Will Claims By Contractors on Big Design-Build Projects Ever End?
February 27, 2023 —
Richard Korman - Engineering News-RecordIn the annals of construction disputes, it is a blip, not a blast.
After a Flatiron Construction-Zachry Group joint venture struck out on most of its arbitrated claims against engineering firm partners on the I-85/385 design-build interchange project in Greenville, S.C., and had others dismissed in court, the contractors had one more source from which to try to cover unexpected project costs: a contractor protective professional policy. Flatiron-Zachry filed a lawsuit last October in San Antonio federal court to try to force payment from Steadfast, a subsidiary of Zurich American Insurance Co.
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Preserving Your Construction Claim
February 18, 2015 —
Craig Martin – Construction Contractor AdvisorA recent article in the Construction Executive discussed the importance of preserving your claim, both in terms of timeliness of submitting your claim and making sure that you aren’t waiving portions of your claim when executing releases. These are all excellent points and bear some follow-up.
Timing Your Claim
I often review construction contracts that contain deadlines by which claims must be submitted. It may seem counter intuitive to think that you need to submit a claim when you are discussing the basis for the claim with an upstream contractor or the owner. But, there are more cases than I care to count where a contractor’s claim has been denied because the claim was not timely submitted.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Want to Make Your Jobsite Safer? Look to the Skies.
October 10, 2022 —
Rory San Miguel - Construction ExecutiveNew York Gov. Kathy Hochul is set to sign Carlos’ Law for worker protection. The law would set a national precedent for construction site safety, substantially raising the minimum fines for construction companies found liable for onsite injuries.
Worksites are very complex, and many factors go into creating a safe space. Following suit, innovative operators are looking at advanced technologies to boost onsite safety, including drone data visualization, which involves flying a drone over a site to capture a highly accurate 3D model of current conditions in close to real time. Using drones can't solve every problem, but it can help not only protect workers but also encourage new ones to join your team.
How drone surveying improves jobsite safety
3D mapping a worksite with a drone keeps workers out of harm’s way, helping surveyors avoid potentially dangerous areas filled with constantly moving heavy equipment and machinery. Drone mapping also means surveyors can stay out of the heat, avoiding the risk of excess sun exposure by sending the drone out in their stead to traverse the terrains and slopes of the site.
Reprinted courtesy of
Rory San Miguel, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Cuba: Construction Boom Potential for U.S. Construction Companies and Equipment Manufacturers?
June 30, 2016 —
Sanjo Shatley, Esq. – Florida Construction Law UpdateOn July 20, 2015, diplomatic relations were officially restored between the U.S. and Cuba. Since that date, a number of significant political events have taken place. First, the U.S. reopened its embassy in Cuba on August 14, 2015. Next, on January 26, 2016, offices of the U.S. Departments of the Treasury and Commerce announced new amendments to the Cuban Assets Control Regulations and Export Administration Regulations. These amendments removed “existing restrictions on payment and financing terms for authorized exports and reexports to Cuba of items other than agricultural items or commodities,” and established “a case-by-case licensing policy for exports and reexports of items to meet the needs of the Cuban people, including those made to Cuban state-owned enterprises.”[1] Additionally, these amendments “further facilitate travel to Cuba for authorized purposes by allowing blocked space, code-sharing, and leasing arrangements with Cuban airlines, authorizing additional travel-related and other transactions directly incident to the temporary sojourn of aircraft and vessels, and authorizing additional transactions related to professional meetings and other events, disaster preparedness and response projects, and information and informational materials, including transactions incident to professional media or artist productions in Cuba.”[2] Finally, on March 21, 2016, President Barack Obama was the first sitting U.S. President to visit Cuba since the 1959 revolution, in which Fidel Castro overthrew Fulgencio Batista. This revolution ultimately led to the U.S. severing diplomatic relations in 1961 and President John F. Kennedy imposing a trade embargo between the U.S. and Cuba, which remains in effect today.
Read the court decisionRead the full story...Reprinted courtesy of
Sanjo Shatley, Esq., Cole, Scott & Kissane, P.A.Mr. Shatley may be contacted at
sanjo.shatley@csklegal.com
New York Restrictions on Flow Through Provision in Subcontracts
August 14, 2023 —
Bill Wilson - Construction Law ZoneMost subcontracts include a flow through provision (also called flow down and incorporation clauses) stating that the subcontractor and contractor are bound by the same obligations as set forth in the prime contract between the contractor and owner. Many jurisdictions interpret such provisions narrowly, as illustrated in a recent case out of New York. In Amerisure Insurance Company v. Selective Insurance Group, Inc., 2023 WL 3311879, the U.S. Court of Appeals for the Second Circuit affirmed the District Court’s interpretation of a flow through clause in a construction subcontract. The Amerisure case involved a dispute over insurance coverage for a personal injury to a subcontractor’s employee on a construction project. The owner of the project sought defense and indemnity from the general contractor (GC) and its insurance company, who in turn sought coverage for the owner as an additional insured under the subcontractor’s policy. The GC based its argument for coverage on the flow through provision in the subcontract.
The prime contract required the GC to procure commercial liability insurance including the owner as an additional insured for claims caused by the GC’s negligent acts or omissions. The subcontract likewise required the subcontractor to procure commercial general liability insurance but required only that the GC be named as an additional insured. However, the subcontract also included a flow through clause, binding the subcontractor to the terms of the prime contract and assuming toward the GC all the obligations and responsibilities that the GC assumed toward the owner. However, the subcontract did not expressly require that the subcontractor name the owner as an additional insured, and in order for the owner to qualify as an additional insured under the subcontractor’s insurance policy, the subcontractor must have agreed in the subcontract to name the owner as an additional insured.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Wilson, Robinson & Cole LLPMr. Wilson may be contacted at
wwilson@rc.com
The Word “Estimate” in a Contract Matters as to a Completion Date
February 12, 2024 —
David Adelstein - Florida Construction Legal UpdatesLanguage in a contract matters. The word “estimates” or “estimated” matters particularly when it comes to a date certain such as a substantial completion or completion date. Remember this.
Here is an example.
In Parque Towers Developers, LLC v. Pilac Management, Ltd., 49 Fla.L.Weekly D190a (Fla. 3d DCA 2024), a trial court held that the developer did not complete the construction of five condominium units by the date in the purchase agreements. The developer appealed because “[t]he agreements contain no date certain for the completion of the units, but rather include a clause that ‘Seller estimates it will substantially complete construction of the Unit, in the manner specified in this Agreement, by December 31, 2017, subject to extensions resulting from ‘Force Majeure (the ‘Outside Date’).’” Parque Towers, supra. Another provision in the purchase agreements stated, “[w]henver this Agreement requires Seller to complete or substantially complete any item of construction, that item will be understood to be complete or substantially complete when so completed or substantially completed in Seller’s opinion. Id.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Homeowners Must Comply with Arbitration over Construction Defects
January 06, 2012 —
CDJ STAFFThe California Court of Appeals has upheld a decision by the Superior Court of Kern County that homeowners must comply with arbitration procedures in their construction defect claim. The California Court of Appeals ruled on December 14 in the case of Baeza v. Superior Court of Kern County, denying the plaintiff’s petition that the trial court vacate its order.
The plaintiffs in the case are homeowners in various developments built by Castle & Cook. The homes were sold with a contract that provided for “nonadversarial prelitigation procedures, including mediation, and judicial reference.” The homeowners made defect claims and argued that Castle & Cooke failed to comply with statutory disclosure requirements and that some of the contracts violate related statutes.
The appeals court found that there was no ground for appeal of the lower court’s order to continue with prelitigation procedures. The court noted that the plaintiffs could not seek a review of the mediation until a judgment was issued, but that then the issue would be moot. The court felt that there were issues presented that needed clarification, and so they reviewed this case. This was cleared for publication.
The court considered the intent of the legislature in passing the Right to Repair Act, noting that “under the statutory scheme, the builder has the option of contracting for an alternative nonadversarial prelitigation procedure,” as established in Chapter 4. The court noted that Chapter 4 “contains no specifics regarding what provisions the alternative nonadversarial contractual provisions may or must include.”
The plaintiffs contended that the builder was in violation of the standards set out in Section 912, however the court responded that these sections set out one set of procedures, but they concluded that “if the Legislature had intended the section 912 disclosure provisions…it could have made the requirements applicable to all builders by locating them in a section outside Chapter 4.”
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Quick Note: Independent Third-Party Spoliation Of Evidence Claim
June 18, 2019 —
David Adelstein - Florida Construction Legal UpdatesIn an earlier posting I discussed the difference between first-party spoliation of evidence and third-party spoliation of evidence.
There is NO independent cause of action for first-party spoliation of evidence because that can be dealt with directly in the underlying lawsuit. This deals with the assertion that an actual party to a lawsuit spoiled evidence.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com