Quick Note: Aim to Avoid a Stay to your Miller Act Payment Bond Claim
February 23, 2017 —
David Adelstein – Florida Construction Legal UpdatesStrategy is important. This is especially true if you are trying to avoid arbitration. In a recent federal district court case, a subcontractor sued the prime contractor and the Miller Act payment bond surety. The subcontractor, however, had an arbitration provision in its subcontract with the prime contractor. The prime contractor moved to compel arbitration pursuant to the subcontract and moved to stay the subcontractor’s Miller Act payment bond claim. The last thing, and I mean the last thing, the subcontractor wanted to do was to stay its claim against the Miller Act payment bond. However, the district court compelled the subcontractor’s claim against the prime contractor to arbitration and stayed the subcontractor’s Miller Act payment bond claim pending the outcome of the arbitration. See U.S. v. International Fidelity Ins. Co., 2017 WL 495614 (S.D.Al. 2017). This is not what the subcontractor wanted.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Contractual Waiver of Consequential Damages
January 21, 2019 —
David Adelstein - Florida Construction Legal UpdatesContractual waivers of consequential damages are important, whether they are mutual or one-sided. I believe in specificity in that the types of consequential damages that are waived should be detailed in the waiver of consequential damages provision. Standard form construction agreements provide a good template of the types of consequential damages that the parties are agreeing to waive.
But, what if there is no specificity in the waiver of consequential damages provision? What if the provision just states that the parties mutually agree to waive consequential damages or that one party waives consequential-type damages against the other party? Let me tell you what would happen. The plaintiff will argue that the damages it seeks are general damages and are NOT waived by the waiver of consequential damages provision. The defendant, on the other hand, will argue that the damages are consequential in nature and, therefore, contractually waived. FOR THIS REASON, PARTIES NEED TO APPRECIATE WHAT DAMAGES ARE BEING WAIVED OR LIMITED, AND POTENTIALLY THOSE DAMAGES NOT BEING WAIVED OR LIMITED, WHEN AGREEING TO A WAIVER OF CONSEQUENTIAL DAMAGES PROVISION!
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Microwave Transmission of Space-Based Solar Power: The Focus of New Attention
July 24, 2023 —
Robert A. James & William E. Fork - Gravel2Gavel Construction & Real Estate Law BlogScientists have long proposed that solar electricity generation in space could be an integral component of the world’s carbon-free future. In the 1970s, a U.S. Navy experiment showed that it might be possible to capture solar power and wirelessly transmit it from outer space using microwave beams. Progress stalled after that early test—the models used were at such a massive scale that creating a real-world system felt like science fiction. Recently, amid growing concerns about power grid security and intensifying legislation around carbon emissions, renewed attention focused on a smaller, more lithe microwave transmission system. This time around, the military is not the only interested party. Scientists around the world are conducting similar research. As investors and governments stand at the edge of a fresh green power opportunity, we look at microwave power transmission and some of the projects in this emerging field.
The basic premise of space-based solar power technology is simple enough: photovoltaic panels on a satellite in space convert the sun’s energy to electromagnetic waves at microwave frequencies. The satellite then beams the microwave energy to a receiver on Earth that transforms it into direct current. Until recently, this technique had been performed on the ground over short distances, but nobody had attempted to launch a solar panel into space. The status quo has shifted over the past few years as researchers have begun to send prototypes into orbit. In early 2023, CalTech was the first to report a breakthrough. Its model successfully beamed power from space back to their receiver atop a building in California.
Reprinted courtesy of
Robert A. James, Pillsbury and
William E. Fork, Pillsbury
Mr. James may be contacted at rob.james@pillsburylaw.com
Mr. Fork may be contacted at william.fork@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
The Coronavirus, Zoom Meetings and Now a CCPA Class Action
April 13, 2020 —
Jeffrey M. Dennis & Heather H. Whitehead - Newmeyer DillionWith the ongoing COVID-19 (commonly referred to as the Coronavirus) pandemic and orders to “stay at home” in place across the United States, most organizations have been and continue to utilize remote arrangements. The software program known as “Zoom Meetings”, has become immensely popular as a means to facilitate meetings amongst employees, team members and other consultants rather than meeting in person.
Despite such status, Zoom Video Communications, Inc. (Zoom) has been named as a defendant in one of the first, and certainly the most high-profile, class action lawsuits to be filed in California alleging violations of the California Consumer Privacy Act of 2018 (CCPA).
The Class Action
The complaint filed alleges that Zoom did not protect the personal information of its users as it collected personal information and then shared such information to third parties, including Facebook, without adequate disclosures to users. The allegations specifically refer to Zoom’s boasting about its maintenance of users’ privacy and that they can be trusted with user data. Further, it is noted that there is no disclosure provided in the Zoom Privacy Policy that disclosed that personal information was being shared with Facebook and other third parties.
Reprinted courtesy of
Jeffrey M. Dennis, Newmeyer Dillion and
Heather H. Whitehead, Newmeyer Dillion
Mr. Dennis may be contacted at jeff.dennis@ndlf.com
Ms. Whitehead may be contacted at heather.whitehead@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Pennsylvania Federal Court Confirms: Construction Defect Claims Not Covered by CGL Policies
March 06, 2022 —
Nathan A. Cazier & Scott S. Thomas - Payne & FearsThe construction industry operates under the constant spectre of claims seeking damages for defective or faulty workmanship. Fortunately, the law in most states treats these claims as covered under commercial general liability (“CGL”) policies. A small minority of states take a much stingier view. In a newly decided case, a Pennsylvania federal court confirmed that Pennsylvania belongs to this small group of states that regard construction claims as not worthy of liability insurance coverage. Main St. Am. Assurance Co. v. Howard Lynch Plastering, Inc., No. CV 21-3977, 2022 WL 445768, (E.D. Pa. Feb. 14, 2022).
Main St. involves a typical construction defect case: W.B. Homes (“W.B.”) developed a residential community, contracting with various trades to build the homes. W.B. required these subcontractors to obtain liability insurance covering their work and, when homeowners sued W.B. for damages due to allegedly faulty work, W.B. tendered the claim to these insurers. One of them, Main Street Assurance Co. (“Main Street”) then sued W.B. for declaratory relief, arguing that under Pennsylvania law, it had no duty to defend W.B.
Reprinted courtesy of
Nathan A. Cazier, Payne & Fears and
Scott S. Thomas, Payne & Fears
Mr. Cazier may be contacted at nac@paynefears.com
Mr. Thomas may be contacted at sst@paynefears.com
Read the court decisionRead the full story...Reprinted courtesy of
Cal/OSHA ETS: Newest Version Effective Today
January 17, 2022 —
Amy R. Patton, Matthew C. Lewis & Rana Ayazi - Payne & FearsThe newest version of the Cal/OSHA ETS goes into effect today, Jan. 14, 2022, and will expire on April 15, 2022. A redline of the recently expired Cal/OSHA ETS and the newest Cal/OSHA ETS is available HERE. The newest Cal/OSHA ETS, which was drafted prior to Dec. 16, 2021, is already partially out-of-date based on the California Department of Public Heath’s Guidance For the Use of Masks (released Jan. 5, 2022) and the CDPH’s Guidance for Local Health Jurisdictions on Isolation and Quarantine of the General Public (released Jan. 8, 2022); these changes have been addressed in the Cal/OSHA ETS FAQs.
With all of these changes occurring (not to mention all of the litigation surrounding the now-stayed federal OSHA ETS), California employers are asking: How do I comply with the current Cal/OSHA ETS and the updated CDPH Guidance? Here are the key points to ensure you are in compliance:
- New Shorter Isolation and Quarantine Periods
Isolation: When an employee has COVID-19 (even without symptoms).
- Day 0: First day of symptoms or the day a positive test specimen was collected. Begin isolation.
- Day 1: First full day after symptoms developed or positive test specimen was collected.
- Day 5: Recommended day to take COVID-19 test.
Reprinted courtesy of
Amy R. Patton, Payne & Fears,
Matthew C. Lewis, Payne & Fears and
Rana Ayazi, Payne & Fears
Ms. Patton may be contacted at arp@paynefears.com
Mr. Lewis may be contacted at mcl@paynefears.com
Ms. Ayazi may be contacted at ra@paynefears.com
Read the court decisionRead the full story...Reprinted courtesy of
California Supreme Court Holds that Prevailing Wages are Not Required for Mobilization Work, for Now
October 18, 2021 —
Garret Murai - California Construction Law BlogIn the midst of the Great Depression the federal government enacted the Davis-Bacon Act (40 U.S.C. section 32141 et seq.) to help workers on federal construction projects. Under the Davis-Bacon Act, minimum wages must be paid to workers on federal public works projects based on local “prevailing” wages. At the time, the goal of the law was to help curb the displacement of families by employers who were recruiting lower-wage workers from outside local areas. A darker history suggests that it was also intended to discourage minority workers from competing with unionized white workers.
Fast forward to today. Many states, including California, adopted “Little Davis-Bacon” laws applying similar requirements on state and local public works projects. California’s prevailing wage law (Labor Code section 1720 et seq.) requires contractors on state and local public works projects pay their workers the general prevailing rate of per diem wages based on the classification or type of work performed by the employee in the locality where the project is located.
Over the years, labor unions have sought to expand the definition of what constitutes a “public works project” from private residential developments receiving public funding (generally, prevailing wages required) to off-site fabrication of materials at permanent facility for a public works project (no prevailing wages required) to enforcement mechanisms such as making a general contractor liable for prevailing wage violations of its subcontractors (yes, indeedy, see Labor Code section 1775).
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
New York’s Highest Court Weighs in on N.Y. Labor Law
September 23, 2024 —
Bill Wilson - Construction Law ZoneN.Y. Labor Law § 241(6) requires owners and contractors to provide reasonable and adequate protection and safety to persons employed at or lawfully frequenting a construction site. If a worker is injured on a construction site and establishes a violation of a specific and applicable Industrial Code regulation, both the owner and contractor will be held vicariously liable for the worker’s injury, without regard to their fault and even in the absence of control or supervision of the worksite. The Court of Appeals of New York recently addressed the broad scope of the Labor Law in the context of slipping hazards.
In Bazdaric v. Almah Partners, LLC, 41 N.Y.3d 310 (2024), the plaintiff, an injured painter, slipped and fell on a plastic covering placed over an escalator in an area he was assigned to paint. The plaintiff claimed that the plastic covering was a foreign substance for purposes of Industrial Code 12 NYCRR 23-1.7(d) because it was not part of the escalator. Industrial Code 12 NYCRR 23-1.7(d) states:
Slipping hazards. Employers shall not suffer or permit any employee to use a floor, passageway, walkway, scaffold, platform or other elevated working surface which is in a slippery condition. Ice, snow, water, grease and any other foreign substance which may cause slippery footing shall be removed, sanded or covered to provide safe footing.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Wilson, Robinson & Cole LLPMr. Wilson may be contacted at
wwilson@rc.com