Leveraging the 50-State Initiative, Connecticut and Maine Team Secure Full Dismissal of Coverage Claim for Catastrophic Property Loss
March 23, 2020 —
Regen O'Malley - Gordon & Rees Insurance Coverage Law BlogOn behalf of Gordon & Rees’ surplus lines insurer client, Hartford insurance coverage attorneys Dennis Brown, Joseph Blyskal, and Regen O’Malley, with the assistance of associates Kelcie Reid, Alexandria McFarlane, and Justyn Stokely, and Maine counsel Lauren Thomas, secured a full dismissal of a $15 million commercial property loss claim before the Maine Business and Consumer Court on January 23, 2020. The insured, a wood pellet manufacturer, sustained catastrophic fire loss to its plant in 2018 – just one day after its surplus lines policy expired.
Following the insurer’s declination of coverage for the loss, the wood pellet manufacturer brought suit against both its agent, claiming it had failed to timely secure property coverage, as well as the insurer, alleging that it had had failed to comply with Maine’s statutory notice requirements. The surplus lines insurer agreed to extend the prior policy several times by endorsement, but declined to do so again. Notably, the insured alleged that the agent received written notice of the non-renewal prior to the policy’s expiration 13 days before the policy’s expiration. However, the insured (as well as the agent by way of a cross-claim) asserted that the policy remained effective at the time of the loss as the insured did not receive direct notice of the decision not to renew coverage and notice to the agent was not timely. Although Maine’s Attorney General and Superintendent intervened in support of the insured’s and agent’s argument that the statute’s notice provision applied such that coverage would still be owed under the expired policy, Gordon & Rees convinced the Court otherwise.
At issue, specifically, was whether the alleged violation of the 14-day notice provision in Section 2009-A of the Surplus Lines Law (24-A M.R.S. § 2009-A), which governs the “cancellation and nonrenewal” of surplus lines policies, required coverage notwithstanding the expiration of the policy. The insured, the agent, and the State of Maine intervenors argued that “cancellation or nonrenewal” was sufficient to trigger the statute’s notice requirement, and thus Section 2009-A required the insurer to notify the insured directly of nonrenewal. In its motion to dismiss, Gordon & Rees argued on behalf of its client that Section 2009-A requires both “cancellation and nonrenewal” in order for the statute to apply. Since there was no cancellation in this case – only nonrenewal – Gordon & Rees argued that Section 2009-A is inapt and that the insurer is not obligated to provide the manufacturer with notice of nonrenewal. Alternatively, it argued that the statute is unconstitutionally vague and unenforceable.
Read the court decisionRead the full story...Reprinted courtesy of
Regen O'Malley, Gordon & ReesMs. O'Malley may be contacted at
romalley@grsm.com
Failure to Comply with Sprinkler Endorsement Bars Coverage for Fire Damage
July 31, 2013 —
Tred Eyerly, Insurance Law HawaiiDespite its application stating otherwise, the insured's failure to install a sprinkler system in its building barred coverage for extensive damage caused by fire.American Way Cellular, Inc. v. Travelers Prop. Cas. Co. of Am., 2013 Cal. App. LEXIS 425 (Cal. Ct. App. May 30, 2013).
American Way contacted a broker, A&J, regarding liability and property coverage. A&J sent American Way an application for a policy with Travelers. The application indicated American Way had a sprinkler system and fire detectors in its building.
Travelers issued a policy with a Protective Safeguards Endorsement For Sprinkler Locations and Restaurants. The endorsement stated that as a condition of the insurance, the insured was required to maintain a sprinkler system. An exclusions section said the insurer would not pay for loss caused by fire if there was no sprinkler system.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
Index Demonstrates Increase in Builders’ Sentiment
September 17, 2014 —
Beverley BevenFlorez-CDJ STAFFThe National Association of Home Builders’ Eye on Housing reported that “[b]uilders’ sentiment jumped four points to 59, the highest level since November 2005, according to the September NAHB/Wells Fargo Housing Market Index.” Furthermore, builders mentioned “renewed interest by potential home buyers and higher traffic in their models and through their phone calls.”
Eye on Housing also reported that the “inventory of new home for sale has increased to over 200,000.” While still lower than the 300,000 typical in 1990s and early 2000s, “the steady increase has provided a better selection for consumers.”
Read the court decisionRead the full story...Reprinted courtesy of
White and Williams Announces Lawyer Promotions, Four Attorneys Promoted to Partner and One Attorney Promoted to Counsel
January 23, 2023 —
White and Williams LLPPHILADELPHIA -- White and Williams LLP is very pleased to announce the promotion of the following attorneys: Michael J. Ciamaichelo, Russell P. Lieberman, Tanya A. Salgado and Brett N. Tishler, who have become members of the firm’s partnership. All four attorneys are promoted from counsel to partner. The firm has also promoted Zachery B. Roth from associate to counsel. The partnership concluded in elevating these attorneys that each have made significant contributions to the firm and their respective practices.
“All of our new partners and counsel enrich the firm both internally and externally. They have a demonstrated, deep commitment to client service excellence and through their dedication, personal sacrifice and leadership warranted elevation to partnership and counsel at White and Williams,” said firm Managing Partner Andy Susko. “We are proud to welcome these four lawyers to our partnership and look forward to their continued contributions to the firm’s success.”
Read the court decisionRead the full story...Reprinted courtesy of
White and Williams LLP
Don’t Conspire to Build a Home…Wait…What?
June 08, 2020 —
Ben Volpe - Colorado Construction Litigation BlogIn 1986, the Colorado General Assembly enacted the Pro Rata Liability Act, codified at C.R.S. § 13-21-111.5, which eliminated joint and several liability for defendants in favor of pro rata liability.[1] The statute was “designed to avoid holding defendants liable for an amount of compensatory damages reflecting more than their respective degrees of fault.”[2] However, the following year, the Colorado legislature carved out an exception to preserve joint liability for persons “who consciously conspire and deliberately pursue a common plan or design to commit a tortious act.”[3] Because of this conspiracy exception, plaintiffs try to circumvent the general rule against joint and several liability by arguing that construction professionals defending construction defect cases were acting in concert, as co-conspirators. Plaintiffs argue that if they can prove that two or more construction professionals consciously conspired and deliberately pursued a common plan or design, i.e., to build a home or residential community, and such a plan results in the commission of a tort, i.e., negligence, the defendants may be held jointly and severally liable for all of the damages awarded.
Since 1986, Colorado courts have construed the “conspiracy” provision in § 13-21-111.5(4), but some have disagreed as to what constitutes a conspiracy for purposes of imposing joint liability.
Civil Conspiracy
In Colorado, the elements of civil conspiracy are that: “(1) two or more persons; (2) come to a meeting of the minds; (3) on an object to be accomplished or a course of action to be followed; (4) and one or more overt unlawful acts are performed; (5) with damages as the proximate result thereof.”[4]
Read the court decisionRead the full story...Reprinted courtesy of
Benjamin Volpe, Higgins, Hopkins, McLain & Roswell, LLCMr. Volpe may be contacted at
volpe@hhmrlaw.com
Homebuilder Predictions for Tallahassee
October 10, 2013 —
CDJ STAFFThe cost of putting up a new home in Tallahassee has risen, but Joe Manausa thinks that builders might be putting up homes that will cost more than home buyers are able to pay. He notes that permits and sales are up, but numbers are still well below those in 2006.
Mr. Manusa thinks that Tallahassee could face “a need (demand) for homes priced below $300,000, but a glut of supply for those priced above $300,000.” He says that home builders “need to target construction opportunities below that price point.”
He notes that average price of new construction is $272,000, but resales are going for $161,000, which puts quite a premium on a new home.
Read the court decisionRead the full story...Reprinted courtesy of
Labor Code § 2708 Presumption of Employer Negligence is Not Applicable Against Homeowners Who Hired Unlicensed Painting Company
December 02, 2015 —
Kristian B. Moriarty & Yvette Davis – Haight Brown & Bonesteel LLPIn Vebr v. Culp (Filed 10/28/2015, No. G050730), the Fourth District Court of Appeal affirmed a trial court’s grant of summary judgment in favor of homeowners, where an employee of an unlicensed painting company was injured on the premises. Despite the fact that the painting company was deemed unlicensed for failure to acquire workers’ compensation insurance, the negligence presumption of Labor Code § 2708 was inapplicable to the homeowners as de facto “employers" of the plaintiff.
Plaintiff, Tomas Vebr, was employed by OC Wide Painting, a licensed painting contractor. OC Wide Painting had a license issued by the California Contractors State License Board, but had filed for an exemption from the requirement that it maintain workers’ compensation insurance. The exemption was granted on the basis OC Wide Painting “did not have any employees.” However, OC Wide Painting actually had multiple employees, including Vebr. Therefore, by operation of law, the license was deemed void.
Reprinted courtesy of
Kristian B. Moriarty, Haight Brown & Bonesteel LLP and
Yvette Davis, Haight Brown & Bonesteel LLP
Mr. Moriarty may be contacted at kmoriarty@hbblaw.com
Ms. Davis may be contacted at ydavis@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Washington Court Denies Subcontractor’s Claim Based on Contractual Change and Notice Provisions
January 29, 2024 —
Wendy Rosenstein - Ahlers Cressman & Sleight PLLCThe recent unpublished case, Cascade Civil Construction, LLC v. Jackson Dean Construction, Inc., et al.,[1] provides a legal justification for contractors to require a directive or change order in advance of performing changed work—thereby preventing the party who requested the changed work from later arguing that notice provisions were not complied with.
In the case, Jackson Dean, the prime contractor, hired Cascade to perform excavation work on a project to build a new Costco Corporate headquarters. Due to the Covid-19 pandemic and other issues, Jackson Dean directed resequencing, which required Cascade to perform excavation concurrent to dewatering. Jackson Dean also required deeper-than-planned excavation under one of the buildings.
Read the court decisionRead the full story...Reprinted courtesy of