DOD Contractors Receive Reprieve on Implementation of Chinese Telecommunications Ban
September 14, 2020 —
Lori Ann Lange & Sabah Petrov - Peckar & AbramsonIn our previous
alert, we discussed the expansion on the Section 889(a)(1)(B) ban on certain Chinese telecommunications equipment and services to contractors and subcontractors who use the equipment and services in their internal operations. Effective August 13, 2020, federal agencies were prohibited from procuring, obtaining, extending, or renewing a contract with a contractor that uses equipment, systems, or services that use covered telecommunications equipment or services as a substantial or essential component or as critical technology, unless an exception applies or a waiver is granted. Since then we have received feedback from contractors, complaining about the difficulties in determining whether their internal operations use covered telecommunications equipment and services and the need for additional time to become compliant or even obtain enough information to submit a waiver request.
Now it seems that Department of Defense (DoD) contractors and subcontractors may be getting a temporary reprieve. The DoD Under Secretary for Acquisition and Sustainment requested a waiver that would allow DoD to continue to execute procurement actions providing supplies, equipment, services, food, clothing, transportation, care, and support necessary to execute the DoD mission. The Director of National Intelligence granted the temporary waiver until September 30, 2020 pending a further review of waiver request. Depending upon the outcome of this additional review, the temporary waiver may be continued beyond September 30, 2020 if it is in the national security interests of the United States.
Reprinted courtesy of
Lori Ann Lange, Peckar & Abramson and
Sabah Petrov, Peckar & Abramson
Ms. Lange may be contacted at llange@pecklaw.com
Ms. Petrov may be contacted at spetrov@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
More Broad-Based Expansion for Construction Industry Expected in 2015
January 07, 2015 —
Garret Murai - California Construction Law BlogIt’s a short week for most of us this week.
Christmas is over and New Year’s is approaching.
So, what will 2015 bring us?
According Dodge Data & Analytics’s 2015 Dodge Construction Outlook: Continuing expansion of the construction sector, but one that is more broad-based than in recent years.
“The economic environment going forward carries several positives that will help to further lift total construction starts,” said Robert Murray, Chief Economist and Vice President at Dodge Data & Analytics. “Financing for construction projects is becoming more available, reflecting some easing of bank lending standards, a greater focus on real estate development by the investment community, and more construction bond measures getting passed. While federal funding for construction programs is still constrained, states are now picking up some of the slack. Interest rates for the near term should stay low, and market fundamentals (occupancies and rents) for commercial building and multifamily housing continue to strengthen.”
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Embattled SNC-Lavalin Files Ethics Appeal, Realigns Structure
May 01, 2019 —
Debra K. Rubin - Engineering News-RecordEven as Montreal design-build giant SNC-Lavalin Group Inc. faces corporate bribery charges on old Libya contracts, the firm now seeks, in an April 4 federal court appeal, to reverse Canadian prosecutors’ 2018 rejection of a negotiated settlement.
Read the court decisionRead the full story...Reprinted courtesy of
Debra K. Rubin, ENRMs. Rubin may be contacted at
rubind@enr.com
Sometimes, Being too Cute with Pleading Allegations is Unnecessary
June 06, 2018 —
David Adelstein - Florida Construction Legal UpdatesThere are times where being too darn cute with your pleading allegations is unnecessary and does not work. But, the point is really that the cuteness is unnecessary.
In a Miller Act payment bond dispute in Boneso Brothers Construction, Inc. v. Sauer, Inc., 2018 WL 2387833 (N.D.Cal. 2018), a claimant asserted claims against a Miller Act payment bond surety for breach of the payment bond, breach of a subcontract, open account, and account stated. The question is why would the claimant sue the payment bond surety for breach of subcontract (when the subcontract was not with the surety), and open account and account stated. I have no clue, other than such claims appeared quite unnecessary when the claimant asserted an action on the Miller Act payment bond (which is what the surety is liable under — actions under the statutory payment bond). Such claims were dismissed. And, they should have been.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Sinking Buildings on the Rise?
July 01, 2019 —
Jason M. Adams - Gibbs GidenBy now everyone in the construction and insurance industries is familiar with the 58-story Millennium Tower building in San Francisco that has sunk 17 inches and tilted another 14 inches to the northwest. Another recent New York lawsuit alleges that a 58-story luxury Manhattan condo high-rise is also sinking and causing significant damage. With construction booming in the Southeast and other areas with questionable soils, sinking building cases may be on the rise. Given this reality, the issue of subsidence should be of paramount importance to every construction and insurance professional when insuring a project.
Most insurance carriers will include a subsidence and/or other earth movement exclusion on a commercial general liability ("CGL") quote for insurance as a matter of course. Construction professionals (owners/developers, general contractors, and subcontractors) or their brokers may be under the mistaken impression that they have no choice but to accept these subsidence exclusions as part of a standard construction policy. This is not the case. To the contrary, most insurance carriers are willing to remove subsidence exclusions if the underwriters are provided with acceptable geotechnical/soils reports when considering the project.
The insured construction professional often pushes back on the insurance carrier's request for soils reports because the insured sees the request as an unnecessary hassle, expense or unwelcome interference in the job. However, the carrier's soils review is designed to benefit everyone. If potential soils issues are discovered during the underwriting process they can be addressed at the outset of the project rather than after the project is built, which will typically cost substantially more to remedy. Moreover, a thorough analysis of the condition of the soils at the outset of the project allows the risk management team to recognize any potential issues and ensure that the proper coverage is obtained in order to provide protection down the road. Even if the insurance carrier charges more money to sign off on questionable soils after a review of the reports, the slight increase in premium is likely a worthwhile investment in the event of a subsidence loss.
The lesson is that the insured should not blindly accept a subsidence exclusion and should negotiate its removal. The insured should provide its broker and the insurance carrier the information they need in order to make a fully-informed decision as it pertains to the soils. Once the insurance carrier has had the opportunity to review and sign off on the condition of the soil, the carrier should feel comfortable enough to remove any subsidence exclusions or other similar earth movement limitations.
Subsidence is a relatively straightforward issue to deal with as long as the project team’s lawyers, brokers, risk managers and insurance company underwriters are working together toward the common goal of properly evaluating the risk and adequately insuring the project. This simple cooperative process between the entire risk management team could mean the difference between being covered or not covered in the event of a loss related to earth movement.
Jason M. Adams, Esq. is Senior Counsel at Gibbs Giden representing construction professionals (owners/developers, contractors, architects, etc.) in the areas of Construction Law, Insurance Law and Risk Management, Common Interest Community Law (HOA) and Civil Litigation. Adams is also a licensed property and casualty insurance broker and certified Construction Risk & Insurance Specialist (CRIS). Gibbs Giden is nationally and locally recognized by U. S. News and Best Lawyers as among the “Best Law Firms” in both Construction Law and Construction Litigation. Chambers USA Directory of Leading Lawyers has consistently recognized Gibbs Giden as among California’s elite construction law firms. Mr. Adams can be reached at jadams@gibbsgiden.com.
The content contained herein is published online for informational purposes only, may not reflect the most current legal developments, verdicts or settlements, and does not constitute legal advice. Do not act on the information contained herein without seeking the advice of licensed counsel. The transmission of information by email, or any transmission or exchange of information over the Internet, or by any of the included links is not intended to create and does not constitute an attorney-client relationship. This publication may not be reproduced or used in whole or in part without written consent of the author. Copyright 2019 ©
Read the court decisionRead the full story...Reprinted courtesy of
Ninth Circuit Finds Policy’s Definition of “Policy Period” Fatal to Insurer’s “Related Claims” Argument
April 10, 2019 —
Jason M. Taylor - TLSS Insurance Law BlogProfessional liability policies often include some form of a “related claims” or “related acts” provision stating that if more than one claim results from a single wrongful act, or a series of related wrongful acts, such claims will be treated as a single claim and deemed first made during the policy period in which the earliest claim was made. These provisions can have significant implications on the applicable policy and policy limits, retroactive date issues, and whether such claims were first made and reported during a particular policy period. Recently, the Ninth Circuit issued a stern reminder of how the particular policy language can effect, and in this case thwart, the intended scope of the carrier’s “related claims” provision.
In Attorneys Ins. Mut. Risk Retention Grp., Inc. v. Liberty Surplus Ins. Corp., 2019 WL 643442 (9th Cir. Feb. 15, 2019), the Ninth Circuit construed a “related claims” provision included in two consecutive lawyers professional liability policies. During both the 2009–2010 and 2010–2011 insurance policy periods, attorney J. Wayne Allen (“Allen”) was insured through his employer by Liberty Surplus Insurance Corporation’s (“Liberty”) professional liability insurance. Third parties filed suit against Allen during the 2009–2010 policy period in a probate case, and a second, related civil suit during the 2010–2011 policy period.
Read the court decisionRead the full story...Reprinted courtesy of
Jason M. Taylor, Traub LiebermanMr. Taylor may be contacted at
jtaylor@tlsslaw.com
Sweet News for Yum Yum Donuts: Lost Goodwill is Not an All or Nothing Proposition
October 07, 2019 —
Josh Cohen - California Construction Law BlogLast month a California Court of Appeals clarified that a property owner facing eminent domain is only required to prove partial loss of goodwill, not total loss of goodwill, to be entitled to a trial on the amount of goodwill lost.
Yum Yum Donuts operated a shop in Los Angeles that was subject to eminent domain by the Los Angeles Metropolitan Transportation Authority (MTA) to make way for light railway track. At trial, Yum Yum sought loss of goodwill as part of its condemnation damages under Code of Civil Procedure section 1263.510.
At trial the MTA’s expert testified that Yum Yum could have reduced its goodwill loss if it relocated to one of three alternative locations rather than simply closing the shop. But the expert conceded that even if Yum Yum had relocated, it would have lost some goodwill. Yum Yum refused to relocate, arguing that its relocation costs would render the move unprofitable. The trial court found that Yum Yum’s failure to mitigate its damages barred Yum Yum from having a jury trial to recover any goodwill damages.
Read the court decisionRead the full story...Reprinted courtesy of
Josh Cohen, Wendel, Rosen, Black & Dean LLPMr. Cohen may be contacted at
jcohen@wendel.com
U.S. Supreme Court Halts Enforcement of the OSHA Vaccine or Test Mandate
January 17, 2022 —
Stephen E. Irving, Kevin J. O’Connor, Aaron C. Schlesinger & Lauren Rayner Davis - Peckar & AbramsonThe United States Supreme Court today stayed enforcement of the OSHA emergency temporary standard (ETS) requiring employers with 100 or more employees to require employees either be “fully vaccinated” against COVID-19 or submit to weekly testing. The ruling immediately stops enforcement of the rule which had gone into effect on January 10, 2022.
Today’s order raises significant doubt as to whether the ETS requirement will ever take effect in its current form. A 6 to 3 majority of the Supreme Court justices issued the profound statement that the parties opposed to the rule “are likely to succeed on the merits of their claim that the Secretary lacked authority to impose the mandate.” The Court went on to state that the OSH Act does not authorize the agency to “set . . . broad public health measures,” such as the found in the current emergency standard.
Reprinted courtesy of
Stephen E. Irving, Peckar & Abramson,
Kevin J. O’Connor, Peckar & Abramson,
Aaron C. Schlesinger, Peckar & Abramson and
Lauren Rayner Davis, Peckar & Abramson
Mr. Irving may be contacted at sirving@pecklaw.com
Mr. O'Connor may be contacted at koconnor@pecklaw.com
Mr. Schlesinger may be contacted at aschlesinger@pecklaw.com
Ms. Davis may be contacted at ldavis@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of