Standard For Evaluating Delay – Directly from An Armed Services Board Of Contract Appeal’s Opinion
October 04, 2021 —
David Adelstein - Florida Construction Legal UpdatesSometimes, it is much better to hear it from the horse’s mouth. That is the case here. The Armed Services Board of Contract Appeal’s (ASBCA) opinion in Appeals of -GSC Construction, Inc., ASBCA No. 59402, 2020 WL 8148687 (ASBCA November 4, 2020) includes an informative discussion of a contractor’s burden when it encounters excusable delay and, of importance, the standard for evaluating delay. It’s a long discussion but one that parties in construction need to know, appreciate, and understand. EVERY WORD IN THIS DISCUSSION MATTERS.
Construction projects get delayed and with a delay comes money because time is money. Many claims are predicated on delay. These can be an owner assessing liquidated damages due to a delayed job or a contractor seeking its costs for delay. Either way, the standard for evaluating delay and the burdens imposed on a party cannot be understated and, certainly, cannot be overlooked. For this reason, here is the discussion on evaluating delay directly from the horse’s mouth in the Appeal of-GSC Construction, Inc.:
The critical path is the longest path in the schedule on which any delay or disruption would cause a day-for-day delay to the project itself; those activities must be performed as they are scheduled and timely in order for the project to finish on time. Wilner v. United States, 23 Cl. Ct. 241, 245 (1991). In Yates-Desbuild Joint Venture, CBCA No. 3350 et al., 17-1 BCA ¶ 36,870, our sister board compiled an excellent and very helpful synopsis of the standards for evaluating delay claims, which I adopt nearly verbatim among the discussion that follows.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
SEC Proposes Rule Requiring Public Firms to Report Climate Risks
April 11, 2022 —
Debra K. Rubin - Engineering News-RecordThe U.S. Securities and Exchange Commission issued a proposal March 21—both anticipated and feared—that would require publicly-traded companies to standardize disclosure for the first time of climate-related business risks such as those related to severe weather and decarbonization. Exchange-listed firms would also have to report greenhouse gas emissions, their own and in the supply chain, creating a major reporting mandate. The rules also apply to firms listed on overseas exchanges that operate in the U.S.
Reprinted courtesy of
Debra K. Rubin, Engineering News-Record
Ms. Rubin may be contacted at rubind@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Manhattan to Add Most Office Space Since ’90 Over 3 Years
June 18, 2014 —
Jonathan LaMantia – BloombergManhattan is poised to add the most office space in any three-year period since 1990 as projects including buildings at Hudson Yards and the World Trade Center site are completed, the New York Building Congress said.
The borough, home to the largest U.S. office market, probably will add 9 million square feet (836,000 square meters) of office space at nine development sites from last year through 2015, according to the organization, which promotes construction in the New York City area. An additional 10 million square feet at six buildings is likely to become available from 2016 through 2018, the group said in a statement today.
“It’s a vote of confidence in the market, which we think is long overdue,” Richard T. Anderson, president of the New York Building Congress, said in a telephone interview. “As a global center of finance and office-related functions, the city needs to regenerate its office space.”
Read the court decisionRead the full story...Reprinted courtesy of
Jonathan LaMantia, BloombergMr. LaMantia may be contacted at
jlamantia1@bloomberg.net
Are Defense Costs In Addition to Policy Limits?
December 02, 2015 —
Craig Martin – Construction Contractor AdvisorI recently had a discussion with an insurer about whether defense costs were included within the policy limits of a client’s coverage or in addition to policy limits. This was an important discussion because if costs of defense were included in the policy limits, my client was going to exceed those policy limits in a hurry. How would this situation play out with your insurance?
Fortunately, the majority of insurance policies, such as Commercial General Liability (CGL) policies, provide that defense costs are “in addition” to the policy limits. But some policies, often times referred to as “burning limits” policies, provide that cost of defense is included in the policy limits. This means that if you have $1,000,000.00 policy limits, your costs of defense will reduce that limit throughout the course of litigation.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Las Vegas HOA Conspiracy & Fraud Case Delayed Again
September 17, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to the Las Vegas Review-Journal, “[T]he federal trial of former construction company boss Leon Benzer and five others in a massive scheme to take over Las Vegas-area homeowners associations” has been delayed to February 2015 by U.S. District Judge James Mahan.
Defense attorneys “argued they needed more time to review thousands of pages of new documents provided by prosecutors.” The prosecutors did not object to the delay.
Benzer and the other defendants face conspiracy and fraud charges in an HOA takeover scheme that allegedly occurred between 2003 and 2009.
Read the court decisionRead the full story...Reprinted courtesy of
Top 10 Lessons Learned from a Construction Attorney
February 18, 2015 —
Craig Martin – Construction Contractor AdvisorI have had the pleasure of working with
Cordell Parvin, who in his earlier career was a preeminent construction attorney, and now,
coaches attorneys. Cordell has shared countless construction guides and presentations with me over the years, for which I am extremely grateful. Below is Cordell’s Lesson’s Learned list, that is as true today as when he drafted it years ago.
1. Contracts and owners are not all alike. Some are fairer than others. Some create greater risks of making the budget if we encounter changes, delays and impacts. We should appreciate the risks before bidding and not underestimate indirect costs of staff to deal with these situations.
2. It is important to have a thorough understanding of the Contract Administration requirements of complex contracts. Identifying specifically what must be done when changes, delays and differing site conditions are encountered is one way to establish the understanding.
3. If a project ever ends up in court, every letter, note, e-mail and memo is evidence and will be taken out of context by the opposing lawyer. Recording every mistake, miscalculation, problem or lesson learned during construction of the project will come back to haunt you.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
California’s Fifth Appellate District Declares the “Right to Repair Act” the Exclusive Remedy for Construction Defect Claims
September 03, 2015 —
Stephen A. Sunseri – Gatzke Dillon & Balance LLPAugust 26, 2015 - The Fifth Appellate District ruled SB800 (California's "Right to Repair Act" [the "Act"]) provides the sole remedy for homeowners in construction defect actions. The court found "no other cause of action is allowed to recover for repair of the defect itself or for repair of any damage caused by the defect." (McMillin Albany LLC v. Superior Court of California (Aug. 26, 2015, No. F069370) __ Cal.App.4th __ [2015 WL 5029324].) The court issued a blistering criticism of the Fourth Appellate District's prior opinion in Liberty Mutual Ins. Co. v. Brookfield Crystal Cove LLC (2013) 219 Cal.App.4th 98, which severely limited the reach of the Act to actions not involving property damage and allowing property damage claims to proceed freely under common law without any constraints posed by the Act.
In McMillin, the court reviewed whether a homeowner was required to follow the Act's prelitigation procedures even after dismissing a cause of action arising under the Act. In deciding the issue, the court quoted directly from the first line of the Act (Civ. Code § 896) and found "[i]n any action seeking recovery of damages arising out of, or related to deficiencies in, the residential construction … , the claimant's claims or causes of action shall be limited to violation of" the standards set out in the Act. The court recognized the statutory exceptions to this rule, such as for claims arising under contract, or any action for fraud, personal injuries, or statutory violations. (Civ. Code., § 943.) However, this result directly conflicts with the Fourth Appellate District's decision in Liberty Mutual, which found homeowners can circumvent the entire Act by simply alleging property damage claims. McMillin rejects Liberty Mutual's "reasoning and outcome" as being inconsistent with the express language of the Act.
McMillin found that Liberty Mutual failed to fully analyze the statutory language of the Act, which (on its face) limits any action for construction deficiencies to the requirements of the Act. McMillin concludes the Legislature intended that all construction defect actions (for new residences sold on or after January 1, 2003), are subject to the requirements of the Act, including the prelitigation procedures, regardless of whether a complaint expressly alleges a cause of action under the Act or not.
McMillin is a great victory for homebuilders, but battle lines are now clearly drawn between the two appellate districts. McMillin directly conflicts with Liberty Mutual, and because of this conflict, the issue will need to be resolved by the California Supreme Court. Until such review is granted, the conflict will remain and trial courts will likely continue to conflate the issue.
Read the court decisionRead the full story...Reprinted courtesy of
Stephen A. Sunseri, Gatzke Dillon & Balance LLPMr. Sunseri may be contacted at
ssunseri@gdandb.com
Court Finds Duty To Defend Environmental Claim, But Defense Limited to $100,000
August 14, 2023 —
Tred R. Eyerly - Insurance Law HawaiiWhile agreeing with the insured there was a duty to defend, the court determined the defense of an environmental claims was limited to $100,000. Casa Nido Partnership v. JAE Kwon, 2023 U.S. Dist. LEXIS 97701 (N.D. Calif. June 5, 2023).
In 1976, Casa Nido purchased the property and remains the current owner to this day. Catherine O'Hanks owned and operated a dry-cleaning facility at the property from 1960 to 1992.
In August 2016, Casa Nido learned of Tetrachloroethylene (PCE) subsurface contamination. Casa Nido stipulated that it did not know, nor had any reason to know, before 2016, of the existence of the subsurface contamination. Casa Nido alleged that due to equipment malfunction or improper usage, there were sudden and accidental spills and equipment overflows of PCE during the 32-year period that defendant O'Hanks operated the dry-cleaning business on the property. Casa Nido spent hundreds of thousands of dollars remediating the environmental damage.
Read the court decisionRead the full story...Reprinted courtesy of