Reminder: Pay if Paid Not All Encompassing (but Could it be?)
December 09, 2019 —
Christopher G. Hill - Construction Law MusingsOn numerous occasions, I have discussed the need to be careful with so called “pay if paid” clauses in construction contracts. While such clauses are enforceable in Virginia (when phrased correctly), there are exceptions and limitations (for instance in the Miller Act context).
One such exception (that I frankly would have thought to be obvious) is that such clauses do not protect a general contractor from paying all subcontractors. Such a clause only protects a general contractor from payment to those subs for whose work the general contractor has not been paid. In other words, if a general contractor has been paid by an owner for a particular subcontractors work, it cannot use the pay if paid clause to deny payment even in the event that other subcontractors were deficient in their work or the owner has failed to pay the general contractor in full.
In Precision Contractors Inc. v. Masterbuilt Companies Inc. (PDF) the Fairfax, VA Circuit Court reiterated this principal stating that nothing in the contract suggests that either party to the lawsuit had any intention to shift the risk of non-payment by the owner or non-performance of other subcontractors to the plaintiff (Precision).
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Illinois Court Addresses Rip-And-Tear Coverage And Existence Of An “Occurrence” In Defective Product Suit
September 04, 2018 —
Brian Bassett - TLSS Insurance Law BlogIn Lexington Ins. Co. v. Chi. Flameproof & Wood Specialties Corp., 2018 U.S. Dist. LEXIS 135871, 2018 WL 3819109 (N.D. Ill. Aug. 10, 2018), the U.S. District Court for the Northern District of Illinois found that rip-and-tear costs could qualify as covered “property damage,” but the court rejected coverage for claims that the insured intentionally sold a noncompliant product as the suit did not allege an “occurrence.”
Lexington Insurance Company (“Lexington”) issued a CGL policy to Chicago Flameproof & Wood Specialties Corp. (“Flameproof”). During the policy period, a third party ordered fire-retardant-treated lumber from Flameproof for construction in Minnesota. Flameproof instead sent materials that were not tested, certified, or labeled as compliant. The third party installed the materials, discovered the non-compliance, and then removed the materials. Removing the materials allegedly damaged other portions of the building on the project. The third party then sued Flameproof, alleging costs associated with replacing the lumber as well as property damage to the other materials from the removal of the lumber. Flameproof tendered the claim to Lexington seeking a defense. Lexington filed a declaratory action in the Northern District of Illinois.
Read the court decisionRead the full story...Reprinted courtesy of
Brian Bassett, Traub Lieberman Strauss & Shrewsberry LLPMr. Bassett may be contacted at
bbassett@tlsslaw.com
Construction Litigation Roundup: “How Bad Is It?”
September 25, 2023 —
Daniel Lund III - LexologyHow bad is it?
“Not that bad,” said an Illinois federal court to a surety which was complaining that its subcontract performance bond terms had not been satisfied by the obligees on the bonds (the general contractor and the building owner).
In response to $3.6 million demand by the obligees on the performance bond, the surety filed an action in federal court in Illinois seeking to have the court declare that the surety had no further obligation on its performance bond. The surety urged that the obligees had not fulfilled the prerequisite requirements in the bond to make a claim on the bond (which, although the court never identified the bond form, was a bond form that closely resembled the AIA A312-2010 performance bond).
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Design & Construction Case Expands Florida’s Slavin Doctrine
January 21, 2015 —
Beverley BevenFlorez-CDJ STAFFAccording to Amanda Baggett of Rogers Towers, Florida’s “Fourth District Court of Appeal appears to have expanded the Slavin doctrine in the context of design professional liability” in the case McIntosh v. Progressive Design and Engineering, Inc. (Jan. 7, 2015). McIntosh, a personal injury case, involved whether the design and construction of an intersection with multiple traffic signals in close proximity created confusion for drivers.
Baggett stated that McIntosh expanded the Slavin doctrine in two ways: “first, the ruling eliminates the requirement that the ultimate owner of a project accept the project before the Slavin doctrine may be invoked. Second, the decision applies the Slavin doctrine to completed and accepted design plans without regard to the completion of the project for which they were prepared.”
Read the court decisionRead the full story...Reprinted courtesy of
The International Codes Development Process is Changing to Continue Building Code Modernization
March 06, 2023 —
The International Code CouncilWashington D.C., March 02, 2023 (GLOBE NEWSWIRE) -- The International Code Council is revising its rigorous code development process. The changes will take effect in 2024-2026 for the development of the 2027 International Codes (I-Codes) and will move the development process to an integrated and continuous three-year cycle.
In the new timeline, year one will include two Committee Action Hearings for Group A Codes; year two will include two Committee Action Hearings for Group B Codes; and year three will be the joint Public Comment Hearings and Online Governmental Consensus Vote for both Group A and B Codes.
The addition of the second Committee Actions Hearings in year one and two will foster a more in-depth vetting of code change proposals, allowing an opportunity for the committee members to review and evaluate the original proposals and consider the submitted responses. This also provides more opportunity for proponents to build consensus for their code change proposal and ensure the best version of their intended improvement to the existing codes.
Additionally, with combined Public Comment Hearings in the third year, voting members are able to vote on all suggested changes to the next edition of the I-Codes at one time. The updated process also provides more opportunity for proposed new referenced standards to be developed and finalized on a consistent timeline regardless of the group (Group A or B) with which they are associated.
About the International Code Council
The International Code Council is the leading global source of model codes and standards and building safety solutions. Code Council codes, standards and solutions are used to ensure safe, affordable and sustainable communities and buildings worldwide.
Read the court decisionRead the full story...Reprinted courtesy of
Take Advantage of AI and Data Intelligence in Construction
May 06, 2019 —
Nick Carter - Construction ExecutiveFor consumers, AI and data intelligence are daily activities. Purchase recommendations from Amazon simplify holiday shopping. Music options from Spotify helps employees focus during the workday and relax at night. Car-sharing apps remove the stress from post-happy hour transport.
It is time for this kind of data-driven ease to hit the construction industry. Building is booming, yet despite the good times, the industry still lags in terms of data intelligence and AI. With them, construction providers can transform document and jobsite information into intelligent insights, reduce errors, keep projects on schedule and predict and prevent costly inefficiencies. Artificial intelligence is the “connective tissue” that construction is missing--if it is used wisely.
Why Construction is Ready for AI
With its endless stream of owners, architects, engineers, contractors, subcontractors and suppliers, the construction industry manages more critical information on a day-to-day basis than nearly any other business. As a result, there are dozens of potential miscommunications just waiting to happen every day.
Reprinted courtesy of
Nick Carter, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
While You Were Getting Worked Up Over Oil Prices, This Just Happened to Solar
October 29, 2014 —
Tom Randall – BloombergEvery time fossil fuels get cheaper, people lose interest in solar deployment. That may be about to change.
After years of struggling against cheap natural gas prices and variable subsidies, solar electricity is on track to be as cheap or cheaper than average electricity-bill prices in 47 U.S. states -- in 2016, according to a Deutsche Bank report published this week. That’s assuming the U.S. maintains its 30 percent tax credit on system costs, which is set to expire that same year.
Even if the tax credit drops to 10 percent, solar will soon reach price parity with conventional electricity in well over half the nation: 36 states. Gone are the days when solar panels were an exotic plaything of Earth-loving rich people. Solar is becoming mainstream, and prices will continue to drop as the technology improves and financing becomes more affordable, according to the report.
Read the court decisionRead the full story...Reprinted courtesy of
Tom Randall, BloombergMr. Randall may be contacted at
trandall6@bloomberg.net
Construction Contract Clauses Only a Grinch Would Love – Part 4
November 30, 2016 —
Garret Murai – California Construction Law BlogScope, time and cost provisions may be the most important clauses in your construction contract but they’re not the only ones which can impact your bottom line. The fourth and final part in a multi-part series, here are some other important construction contract clauses that can put a damper on your holidays.
Provision: Warranty Provisions
- Typical Provision: “Subcontractor warrants to Contractor that all materials and equipment furnished shall be new unless otherwise specified and that all Work performed shall be performed in a good and workmanlike manner, of good quality and free from defects, and in conformance with industry standards, manufacturer’s recommendations and the Contract Documents. All work not conforming to these requirements, including substitutions not properly approved, shall be considered defective. Subcontractor agrees to promptly make good any and all defects due to faulty workmanship, materials and/or equipment which may appear within the Contract Documents, and if no such period is stipulated in the Contract, then for a period of one year from the date of acceptance by the Owner. Nothing herein shall shorten or limit any applicable periods of limitations including, but not limited to, those set forth in Civil Code, Part 2, Title 2, Chapter 3.”
- What it Means: Warranty periods are subject to the agreement of the parties. However, warranties are different than limitations periods, such as California’s 4 year statute of repose for patent defects and 10 year statute of repose for latent defects (note: a statute of repose is different than a statute of limitation. A statute of repose sets a deadline based on an event. So, for example, under the 10 year statute of repose for latent defects a claimant must bring a latent defect claim within 10 years following substantial completion even if the latent defect wasn’t discovered until 10 years and 1 month following substantial completion. A statute of limitation, in contrast, sets a deadline based on the occurrence of an injury or damage. So, for example, California has a 2 year statute of limitation for personal injuries, which sets a deadline of 2 years from the date of injury to bring a personal injury claim). Warranty periods are also different from limitations periods because most warranties require work to be corrected at no cost, and because many contracts include attorney’s fee provisions, breach of a warranty can give rise to claim for attorney’s fees as well.
- What You Can Do: Lower-tiered parties should examine warranty provisions to see if they are reasonable, and if not reasonable, should seek to either eliminate or limit those provisions, such as by reducing the warranty period or providing different warranty periods for different components of work, etc.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com