Application Of Two Construction Contract Provisions: No-Damages-For-Delay And Liquidated Damages
February 14, 2022 —
David Adelstein - Florida Construction Legal UpdatesA recent Florida opinion between a prime contractor and a Florida public body touches upon two important issues: (1) the application of a no-damage-for-delay provision; and (2) the application of a liquidated damages provision. Both provisions find there way into many construction contracts. Unfortunately, the opinion is sparse on facts. Nevertheless, the application of these provisions is worthy of consideration.
In this opinion, Sarasota County v. Southern Underground Industries, Inc., 2022 WL 162977 (Fla. 2d DCA 2022), a county hired a contractor to install sanitary and water piping underneath a waterway. During construction, a nearby homeowner complained that vibration from the drilling caused damage to his home. As a result, the county stopped the contractor’s work to address a potential safety issue, as it was contractually entitled to do. The contractor hired a structural engineer to inspect the house and the engineer issued a report determining that any alleged damage was cosmetic and that there was sufficient monitoring of the vibrations to prevent future damage. The contractor also had an insurance policy to cover any homeowner claim for damage. However, upon receipt of the engineer’s report, the county did not lift its stop work order. Rather, the stop work order remained in place for an additional 71 days.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Preventing Common Electrical Injuries on the Jobsite
February 03, 2020 —
Kelsey Rzepecki - Construction ExecutiveDespite the overall decrease in electrical workplace fatalities, construction workers remain the most at risk of death from electrical accidents. In 2016, 53% of all fatal electrical injuries were in the construction industry, according to the Bureau of Labor Statistics.
Employers can improve their bottom line by implementing prevention strategies to reduce chances of electrical injuries and create a safer, more efficient jobsite.
What Are the Most Common Electrical Injuries in Construction?
The three types of electrical injuries that occur the most often on construction jobsites are:
- electrocution (such as electric shock and burns) through unintentional contact with high-voltage lines or equipment;
- severe burns or death from explosive gases accidentally ignited by electrical equipment; and
- injuries from falls or from contact with moving equipment after worker experiences a low-voltage electrical shock and can no longer keep balance or physical control of the tools or equipment they have when shocked.
Reprinted courtesy of
Kelsey Rzepecki, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Ms. Rzepecki may be contacted at
krzepecki@graphicproducts.com
Contractor Gets Benched After Failing to Pay Jury Fees
April 11, 2022 —
Garret Murai - California Construction Law BlogTrial by jury is a fundamental right under the U.S. and California Constitutions. However, to avail yourself of this right, you not only have to declare that in advance that you intend to try your case to a jury but post jury fees as well. In TriCoast Builders, Inc. v. Fonnegra, a contractor who failed to timely post jury fees, discovered on the day of trial that it waived the right to insist on a jury trial when the defendant pulled an “I gotcha” and waived his right to a jury trial.
The TriCoast Case
In May 2014, Nathaniel Fonnegra house was damaged by fire. The following month, Fonnegra entered into a construction contract with TriCoast Builders, Inc. to repair the property. Dissatisfied with the work, Fonnegra terminated the contract, and TriCoast in turn filed a complaint against Fonnegra for unpaid work.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Construction in Indian Country – What You Need To Know About Sovereign Immunity
July 22, 2019 —
Edward J. Hermes - Snell & Wilmer Under Construction BlogThere are many legal issues to consider when bidding on and building projects in American Indian Country. Which labor and employment laws apply? Are there contracting or hiring preferences that apply? Do the Prompt Pay Act and other state laws apply? Can I bring a lawsuit to enforce the contract and, if so, where would I file suit? This article addresses the final question, which is often the most important question when contracting with a tribal entity.
Many of the construction projects in American Indian Country are with tribes or entities wholly owned or by a tribe, such as housing authorities, casinos, hospitals, schools or other economic enterprises. Like the state and federal government, tribes (and their tribally—owned enterprises) enjoy sovereign immunity from any lawsuit, meaning they cannot be sued unless the tribe expressly agrees to waive its sovereign immunity. Sovereign immunity poses a unique issue for contractors that does not typically arise in other projects, but it need not be a deterrent to doing business with tribes. It is usually in the best interest of both the contractor and tribe to negotiate an acceptable waiver of sovereign immunity. Absent such a waiver, the tribe or tribal entity cannot be sued and the resulting forfeiture of remedies can be devastating for the contractor.
To waive sovereign immunity, the tribe must make it clear in the contract that it can be sued in a specific jurisdiction. Oklahoma Tax Comm'n v. Citizen Band Potawatomi tribe of Okla., 498 U.S. 505, 509 (1991). It does not matter whether the tribe is operating on or off its lands—if there is no express contractual waiver of sovereign immunity, a contractor will have no recourse in the event of non-payment or other breach of contract. See Kiowa tribe of Okla. v. Manufacturing Technologies, Inc., 523 U.S. 751, 118 S.Ct. 1700, 140 L.Ed.2d 981 (1998).
Read the court decisionRead the full story...Reprinted courtesy of
Edward J. Hermes, Snell & WilmerMr. Hermes may be contacted at
ehermes@swlaw.com
Jinx: Third Circuit Rules in Favor of Teamsters in Withdrawal Case
July 28, 2018 —
Wally Zimolong - Supplemental ConditionsBad omen. Last week, I wrote about a Appeals Court decision that affirmed a contractor’s escape from an over $600,000 withdrawal liability assessment from the Laborers Union. The next day the Third Circuit (which covers PA, NJ, and DE) handed down a decision affirming a federal court’s decision to assess withdraw liability. This one shows the dark side of not reading and understanding your CBA.
The belligerents in the litigation were, Penn Jersey, a construction material supplier, and Teamsters Local 676. Their collective bargaining agreement contained a clause purportedly covering withdrawal liability. Specifically, the clause stated “should the Employer withdraw from the Agreement in the future, there will be no withdrawal liability. The CBA expired and Penn Jersey did not renew its agreement with the Teamsters.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Supreme Court Opens Door for Challenges to Older Federal Regulations
August 05, 2024 —
Jane C. Luxton - Lewis BrisboisWashington, D.C. (July 1, 2024) – On July 1, 2024, the U.S. Supreme Court issued another end-of-term major decision limiting the scope of federal agency actions in Corner Post, Inc. v. Board of Governors of the Federal Reserve System. Adding to the tectonic shift in the regulatory landscape created by the Court’s June 27 and 28 rulings constraining the role of administrative law judges and overturning longstanding “Chevron deference” by courts to federal agency expertise, the decision in Corner Post establishes a newly expanded time frame for affected entities to challenge final agency action. Instead of confirming that final agency action is subject to a default six-year statute of limitations, the Court held that under the Administrative Procedure Act (APA), the time limit for appeal begins to run when a plaintiff is injured by the agency's action, not when the action becomes final. This decision has important implications for businesses and others affected by federal regulations.
The case arose when Corner Post, a truck stop and convenience store in North Dakota that opened in 2018, challenged a 2011 Federal Reserve Board regulation (Regulation II) that set maximum interchange fees for debit card transactions. Corner Post filed suit in 2021, arguing that Regulation II allowed higher fees than permitted by statute. The lower courts dismissed the suit as time-barred under 28 U.S.C. § 2401(a), which effectively requires APA claims to be filed "within six years after the right of action first accrues."
Read the court decisionRead the full story...Reprinted courtesy of
Jane C. Luxton, Lewis BrisboisMs. Luxton may be contacted at
Jane.Luxton@lewisbrisbois.com
Tips for Contractors Who Want to Help Rebuild After the California Wildfires
November 02, 2017 —
Garret Murai - California Construction Law BlogI received a call from one of my contractor clients this past week to see what he could do to help those affected by California’s North Bay fires.
The North Bay fires are the deadliest and most destructive wildfires in California’s history. To date, the fires have claimed 42 lives, burned more than 200,000 acres of land, destroyed an estimated 8,400 structures and likely damaged tens of thousands more. By comparison, the state’s second most deadly wildfire, the Oakland Hills fire of 1991, claimed the lives of 25 people, burned 1,600 acres of land, and destroyed 2,900 structures. Rebuilding costs for the North Bay fires, according to the California Insurance Commissioner, are expected to top $1 billion.
For those with insurance, insurance experts say that the rebuilding process can take two years or more for those whose homes and businesses were destroyed. For those whose homes and businesses were fortunate enough only to be damaged, rebuilding efforts are already underway.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Corps Proposes $4.6B Plan to Steel Miami for Storm Surge
June 22, 2020 —
Pam Radtke Russell - Engineering News-RecordA $4.6-billion U.S. Army Corps of Engineers proposal to protect Miami from future storm surge, largely by building massive sea walls and elevating infrastructure systems, is the latest of such plans the agency has developed for East Coast communities.
Pam Radtke Russell, Engineering News-Record
Ms. Russell may be contacted at Russellp@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of