When is a “Notice of Completion” on a California Private Works Construction Project Valid? Why Does It Matter for My Collection Rights?
January 27, 2020 —
William L. Porter - Porter Law GroupWhat is a Notice of Completion?
A “notice of completion” is a document recorded by the owner of property where construction work was performed. Specifically, it is recorded at the Office of the County Recorder in the County where the work was performed. The notice of completion tells the world at large that the construction project is complete. It also triggers the deadlines for those who have not been paid to make their claims for payment.
Is an Owner of a California Private Works Project Required to Record a Notice of Completion?
No, there is no requirement that an owner of a California private works construction project record a Notice of Completion. However, there are consequences which depend on whether an Owner elects to record the notice or not.
For My Collection Rights, Why Does it Matter Whether a Notice of Completion Has Been Recorded?
The date of recording of a valid notice of completion sets the deadline for those who have not been paid for work performed and materials supplied to a California construction project to pursue such important collection remedies as the “mechanics lien”, the “stop payment notice” and the “payment bond claim.” These are very powerful collection remedies for those who have not been paid. If the deadline to pursue these remedies is missed by a claimant, then the claimant’s right to pursue these remedies is also missed. One of these remedies, the mechanics lien, will enable the claimant to sell the owner’s property where the work was performed in order to get paid.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
The Importance of a Notice of Completion to Contractors, Subcontractors and Suppliers
August 12, 2024 —
William L. Porter - Porter Law GroupThe recording of a valid “Notice of Completion” with the County Recorder is an event of significance to owners, contractors, subcontractors and suppliers alike. The recording of a Notice of Completion is one of several methods used to trigger the time period for the recording of mechanics liens and service of stop payment notices. Although the recording of a Notice of Completion is not absolutely required on any given project, all those working in the construction industry should understand its significance.
When a valid Notice of Completion has not been recorded in relation to a construction project, a contractor, subcontractor, or supplier might from ninety to one hundred fifty days after completion of the project to record a mechanics lien or serve a stop payment notice to secure payment for their services on the project, depending on the facts. However, if a valid Notice of Completion is recorded, then the deadline under most circumstances accelerates and subcontractors and suppliers must record a mechanics lien or serve a stop payment notice within only thirty days thereafter. Under the same circumstances, a prime contractor has only sixty days after the recording of a valid Notice of Completion to record a mechanics’ lien. Failure to meet these deadlines often results in loss of the right to a mechanics lien or stop payment notice. There are limited exceptions to these general deadlines, depending on the facts. If you believe you may have missed an important deadline to seek collection of a construction debt, you should consult with a construction attorney immediately to secure your avenues of collection, including the mechanics lien and stop payment notice remedies, if still available.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
New York Court Holds Radioactive Materials Exclusion Precludes E&O Coverage for Negligent Phase I Report
October 30, 2018 —
Brian Margolies - TLSS Insurance Law BlogIn its recent decision in Merritt Environmental Consulting Corp. v. Great Divide Ins. Co., 2018 U.S. Dist. LEXIS 175527 (E.D.N.Y. Oct. 10, 2018), the United States District Court for the Eastern District of New York had occasion to consider the application of a radioactive materials exclusion in a professional liability policy.
Great Divide’s insured, Merritt Environmental, was hired as an environmental consultant by a bank in connection with a mortgage refinance of a property located in Westchester County, New York. Merritt’s responsibility was to prepare a Phase I environmental report concerning the property, which the bank ultimately relied on in agreeing to the refinance. It was later claimed, however, that Merritt’s report failed to document the full extent of the property’s radium and uranium contamination resulting from its use in the Manhattan Project. Merritt was named in two separate lawsuits as a result of its allegedly faulty report, including one by the bank alleging that Merritt negligently prepared its report.
Read the court decisionRead the full story...Reprinted courtesy of
Brian Margolies, Traub Lieberman Straus & Shrewsberry LLPMr. Margolies may be contacted at
bmargolies@tlsslaw.com
Suzanne Pollack Elected to Lawyers Club of San Diego 2021 Board of Directors
May 03, 2021 —
Suzanne Pollack - Lewis BrisboisSan Diego Associate Suzanne Pollack was recently elected to the 2021 Lawyers Club of San Diego Board of Directors for a three-year term that will begin on July 1, 2021. Founded in 1972, the mission of Lawyers Club - San Diego’s largest specialty bar association - is to advance the status of women in the law and society.
“I am honored to be joining Lawyers Club’s Board of Directors, particularly after this last year, during which we saw the dramatic impact that the pandemic had upon women in the workforce," said Ms. Pollack. "Promoting equality, diversity, and advocacy has never been more important, and I look forward to working with the Board to further these goals.”
Read the court decisionRead the full story...Reprinted courtesy of
Suzanne Pollack, Lewis BrisboisMs. Pollack may be contacted at
Suzanne.Pollack@lewisbrisbois.com
Appraisal Award for Damaged Roof Tiles Challenged
December 04, 2023 —
Tred R. Eyerly - Insurance Law HawaiiThe district court denied Travelers' motion for summary judgment and granted the insureds' motion in part regarding replacement of roof tiles damaged in a hail storm. Bertisen v. Travelers Home & Marine Ins. Co., 2023 U.S. Dist. LEXIS 159649 (D. Colo. Sept. 8,2023).
On May 8, 2017, the insureds' home was struck by a hailstorm that damaged their property. A Travelers inspector found damage to metal roof components, a deck, patio furniture and gutters. A partial payment of $6,381.04 was made. A further payment was made for personal property damaged by the storm. Travelers disputed that the hailstorm caused damage to all of the roof tiles.
Travelers' adjustor reinspected the property and observed additional damages caused by hail and another payment of $6,605.22 was issued.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Construction Case Alert: Appellate Court Confirms Engineer’s Duty to Defend Developer Arises Upon Tender of Indemnity Claim
January 27, 2010 —
Steven M. CvitanovicIn the recent case of UDC-Universal Development, L.P. v. CH2M Hill, 2010 Cal.App.LEXIS 47 (filed January 15, 2010), the Sixth District Court of Appeal provided a stunning illustration of the far-reaching effects of the California Supreme Court’s holding in Crawford v. Weather Shield Manufacturing Inc. (2008) 44 Cal.4th 541. In Crawford, the Court held the duty to defend under an indemnity agreement arose upon the mere tender of defense of a claim covered by the indemnity.
In the UDC case, CH2M Hill provided engineering and environmental planning services to developer UDC on a project that ultimately wound up in a construction defect lawsuit by the homeowners association ( HOA ). UDC tendered its defense to CH2M Hill, the tender was rejected, and UDC filed a cross-complaint for negligence, breach of contract and indemnity against CH2M Hill and others. After the HOA’s construction defect claims were settled, UDC proceeded to trial against CH2M Hill. The jury found in favor of CH2M Hill on the claims for negligence and breach of contract. At the request of the parties prior to trial, the trial court ruled on the application of the indemnity agreement in light of Crawford and, in so doing, found that the defense obligation arose upon the tender and that CH2M Hill breached that duty despite the jury finding in favor of CH2M Hill.
The Court of Appeal affirmed, noting that the defense obligation arose as soon as the defense was tendered and did not depend on the outcome of the litigation, and that the HOA’s general description of the defects along with an allegation that Doe engineers were negligent triggered the duty to defend.
Although this case did not expand the crushing impact of Crawford’s holding, it is
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
Harmon Tower Construction Defects Update: Who’s To Blame?
August 17, 2011 —
CDJ STAFFReporting on the site VegasInc.com, Liz Benton notes that “nobody wants to take the fall for what happened at Harmon.” Work on the Harmon hotel building in Las Vegas’s CityCenter stopped in 2008 after 26 of the planned 49 stories were completed. Lorence Slutzky, a construction law professor at John Marshall Law School and a partner with the Chicago firm Robbins Schwartz Nicholas Lifton & Taylor told Benton that while inspectors and others are complicit, “the real responsibility rests with Perini, which has an obligation to comply with the plan specifications.” Perini’s claim is that they were given faulty design drawings. MGM disputes this.
Perini has offered to repair the building defects, however MGM has released a statement that they have “zero confidence or trust that Perini can and will properly fix a building it has so badly constructed thus far.” One MGM spokesperson likened these requests from Perini to “the director of ‘Ishar’ demanding a sequel.” “Ishtar,’ cost Columbia Pictures $55 million dollars and earned only $4.2 million in its initial run. Perini claims that MGM halted work because of the economy.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Indictments Issued in Las Vegas HOA Scam
January 22, 2013 —
CDJ STAFFA federal grand jury has indicted eleven individuals involved in the Las Vegas homeowners association scam. Leon Benzer, Keith Gregory, and Barry Levinson were all indicted for their roles in the scam, where conspirators took over homeowners associations in order to profit from construction defect suits. According to the Las Vegas Review Journal, all eleven were charged with conspiracy to commit mail and wire fraud. Mr. Levinson's license to practice law has been suspended due to an investigation that he misappropriated client funds. Mr. Benzer has been described as the "mastermind" of the scam.
Twenty-eight defendants have plead guilty, with all but one agreeing to cooperate with investigators. The report quotes William C. Woerner, the acting special agent in charge of the FBI in Las Vegas, as saying that "today's indictment demonstrates the continued commitment of the FBI and its law enforcement partners to identify and root out public corruption at all levels."
Read the court decisionRead the full story...Reprinted courtesy of