted time and filing fee. This post focuses on the first case.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Offices of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Key Takeaways For Employers in the Aftermath of the Supreme Court’s Halt to OSHA’s Vax/Testing Mandate
January 24, 2022 —
Laura H. Corvo - White and Williams LLPPolitical pundits and legal scholars have been engaged in frenzied debate trying to decipher the fallout of the United States Supreme Court’s decision that stopped stopped the Occupational Safety and Hazard Administration (OSHA) from enforcing its Emergency Temporary Standard (ETS) which mandated that employers with 100 or more employees require workers to show proof of vaccination against COVID-19 or submit to weekly testing. The Court’s decision prevents OSHA from enforcing its ETS until all legal challenges have been heard. Because the Court concluded that those legal challenges are “likely to succeed on the merits” of their argument that OSHA does not have the statutory authority to issue its vaccine and testing mandates, there is significant doubt that they will ever come to fruition.
While the pundits and scholars have now had their say, employers, who are struggling to manage a highly contagious variant, a tight labor market, and employees with divergent and staunch views on vaccination, are also left wondering what the Court’s decision means for them and what they should be doing. Here are some key takeaways for employers in the aftermath of the Court’s decision.
Read the court decisionRead the full story...Reprinted courtesy of
Laura H. Corvo, White and Williams LLPMs. Corvo may be contacted at
corvol@whiteandwilliams.com
Insurer's Motion to Dismiss Allegations of Collapse Rejected
August 08, 2018 —
Tred R. Eyerly - Insurance Law HawaiiIn yet another of the collapse cases being litigated in state and federal courts in Connecticut, the federal district court denied the insurer's motion to dismiss. Rosenberger v. Amica Mut. Ins. Co., 2018 U.S. Dist. LEXIS 95345 (D. Conn. June 6, 2018).
The insureds had policies with Amica since 1989. Policies before December 18, 2006, covered collapse caused by hidden decay or other specified causes. "Collapse" was not defined by the policy. These policies did not include any provisions explicitly excluding coverage for a chemical reaction.
The post-2006 policies held by the insureds covered collapse, but under a significantly modified definition. The newer policy language stated that "collapse applies only to an abrupt collapse." Further, collapse was defined as "an abrupt falling down or caving in of a building or any part of a building with the result that the building or part of the building cannot be occupied for its intended purpose."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Construction Termination Issues Part 4: What to Do When They Want to Fire You, the Architect or Engineer
August 14, 2023 —
Melissa Dewey Brumback - Construction Law in North CarolinaWhat if you are told that your own design services are no longer needed or welcome on a project? Can they do that? What happens then? How do you protect yourself.
As you probably realize, while rare, the Owner does have the legal right to fire you “for cause”. See B101 §9.4, as long as the Owner gives you 7 days written notice. In fact, the Owner can terminate your contract for any reason at all (maybe you root for the wrong basketball team?) by terminating you for convenience (i.e., for any reason whatsoever) under B101 §9.5, again with 7 days written notice.
As with
Contractor terminations, the money you get when fired for convenience is much greater than when you are terminated for cause. If you are fired “for convenience”, you get paid for all services previously rendered as well as termination expenses, including anticipated profit on the value of services not performed. See B101 §9.7.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale LiggettMs. Brumback may be contacted at
mbrumback@rl-law.com
Engineer Probing Champlain Towers Debacle Eyes Possibility of Three Successive Collapses
July 05, 2021 —
Nadine M. Post - Engineering News-RecordThough the trigger may remain a mystery for some time, by the end of the week, the structural engineer probing the partial progressive collapse of a 40-year-old Surfside, Fla., residential condominium expects to complete a computer model of the unstable, 12-story remains of the building. The computer model of the still-standing wing of Champlain Towers South will initially be used to alert the search and rescue team to suspend operations if a hurricane is coming.
Reprinted courtesy of
Nadine M. Post, Engineering News-Record
Ms. Post may be contacted at postn@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Buyer Beware: Insurance Agents May Have No Duty to Sell Construction Contractors an Insurance Policy Covering Likely Claims
May 20, 2024 —
David McLain - Higgins, Hopkins, McLain & Roswell, LLCConstruction contractors in the market for insurance coverage have few legal protections if their insurance agent fails to provide insurance that covers likely claims against the contractor. As construction defect lawsuits continue to be a frequent occurrence throughout Colorado, we have seen an increase in the number and complexity of coverage endorsements and exclusions in insurance policies. Some of these exclusions result in insurance policies that are essentially useless to the contractor who purchased them. For example, we have seen dirt work contractors with earth movement exclusions or an earth movement sublimit that turns their $2 million policy into a $100,000 policy. We have seen contractors who primarily build tract homes in subdivisions with tract home exclusions. We have seen general contractors whose policies state that every subcontractor must name the contractor as an additional insured or else the general contactor’s policy converts from a seven-figure policy to a five-figure policy with eroding limits (meaning that the attorney’s fees, expert fees, and litigation costs reduce the coverage limits). The list goes on and leads to an unfortunately high number of contractors who pay significant sums for their insurance policies, finding themselves uninsured or underinsured.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com