Georgia Supreme Court Addresses Anti-Indemnity Statute
October 21, 2019 —
David R. Cook - AHC Construction and Procurement BlogIn prior blog posts, we addressed Georgia’s anti-indemnity statute. One of the posts addressed the statute in the context of an electric utility easement near an airport. That case made its way to the Supreme Court Georgia, which provided some additional clarity to the statute. Milliken & Co. v. Georgia Power Co., — Ga. –, 829 S.E.2d 111 (2019).
When a plane crashed and several passengers and crew died or were injured, their representatives sued several defendants, including a nearby plant owner, Milliken & Company (“Milliken”), based on claims that transmission lines on Milliken’s property were too close to the runways, were too high, and encroached on the airport easements. Milliken cross claimed against Georgia Power Company (“GPC”). Milliken’s claim was based on an easement it granted to GPC, which required GPC to indemnify it for any claims arising out of GPC’s construction or maintenance of the transmission lines.
On appeal, the Supreme Court considered whether the clause was unenforceable under O.C.G.A. § 13-8-2(b). In general, “a party may contract away liability to the other party for the consequences of his own negligence without contravening public policy, except when such agreement it prohibited by statute.” Id. at 113 citing Lanier at McEver v. Planners & Eng’rs Collaborative, 284 Ga. 204, 205 (2008). As one such statute, O.C.G.A. § 13-8-2(b) applies when an indemnification provision (i) “relates in some way to a contract for construction, alteration, repair, or maintenance of certain property” and (ii) “promises to indemnify a party for damages arising from that own party’s sole negligence.” Id. at 114 (internal punctuation omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
UPDATE - McMillin Albany LLC v. Superior Court
June 05, 2017 —
Richard H. Glucksman, Glenn T. Barger, & David A. Napper - CGDRB News & PublicationsThe matter has been fully briefed since last year and the construction industry anxiously awaits the California Supreme Court's highly anticipated decision regarding McMillin Albany LLC v. Superior Court (2015) 239 Cal.App.4th 1132. Numerous amicus briefs have also been filed including one by the Association of Southern California Defense Counsel, with the immediate past president of the organization, CGDRB's Glenn T. Barger, Esq., listed as the attorney of record. The Supreme Court will consider the issue of whether the Right to Repair Act (SB800) is the exclusive remedy for all defect claims arising out of new residential construction sold on or after January 1, 2003, thereby resolving the split of authority presented by the Fifth Appellate District's holding in McMillin Albany, which outright rejected the Fourth Appellate District's holding in Liberty Mutual Insurance Co. v. Brookfield Crystal Cove LLC (2013) 219 Cal.App.4th 98, on this particular issue. Oral argument is still pending and CGDRB will continue to closely monitor the progress of this case. Stay tuned.
Reprinted courtesy of Chapman Glucksman Dean Roeb & Barger attorneys
Richard H. Glucksman,
Glenn T. Barger and
David A. Napper
Mr. Glucksman may be contacted at rglucksman@cgdrblaw.com
Mr. Barger may be contacted at gbarger@cgdrblaw.com
Mr. Napper may be contacted at dnapper@cgdrblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Texas Jury Finds Presence of SARS-CoV-2 Virus Causes “Physical Loss or Damage” to Property, Awards Over $48 Million to Baylor College of Medicine
September 26, 2022 —
Michael S. Levine & Kevin V. Small - Hunton Insurance Recovery BlogA Texas jury has found that the presence of SARS-CoV-2 virus on the property of Baylor College of Medicine (BCM) caused “physical loss or damage” and resulting economic loss, triggering coverage under BCM’s commercial property insurance program. The jury awarded BCM over $48 million following a three-day trial; the award consisted of $42.8 million in business interruption, $3.3 million in extra expense, and $2.3 million in damage to research projects.
The verdict came after the court denied the insurers’ pre-trial motion for summary judgment, rejecting the insurers’ contention that a virus cannot—as a matter of law—cause physical loss or damage to property. In denying the motion, the court held that whether the presence of the virus causes physical loss or damage presents a question of fact for the jury to resolve; a copy of the order rejecting the insurers’ summary judgment argument can be found
here.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Kevin V. Small, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Small may be contacted at ksmall@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Flood Sublimits Do Not Apply to Loss Caused by Named Windstorm
May 07, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe New Jersey Superior Court considered whether recovery for storm surge was limited by the policy's sublimit for loss caused by flood. Public Serv. Enter. Group, Inc. v. Ace Am. Ins. Co., 2015 N. J. Super. Unpub. LEXIS 620 (N.J. Super. Ct. Law Div. March 23, 2015).
Storm surge from Superstorm Sandy inundated and damaged Public Service Enterprise Group, Inc.'s (PSEG) property, including eight large generating stations. PSEG had coverage of $1 billion under policies with defendant carriers. There was no sublimit in the policies for "named windstorms," other than named windstorms in Florida. A $250 million sublimit appeared in the policies for losses caused by "flood."
The carriers paid only a portion of PSEG's claim. The total damages exceeded $500 million.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Maritime Law: An Albatross for Contractors Navigating Marine Construction
January 03, 2022 —
Cindy Matherne Muller - ConsensusDocs“Ah! Well a-day! When evil looks, Had I from old and young! Instead of the cross, the Albatross, About my neck was hung.” 1
Contractors and subcontractors performing construction over water may find themselves encountering maritime law for the first time. Like the ancient mariner’s encounter with an albatross in The Rime of the Ancient Mariner, a contractor may be able to use maritime law to safely guide it through rough seas, or, if not careful, a contractor may find itself with maritime law hung, like an albatross, around its neck. This article gives an overview of key maritime law issues to demystify this historical body of law and answers some basic questions.
What is admiralty jurisdiction?
The Constitution gives federal courts jurisdiction over all maritime cases. This jurisdiction gives litigants the opportunity to remove state court cases to federal court and to avoid a jury trial. The purpose of admiralty jurisdiction in federal court is to protect and ensure the uniform treatment of nationwide maritime commerce and extends to maritime contracts and accidents. Any contract which relates to the navigation, business, or commerce of the sea is a maritime contract. Even contracts with mixed obligations on land and sea can fall within admiralty jurisdiction – such as construction contracts with a waterborne component. Admiralty jurisdiction also extends to maritime accidents – those that occur on navigable waters and have a maritime nexus.
Read the court decisionRead the full story...Reprinted courtesy of
Cindy Matherne Muller, Jones Walker LLPMs. Muller may be contacted at
cmuller@joneswalker.com
Ahlers Cressman & Sleight PLLC Recognized Among The Top 50 Construction Law Firms TM of 2024 by Construction Executive
July 15, 2024 —
Ahlers Cressman & Sleight PLLCACS is proud to announce that it has once again been ranked among The Top 50 Construction Law Firms in the Construction Executive 2023 rankings.
Since its first publication in 2003, Construction Executive magazine has served as the leading source for news, market developments, and business issues impacting the construction industry, and its articles are designed to help owners and top managers run a more profitable and productive construction business.
Construction Executive established the rankings by asking over 600 hundred U.S. construction law firms to complete a survey. Constructive Executive’s data collection includes: 2023 revenues from the firm’s construction practice, the number of attorneys in the firm’s construction practice, percentage of the firm’s total revenues derived from its construction practice, the number of states in which the firm is licensed to practice, the year in which the construction practice was established, and the number of construction industry clients served during the fiscal year 2023.
Read the court decisionRead the full story...Reprinted courtesy of
Ahlers Cressman & Sleight PLLC
Dump Site Provider Has Valid Little Miller Act Claim
October 19, 2020 —
Christopher G. Hill - Construction Law MusingsYou may have thought that a Virginia “Little Miller Act” bond claim, like a mechanic’s lien, could only be brought by those that provide materials and labor incorporated into the construction project. If you did, you aren’t alone.
In fact, Safeco Insurance Co. of America, a surety, made exactly the above argument in Yard Works LLC v. GroundDown Constructors LLC. In that case, a debris hauling company failed to pay Yard Works, the company that provided the dumping site for the debris. Yard Works sued pursuant to the Little Miller Act to get paid. In response, the surety sought to have the claim against the payment bond dismissed and argued that because Yard Works did not actually improve the property or provide improvements and that Yard Works only passively provided a dump site, Yard Works could not claim under the payment bond.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Eyerly may be contacted at
te@hawaiilawyer.com
Mediation in the Zero Sum World of Construction
September 26, 2022 —
Christopher G. Hill - Construction Law MusingsConstruction is a zero sum game. What do I mean by that? I mean that even where you, a construction professional with a great construction lawyer, have reviewed and edited a subcontract presented to you or provided a well-drafted contract to the other party that contains an attorney fees provision, every dollar that you spend on litigation is a dollar less of profit.
Couple the fact that no construction company can or should bid or negotiate work with an eye toward litigation (aside from having a well written contract that will be enforced to the letter here in Virginia). Particularly on “low bid” type projects, contractors and subcontractors cannot “pad” their bids to take into account the possibility of attorney fees, arbitration, or litigation. Furthermore, the loss of productivity when your “back office” personnel are tied up dealing with discovery, phone calls, and other incidents of litigation that do nothing but rehash a bad project and increase the expense sap money from the bottom line. While the possibility of a judgment including attorney fees may soften this blow, you are still out the cash.
All of this said, if you are in commercial construction for any significant period of time disputes will arise and I have discussed the process in some detail at other places here at Construction Law Musings. As a construction litigator, I am fully aware of this fact of life. Efficient management of these disputes is key, particularly when they escalate to the point where some form of outside “help” (read arbitrator or judge) is necessary.
Read the court decisionRead the full story...Reprinted courtesy of