Economic Damages and the Right to Repair Act: You Can’t Have it Both Ways
March 16, 2017 —
Garret Murai – California Construction Law BlogIn 2002, the California State Legislature passed Senate Bill 800 also known as the Right to Repair Act (Civil Code Sections 895 et seq.) in an effort to stem a then rising tide in residential construction defect litigation.
SB 800, which applies to newly constructed residential units including single-family homes and condominiums (but not condominium conversions) sold after January 1, 2003, was intended to curb residential construction defect lawsuits by giving developers and others in the construction chain an opportunity to repair construction defects before being sued in court. SB 800 also provides minimum construction standards and limits the time in which a homeowner can bring a claim for construction defects.
In Acqua Vista Homeowners Association v. MWI, Case No. D068406 (January 26, 2017), the California Court of Appeals for the Fourth District examined the circumstances in which homeowners can sue a material supplier under the Right to Repair Act.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
History of Defects Leads to Punitive Damages for Bankrupt Developer
March 01, 2012 —
CDJ STAFFThe South Carolina Court of Appeals has ruled that evidence of construction defects at a developer’s other projects were admissible in a construction defect lawsuit. They issued their ruling on Magnolia North Property Owners’ Association v. Heritage Communities, Inc. on February 15, 2012.
Magnolia North is a condominium complex in South Carolina. The initial builder, Heritage Communities, had not completed construction when they filed for bankruptcy protection under Chapter 11. The remaining four buildings were completed by another contractor. The Property Owners’ Association subsequently sued Heritage Communities, Inc. (HCI) alleging defects. The POA also sued Heritage Magnolia North, and the general contractor, BuildStar.
The trial court ruled that all three entities were in fact one. On appeal, the defendants claimed that the trial court improperly amalgamated the defendants. The appeals court noted, however, that “all these corporations share officers, directors, office space, and a phone number with HCI.” Until Heritage Communities turned over control of the POA to the actual homeowners, all of the POA’s officers were officers of HCI. The appeals court concluded that “the trial court’s ruling that Appellants’ entities were amalgamated is supported by the law and the evidence.”
Heritage also claimed that the trial court should not have allowed the plaintiffs to produce evidence of construction defects at other Heritage properties. Heritage argued that the evidence was a violation of the South Carolina Rules of Evidence. The court cited a South Carolina Supreme Court case which made an exception for “facts showing the other acts were substantially similar to the event at issue.” The court noted that the defects introduced by the plaintiffs were “virtually identical across all developments.” This included identical use of the same products from project to project. Further, these were used to demonstrate that “HCI was aware of water issues in the other projects as early as 1998, before construction on Magnolia North had begun.”
The trial case ended with a directed verdict. Heritage charged that the jury should have determined whether the alleged defects existed. The appeals court noted that there was “overwhelming evidence” that Heritage failed “to meet the industry standard of care.” Heritage did not dispute the existence of the damages during the trial, they “merely contested the extent.”
Further, Heritage claimed in its appeal that the case should have been rejected due to the three-year statute of limitations. They note that the first meeting of the POA was on March 8, 2000, yet the suit was not filed until May 28, 2003, just over three years. The court noted that here the statute of limitation must be tolled, as Heritage controlled the POA until September 9, 2002. The owner-controlled POA filed suit “approximately eight months after assuming control.”
The court also applied equitable estoppel to the statute of limitations. During the time in which Heritage controlled the board, Heritage “assured the unit owners the construction defects would be repaired, and, as a result, the owners were justified in relying on those assurances.” Since “a reasonable owner could have believed that it would be counter-productive to file suit,” the court found that also prevented Heritage from invoking the statute of limitations. In the end, the appeals court concluded that the even apart from equitable tolling and equitable estoppel, the statute of limitations could not have started until the unit owners took control of the board in September, 2002.
Heritage also contested the jury’s awarding of damages, asserting that “the POA failed to establish its damages as to any of its claims.” Noting that damages are determined “with reasonable certainty or accuracy,” and that “proof with mathematical certainty of the amount of loss or damage is not required,” the appeals court found a “sufficiently reasonable basis of computation of damages to support the trial court’s submission of damages to the jury.” Heritage also claimed that the POA did not show that the damage existed at the time of the transfer of control. The court rejected this claim as well.
Finally, Heritage argued that punitive damages were improperly applied for two reasons: that “the award of punitive damages has no deterrent effect because Appellants went out of business prior to the commencement of the litigation” and that Heritages has “no ability to pay punitive damages.” The punitive damages were upheld, as the relevant earlier decision includes “defendant’s degree of culpability,” “defendants awareness or concealment,” “existence of similar past conduct,” and “likelihood of deterring the defendant or others from similar conduct.”
The appeals court rejected all of the claims made by Heritage, fully upholding the decision of the trial court.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Contract’s Definition of “Substantial Completion” Does Not Apply to Third Party for Purposes of SOL, Holds Court of Appeal
June 15, 2020 —
Garret Murai - California Construction Law BlogThose of you in the construction industry know that the two primary statutes of limitation are the 4-year year statute of limitations for patent defects and 10-year statute of limitations for latent defects. Both statutes begin to run on “substantial completion.”
In Hensel Phelps Construction Co. v. Superior Court of San Diego, Case No. D076264 (January 22, 2020), the 4th District Court of Appeal examined whether the term “substantial completion,” as used in Civil Code section 941, which applies to residential construction, can be defined by the parties’ contract and applied to third-parties.
The Hensel Phelps Case
Hensel Phelps Construction Co. entered into a prime construction contract with the owner and developer of a mixed-use project in San Diego. Hensel Phelps was the general contractor on the project. The project included a residential condominium tower which would eventually be managed and maintained by Smart Corner Owners Association. Smart Corners was not a party to the contract.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
OSHA Advisory Committee, Assemble!
February 06, 2023 —
Rachel E. Pelovitz - Construction ExecutiveThe Occupational Safety and Health Administration (OSHA) has sourced new members for its Advisory Committee on Construction Safety and Health, which was established by the Construction Safety Act to provide “advice and assistance in construction standards and policy matters” to the assistant secretary of labor for occupational safety and health. The committee consists of 15 members, one appointed by the secretary of labor, to represent the interests of employers, employees, state safety and health agencies, in addition to the public.
Reprinted courtesy of
Rachel E. Pelovitz, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Ms. Pelovitz may be contacted at pelovitz@abc.org
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Independent Contractor v. Employee. The “ABC Test” Does Not Include a Threshold Hiring Entity Test
October 03, 2022 —
Garret Murai - California Construction Law BlogIn 2018, in Dynamex Operations West, Inc. v. Superior Court, 4 Cal.5th 903 (2018), the California Supreme Court overturned nearly thirty years of jurisprudence governing the manner in which workers are classified as employees or independent contractors. The Dynamex decision replaced the “Borello test,” derived from a case of the same name, S.G. Borello & Sons, Inc. v. Department of Industrial Relations, 48 Cal.3d 341 (1989), in which the California Supreme Court at the time set forth a variety of factors to be considered when determining whether a worker was an employee or independent contractor.
The Dynamex decision replaced with the “Borello test” with the “ABC test.” Under the ABC test, a worker can be deemed an independent contractor if three conditions are met:
- The worker is free from the control and direction of the hiring entity in connection with the performance of the work, both under the contract for the performance of the work and in fact;
- The worker performs work that is outside the usual course of the hiring entity’s business; and
- The worker is customarily engaged in an independent established trade, occupation, or business
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Sometimes it Depends on “Whose” Hand is in the Cookie Jar
January 21, 2015 —
Roger Hughes – California Construction Law BlogIn a lengthy and somewhat detailed decision, the California Court of Appeal for First District, in Pittsburg Unified School District v. S.J. Amoroso Construction Company, Inc., Case No. A138825 (December 22, 2014), held that a public entity could unilaterally withdraw retention funds during a pending legal dispute without the court first finding that the contractor had defaulted on the public works project.
Background
In 2008, general contractor S.J. Amoroso Construction Company, Inc. (“S.J. Amoroso”) entered into a construction contract with the Pittsburg Unified School District (“District”) for the reconstruction and modernization of a high school in Pittsburg, California.
Read the court decisionRead the full story...Reprinted courtesy of
Roger Hughes, Wendel Rosen Black & Dean LLPMr. Hughes may be contacted at
rhughes@wendel.com
Deadline for Hurricane Ian Disaster Recovery Applications Announced
October 17, 2022 —
Lewis BrisboisWashington, D.C. (October 11, 2022) - On Friday, October 7, 2022, the Florida Division of Emergency Management (FDEM) announced that applications for the Federal Emergency Management Agency’s (FEMA) Public Assistance Grant Program are due by October 29, 2022.
FEMA provides disaster recovery assistance to eligible individuals, families, governments, and private non-profit entities. However, the process for recovering costs is complicated, and FEMA has broad discretion to determine whether applicants and their expenses are eligible. All too often, failure to understand FEMA regulations or submit sufficient documentation results in FEMA denying applicants’ claims, leaving individuals, local governments, and non-profits to bear the full cost of recovery.
While ensuring successful recovery through the FEMA grant program can be challenging, clients can increase their likelihood of success when preparing the initial application and documentation by enlisting experienced legal counsel who understand the FEMA process and regulations.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
It’s All a Matter of [Statutory] Construction: Supreme Court Narrowly Interprets the Good Faith Dispute Exception to Prompt Payment Requirements in United Riggers & Erectors, Inc. v. Coast Iron & Steel Co.
May 30, 2018 —
Erinn Contreras & Joy O. Siu - Sheppard Mullin Construction & Infrastructure Law BlogOn May 14, 2018, the California Supreme Court issued its opinion in United Riggers & Erectors, Inc. v. Coast Iron & Steel Co., No. S231549, slip. op. (Cal. Sup. Ct. May 14, 2018). In it, the Court narrowly construed the “good faith” exception to the general rule that a direct contractor must make retention payments to its subcontractors within 10 days of receiving any retention payment. The exception provides that “[i]f a good faith dispute exists between the direct contractor and a subcontractor, the direct contractor may withhold from the retention to the subcontractor an amount not in excess of 150 percent of the estimated value of the disputed amount.” Cal. Civ. Code section 8814(c).
Reprinted courtesy of
Erinn Contreras, Sheppard Mullin and
Joy O. Siu, Sheppard Mullin
Ms. Contreras may be contacted at econtreras@sheppardmullin.com
Ms. Siu may be contacted at jsiu@sheppardmullin.com
Read the court decisionRead the full story...Reprinted courtesy of