Unjust Enrichment and Express Contract Don’t Mix
August 23, 2021 —
Christopher G. Hill - Construction Law MusingsI am a huge fan of clearly written construction contracts. Virginia state and federal courts will interpret contract provisions as written and will seek to enforce all of those terms where possible. Where the contract is ambiguous, we construction attorneys make money and the courts are forced to make decisions that the parties may not like.
A recent case out of the Eastern District of Virginia federal court highlights the ways in which a clear contract affects the claims that can be brought and limits the scope of possible litigation. In First Call Environmental LLC v. Murphy Oil USA LLC, the Court looked at a relatively typical Owner, Contractor, Subcontractor set of agreements. In this matter, Murphy Oil entered a contract with National Rapid Response, Inc. (“NRR”) whereby NRR would provide emergency and environmental management and waste disposal services to Murphy Oil. NRR then subcontracted with the Plaintiff First Call to perform the services for Murphy Oil. First Call filed suit against Murphy Oil alleging two counts: breach of contract (based on a third-party beneficiary theory), and unjust enrichment.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Recommencing Construction on a Project due to a Cessation or Abandonment
October 26, 2017 —
David Adelstein - Florida Construction Legal UpdatesThere are instances where the owner of a construction project terminates its general contractor prior to the completion of the project. There are instances where the owner suspends the work prior to the completion of the project, meaning there is a cessation in the construction. And, there are instances where the project is simply abandoned. I have been involved in all instances, and the owner’s reasons vary…from an owner claiming a termination for default, termination for convenience, or a suspension or abandonment due to the market or financial factors. Regardless of the owner’s reasoning, at some point—hopefully—the owner will want to resume or, more properly stated, recommence construction and complete the project.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
How the Cumulative Impact Theory has been Defined
November 30, 2020 —
David Adelstein - Florida Construction Legal UpdatesLargely in the federal contract arena, there is a theory referred to as “cumulative impacts” used by a contractor to recover unforeseeable costs associated with a multitude of changes that have an overwhelming ripple effect on its efficiency, particularly efficiency dealing with its original, base contract work. In other words, by dealing with extensive changes, there is an unforeseeable impact imposed on the contractor relative to its unchanged or base contract work. Under this theory, the contractor oftentimes prices its cumulative impact under a total cost approach with an examination on its cost overrun. However, this is not an easy theory to prevail on because there needs to be a focus on the sheer number of changes, causation supporting the impact, and whether there were concurrent impacts or delays that played a role in the ripple effect. See, e.g., Appeals of J.A. Jones Const. Co., ENGBCA No. 6348, 00-2 BCA P 31000 (July 7, 2000) (“However, in the vast majority of cases such claims are routinely denied because there were an insufficient number of changes, contractor-caused concurrent delays, disruptions and inefficiencies and/or a general absence of evidence of causation and impact.”).
To best articulate how the cumulative impact theory has been defined, I want to include language directly from courts and board of contract appeals that have dealt with this theory. This way the contractor knows how to best work with their experts with this definition in mind–and, yes, experts will be needed–to persuasively package and establish causation and damages stemming from the multitude of changes. While many of these definitions are worded differently, you will see they have the same focus dealing with the unforeseeable ripple effect of the extensive changes.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
The Fifth Circuit, Applying Texas Law, Strikes Down Auto Exclusion
July 11, 2022 —
Jeremy S. Macklin - Traub Lieberman Insurance Law BlogPenn-America Ins. Co. v. Tarango Trucking, LLC, 30 F.4th 440 (5th Cir. 2022), involved a coverage dispute over Penn-America Insurance Company’s (“Penn-America”) duty to defend and indemnify third-party claims against Tarango Trucking, LLC (“Tarango”) for a fatal accident on its property. At the time of the accident, Penn-America insured Tarango under a commercial general liability policy, which included an “Auto Exclusion” and “Parking Exception” provision. The Auto Exclusion stated the policy did not apply to bodily injury or property damage arising out of the use of any automobile, including the operation and loading or unloading. The Parking Exception stated the Auto Exclusion did not apply to parking an auto on Tarango’s premises. The main issues on appeal were whether the Parking Exception restored coverage otherwise precluded by the Auto Exclusion, and whether the district court prematurely decided Penn-America’s duty to indemnify. The appellate court answered yes to both.
On March 2, 2020, a truck driver employed by WS Excavation, LLC (“WS”), parked his tractor-trailer on Tarango’s property and proceeded to inspect and off-load heavy equipment. While operating the hydraulic lift, the tractor’s braking system disengaged. The tractor rolled back and struck the WS driver and his personal vehicle, resulting in his death and significant property damage. Notably, WS allegedly failed to properly maintain the tractor’s electronic and braking systems, and Tarango allegedly failed to maintain a level parking and loading facility compliant with industry standards and guidelines.
Read the court decisionRead the full story...Reprinted courtesy of
Jeremy S. Macklin, Traub LiebermanMr. Macklin may be contacted at
jmacklin@tlsslaw.com
Sometimes You Just Need to Call it a Day: Court Finds That Contractor Not Entitled to Recover Costs After Public Works Contract is Invalidated
June 29, 2020 —
Garret Murai - California Construction Law BlogJanuary was a tough month in the courts for Hensel Phelps Construction Company. Hot off the heels of Hensel Phelps Construction Co. v. Superior Court, a case concerning the 10-year statute of limitations under Civil Code section 941, comes Hensel Phelps Construction Co. v. California Department of Corrections and Rehabilitation, Case No. B293427 (January 28, 2020), a bid dispute case . . .
The Tale of a Bid, a Bid Protest, and Two Cases
A. The Bid and Bid Protest
On March 15, 2015, the California Department of Corrections and Rehabilitation (CDCR) issues an Invitation for Bid for the HVAC project at the Ironwood State Prison. The deadline to submit bids was April 30, 2015. Hensel Phelps Construction Co. submitted a timely bid and was determined to be the “apparent low bidder” with a bid of $88,160,000.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Nationwide Immigrant Strike May Trigger Excusable Delay and Other Contract Provisions
February 23, 2017 —
Adam P. Handfinger & Meredith N. Reynolds – Peckar & Abramson, P.C.Yesterday, February 16, 2017, media outlets reported a nationwide strike by immigrants and
businesses referred to as “A Day Without Immigrants”. The protest, organized largely through
social media, was a response by some to the Trump Administration’s immigration and foreign
trade policies. Participating businesses shut down and immigrants refused to work or spend
money in an eff ort to demonstrate the role of foreign-born workers in the U.S. economy.
While the number of businesses and individuals that participated is not yet known, several
contractors reported labor shortages and construction project delays or temporary shut
downs as a result of the protest.
Reprinted courtesy of
Adam P. Handfinger, Peckar & Abramson, P.C. and
Meredith N. Reynolds, Peckar & Abramson, P.C.
Mr. Handfinger may be contacted at ahandfinger@pecklaw.com
Ms. Reynolds may be contacted at mreynolds@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Property Damage to Non-Defective Work Is Covered
February 18, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe New Hampshire Supreme Court found some of the property damage evolving from the insured's portion of the work was covered under its liability policy. Cogswell Farm Condo. Ass'n v. Tower Group, Inc., 2015 N.H. LEXIS 3 (N.H. Jan. 13, 2015).
Lemery Building Company, Inc. constructed and developed 24 residential condominium units. After units were sold, the Cogswell Farm Condominium Association sued Lemery, asserting that the "weather barrier" components of the units were defectively constructed and resulted in damage to the units due to water leaks. Cogswell then sued its insurer, Tower Group, Inc., seeking a declaratory judgment that its claims against Lemery were covered.
The trial court eventually determined that exclusions J (1) and J (6) both applied to exclude coverage. Exclusion J (1) excluded coverage for "property damage" to property that Lemery "owns, rents, or occupies." Exclusion J (6) excluded coverage for property damage to "[t] hat particular part of any property that must be restored, repaired or replaced because [Lemery's] work was incorrectly performed on it."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Specific Performance of an Option Contract to Purchase Real Property is Barred Absent Agreement on All Material Terms
December 20, 2017 —
Richard H. Herold - Real Estate Litigation BlogOn November 14, 2017, the Court of Appeals (Division 1), in Offerman v. Granada, LLC, 2017 WL 5352664, reversed a trial court order directing specific performance of an alleged option to purchase real property, holding that the alleged option was too indefinite to be specifically performed because the parties did not agree to all of the material terms of the option.
Tenant-Purchaser Offerman executed a two-year lease with Landlord-Seller Granada, which granted Offerman “the option to purchase [the] property…for a sales price to be determined at that time by an independent appraiser acceptable to both Tenant and Landlord. (Terms and Conditions to be stipulated by both parties at such time).” (emphasis added). Offerman timely advised Granada he intended to exercise the option, asked Granada to name an appraiser, and, when Granada did not respond, Offerman tendered a $240,000 appraisal to exercise the option. Granada did not retain an appraiser but instead simply demanded $350,000 to close the sale. After a bench trial, the Court determined that Offerman was entitled to specific performance, and, as the parties had not agreed to certain terms, held a second evidentiary hearing to resolve the form of judgment, therein naming a title agency to handle the escrow, setting a closing date, allocating the transaction fees between the parties, and ordering Granada to pay for the property inspection.
Read the court decisionRead the full story...Reprinted courtesy of
Richard H. Herold, Snell & WilmerMr. Herold may be contacted at
rherold@swlaw.com