Options When there is a Construction Lien on Your Property
June 02, 2016 —
David Adelstein – Florida Construction Legal UpdatesThere is a construction lien on my property. What are my best options? I hear this question quite a bit…so here it goes…
(1) Do nothing. That’s right – do nothing. If you are not looking to sell your house or refinance in the next year or so, you can do nothing and see whether the lienor files a construction lien foreclosure lawsuit. The lienor has one year from the recording of the lien to file the lawsuit.
(2) Record a
Notice of Contest of Lien. The
Notice of Contest of Lien shortens the lienor’s statue of limitations to foreclose on the lien from one year to 60 days. If the lienor fails to foreclose on the lien within 60 days, the lien is extinguished by operation of law. This is the route I tend to prefer. If the lienor is going to file a lien foreclosure lawsuit, I tend to think it is better forcing the issue on the front end as opposed to waiting a year. But every situation is different.
Read the court decisionRead the full story...Reprinted courtesy of
David M. Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Injury to Employees Endorsement Eliminates Coverage for Insured Employer
February 01, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe court granted summary judgment to the insurer based upon an endorsement which barred coverage for injuries to employees. Northfield Ins. Co. v. Z&J Mgt. LLC, 2020 N.Y. Misc. LEXIS 10801 (N.Y. Sup. Ct. Dec. 18, 2020).
Ravi Sooklal sued his employer, Z&J Management LLC (Z&J), for injuries at the job site. Northfield, who had issued a CGL policy to Z&L, denied coverage based upon two endorsements. The first was titled "Injury to Employees of Insureds" and the second was "Employers' Liability." Northfield sued for a declaratory judgment and now moved for summary judgment.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Real Estate & Construction News Roundup (8/14/24) – Commercial Real Estate AI, Hotel Pipeline Growth, and Housing Market Improvements
September 23, 2024 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, nonresidential spending drops, realtor payment structure changes, office vacancy rates soar, and more!
- A decline in mortgage rates and a drop in housing prices are giving buyers a potential path to securing homeownership. (Omar Mohammed, Newsweek)
- Starting August 17, new rules will roll out that overhaul the way Realtors get paid to help people buy and sell their homes. (Samantha Delouya, CNN)
- Spending dropped in almost half of nonresidential subcategories in June with the decrease stemming from higher interest rates, tighter credit conditions and a softening economy. (Sebastian Obando, Construction Dive)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Untangling Unique Legal Issues in Modern Modular Construction
September 09, 2024 —
Chad Theriot & Brad Sands - Construction ExecutiveModular construction has grown significantly over the last few years and shows no signs of slowing down. This construction method is a departure from traditional approaches where all construction activity occurs onsite. Modular construction involves building standardized project components—usually in an offsite, controlled environment—which are then transported and assembled at the project site. Offsite construction generally allows for better quality control and economic efficiency, as it can utilize an assembly-line process. Modular fabrication can also centralize skilled labor in regions with lower labor costs.
Establishing each party's expectations upfront is always important, but even more so in modular construction since much of the construction activity is performed away from the ultimate project site. This requires extensive coordination among designers, fabricators, installers and owners to ensure construction, testing and quality progresses accordingly. Every field change and design clash could have an exponential impact on the modular fabrication efficiencies given the assembly-line approach and remote nature of modular work.
Reprinted courtesy of
Chad Theriot & Brad Sands, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Reminder: In Court (as in life) the Worst Thing You Can Do Is Not Show Up
September 28, 2017 —
Christopher G. Hill - Construction Law MusingsAs long time (and possibly recent) readers of Construction Law Musings know, I am a Virginia Supreme Court Certified Mediator. In that capacity, I spend quite a bit of time sitting in general district court courtrooms in places like Goochland and Caroline Counties “court sitting” awaiting a referral from the judge of a case with parties ready and willing to take advantage of the mediation process.
As I sit there wearing my mediator “hat,” I see case after case be called for the first return date. Without fail, several cases are called where the defendant fails to appear after being served with process. There are even a case or two where the plaintiff (the party that picked the return date in the first place) fails to appear. In the first instance, where the defendant doesn’t appear, the judge almost inevitably enters a judgment for the amount sued for by the plaintiff. In the latter instance, the case is dismissed without prejudice to the plaintiff with a shake of the head by the judge at the wasted time and filing fee. This post focuses on the first case.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Offices of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Remote Trials Can Control Prejudgment Risk
September 07, 2020 —
Robert G. Devine, Victor J. Zarrilli & Kimberly M. Collins - White and Williams LLPWhile courts across the country are largely unavailable to litigants demanding a jury trial, pre-judgment interest rules present an increasing penalty risk to a defendant wanting its day in court and may not always make a plaintiff whole. The COVID-19 pandemic has altered the manner in which people and industries operate across the board. In light of the need to maintain social distancing whenever possible, the use of technology to replace in-person appearances is becoming more commonplace. As more attorneys become comfortable with the remote platform, the willingness to consider a remote trial grows.
With in-person jury trials suspended until further notice, it is important for attorneys and parties to consider the attendant consequences of the indefinite delay in waiting for a traditional jury trial. Aside from general inconvenience, continued delays may have a substantial financial impact, particularly with regard to the accumulation of pre-judgment interest.
Reprinted courtesy of White and Williams LLP attorneys
Robert G. Devine,
Victor J. Zarrilli and
Kimberly M. Collins
Mr. Devine may be contacted at deviner@whiteandwilliams.com
Mr. Zarrilli may be contacted at zarrilliv@whiteandwilliams.com
Ms. Collins may be contacted at collinsk@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Recent Supreme Court Decision Could Have Substantial Impact on Builders
January 23, 2023 —
Cassidy Ingram - Ahlers Cressman & SleightOn October 27, 2022, the Washington State Supreme Court issued a decision which could have a substantial impact on the enforceability of contract clauses that require litigation to be commenced within a stated period of time from project completion. In Tadych v. Noble Ridge Construction, Inc.,the Supreme Court held that the contractual one-year statute of limitations for bringing claims against the contractor was substantively unconscionable and reversed the Court of Appeals.
In Tadych, plaintiff owners (the Tadychs) contracted with defendant contractor (Noble Ridge Construction, Inc., or NRC) for the construction of a custom home in 2012. The contract included a one-year claim limitations clause that required claims to be raised within a one year period from project completion and that any claims not raised during the one-year period would be waived. In December 2013, as the project neared completion, the Tadychs met with NRC to identify any outstanding project issues. The Tadychs noted several, including rainwater pools at the landing at the bottom of the stairs and several nicks and cracks on the stucco exterior walls.
The Tadychs moved into the home on April 8, 2014, and the City of Seattle Department of Planning and Development conducted its final site inspection on April 15 and approved the residence for occupancy on April 23. In January or February of 2015, the Tadychs began to notice a shift in their home. In February of 2015, the Tadychs engaged the Construction Dispute Resolution (CDR) to review NRC’s work. CDR raised concerns about the adequacy of the home’s construction and prepared a written report in March 2015 indicating several deviations from the architectural plans and building codes. The Tadychs sent this report to NRC, who assured the Tadychs that NRC’s work followed all requirements and rejected any claims that there were deviations from the plans. The Tadychs continued to notice issues with the home through October 2016.
Read the court decisionRead the full story...Reprinted courtesy of
Cassidy Ingram, Ahlers Cressman & SleightMs. Ingram may be contacted at
cassidy.ingram@acslawyers.com
Supply Chain Delay Recommendations
August 07, 2022 —
Denise Motta - Gordon & Rees Construction Law BlogThis Bulletin provides guidance to contractors, subcontractors, suppliers, and others to ensure compliance with contractual change order requirements in the event work on a construction project is impacted by supply chain delays.
Contract Protection Tips:
The construction industry is being impacted substantially by inability to obtain necessary construction products due to supply chain issues. Most construction contracts do not accommodate time extensions due to supply chain impacts. To address this gap in contract terms, we recommend including language such as: “lack of or failure of or other inability to obtain necessary transportation, fuel, power, materials, machinery, equipment or facilities, delays caused by other contractors, subcontractors or their subcontractors of any tier, or any materialmen or suppliers” as part of the defined force majeure event under the contract.
This provision can be included in the Change Order section of the contract as well by including a provision such as: “If the Work is delayed by the failure of or other inability to obtain necessary transportation, fuel, power, materials, machinery, equipment or facilities, delays caused by other contractors, subcontractors or their subcontractors of any tier, or any materialmen or suppliers, contractor shall be entitled to a change order for its costs and time associated with the delay.”
Read the court decisionRead the full story...Reprinted courtesy of