Owner Can’t Pursue Statutory Show Cause Complaint to Cancel Lien… Fair Outcome?
June 10, 2024 —
David Adelstein - Florida Construction Legal UpdatesIf there is a payment dispute with a construction
lienor — could be a contractor, a subcontractor, or supplier – it is possible, and more than likely, a construction lien may get recorded against real property. This scenario is not uncommon as the lien is the mechanism for the lienor to collateralize their claimed nonpayment. Now, in reality, it does not take much money to record a lien. A lienor should utilize a lawyer to prepare their liens, but maybe they prepare liens in-house. Regardless, the recording of the lien is a nominal cost and the clerk that dockets and records the lien does NOT analyze the merits of the lien. That is not what the clerk is there to do; nor do you really want them the delve into the factual merits.
Well, what if a lien is facially invalid, meaning that the lien, on its face, includes information that demonstrates it is NOT properly perfected. Or what if the lienor failed to properly preserve or perfect its lien rights before recording the lien. This happens! Naturally, an owner of the real property wants the lien removed from the property. The owner does not want the encumbrance.
The owner could transfer the lien to a lien transfer bond under Florida’s Lien Law, but that is easier said than done. And this does not discharge the lien; it just removes the lien from the property to the security of the bond.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Newmeyer Dillion Attorneys Named to 2022 Southern California Rising Stars List
June 13, 2022 —
Newmeyer DillionNEWPORT BEACH, Calif. – June 8, 2022 – Prominent business and real estate law firm Newmeyer Dillion is pleased to announce that partner
Jason Moberly Caruso and associate
Jessica Garland Daley have been selected to the 2022 Southern California Rising Stars list by Super Lawyers. Each year, no more than 2.5 percent of the lawyers in the state are selected to receive this honor. The attorneys will be recognized in the June 2022 issues of Super Lawyers Magazine, Los Angeles Magazine and Orange Coast Magazine.
Jason Moberly Caruso is a partner in the Newport Beach office. Jason's practice focuses on land use, "contaminated sites" environmental legal work, complex litigation, and appellate matters. This is the fifth consecutive year Jason has been honored.
Jessica Garland Daley is an associate in the Newport Beach office. Jessica's practice focuses on litigation in the areas of employment law and construction law. This is the first year Jessica has been selected.
About Newmeyer Dillion
For over 35 years, Newmeyer Dillion has delivered creative and outstanding legal solutions and trial results that achieve client objectives in diverse industries. With over 60 attorneys working as a cohesive team to represent clients in all aspects of business, employment, real estate, environmental/land use, privacy & data security and insurance law, Newmeyer Dillion delivers holistic and integrated legal services tailored to propel each client's operations, growth, and profits. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California and Nevada, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949.854.7000 or visit www.newmeyerdillion.com.
Read the court decisionRead the full story...Reprinted courtesy of
Assessing Defective Design Liability on Federal Design-Build Projects
March 22, 2021 —
Dirk Haire, Adam Hamilton & Dana Molinari - ConsensusDocsA common misconception by many government officials is that a design-builder is always responsible for every design error or omission on a design-build project. This article examines the actual liability standard applied by the courts and boards of contract appeals when a design defect arises on a federal design-build project.
Background: Design-Build Contracts and the Spearin Doctrine
Design-build contracts combine the design and construction elements of a construction project into one contract. Design-build contracts often include two types of specifications: design and performance. Design specifications may set forth various parameters, such as precise measurements, tolerances, and materials. In doing so, the specifications create a fixed “roadmap” governing a contractor’s performance of the project. Performance specifications, on the other hand, set forth “operational characteristics” to achieve a particular objective or standard, but generally leave the details to the contractor.
Reprinted courtesy of
Dirk Haire, Fox Rothschild LLP,
Adam Hamilton, Fox Rothschild LLP and
Dana Molinari, Fox Rothschild LLP
Mr. Haire may be contacted at dhaire@foxrothschild.com
Mr. Hamilton may be contacted at ahamilton@foxrothschild.com
Ms. Molinari may be contacted at dmolinari@foxrothschild.com
Read the court decisionRead the full story...Reprinted courtesy of
Reservation of Rights Letter Merely Citing Policy Provisions Inadequate
February 14, 2023 —
Tred R. Eyerly - Insurance Law HawaiiIn an unpublished opinion, the Fourth Circuit affirmed the district court's finding that the insurers' reservation of rights letters did not provide a basis for denial of coverage. Stoneiedge At Lake Keowee Owners Ass'n Inc. v. Cincinnati Ins. Co., 2022 US. App. LEXIS 34292 (4th Dist. Dec. 13, 2022).
The Stoneledge AOAO sued the general contractor Marlick Home Builders, LLC and other defendants after construction of 37 units. The complaint alleged construction defects that resulted in water intrusion and other physical damage. Marlick notified its insurers, Cincinnati Insurance Company and Builders Mutual. Various reservation of rights letter were sent by the insurers.
In the underlying case, a judgment was entered against Marlick totalling approximately $1.6 million. As a judgment creditor of Marlickm, Stoneledge sued Cincinnati and Builders Mutual. The district court granted Stonelege's motion for summary judgment, primarily on the ground that the insurers failed to reserve the right to contest coverage.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Los Angeles Could Be Devastated by the Next Big Earthquake
October 15, 2013 —
CDJ STAFFA group of scientists have made a list of about 1,500 concrete buildings in Los Angeles which could potentially collapse in an earthquake. They have offered to make the list available to Los Angeles officials, although the city has yet to take them up on the offer. In response, a group of Times reporters combed through records to identify which buildings were of the sort most likely to collapse in an earthquake. The group found more than 1,000 concrete buildings built before 1976 when Los Angeles increased the requirements for steel rebar.
Experts estimate that in a major earthquake, five percent of these buildings could collapse, which for Los Angeles would mean about 50 buildings. Many of these buildings could be seismically retrofitted, but the article notes that a retrofit starts with a $100,000 structural study. Carol Schatz of the Central City Association notes that the cost of retrofitting “would be greater than the value of the building.”
Read the court decisionRead the full story...Reprinted courtesy of
Water Drainage Case Lacks Standing
March 28, 2012 —
CDJ STAFFThe Texas Court of Appeals has ruled in the case La Tierra de Simmons Familia Ltd. V. Main Event Entertainment, LP. The trial court had found for Main Event. On appeal, the court threw out some of the grounds on which the trial court had reached its decision.
The case involved two commercial lots in northwest Austin, Texas. The uphill tract (Phase III of the Anderson Arbor development) diverts its runoff onto the lower tract (the “Ballard tract”). The owners of the Ballard tract claim that “the drainage system was designed or constructed in a manner that has damaged and continues to damage the Ballard tract.”
Both tracts have undergone changes of ownership since the construction of the drainage system in 2004. At the time the drainage system was constructed, the parcel was owned by Sears Roebuck and Co. Sears later sold the property. Main Event Entertainment is the current tenant. Likewise, the Ballard tract was previously owned by the Ballard Estate which sold the property to La Tierra on an “as is” basis in 2007.
After La Tierra bought the Ballard tract, La Tierra’s engineer “witnessed and videotaped what he described as ‘flooding’ on the Ballard tract caused by storm water discharge from the Anderson Arbor drainage system during a rainfall event.” La Tierra determined that an adequate drainage system would cost about $204,000. Development plans were put on hold.
La Tierra sued Main Event and various other parties associated with the uphill tract, seeking “actual damages for (1) decrease and loss in rental income due to delay in obtaining the development permit, (2) interest on carrying costs during that time period, (3) the cost to build a water conveyance system on the Ballard tract, (4) engineering fees incurred to redesign the water conveyance system, (5) unspecified out-of-pocket real estate expenses, and (6) property devaluation occasioned by the need to construct an expensive water conveyance system.” The trial court never reached these claims, ruling instead that La Tierra lacked standing, that its claims were barred under the statute of limitations, and that there was no evidence of damage.
La Tierra appealed, arguing that “(1) the summary-judgment evidence does not conclusively establish that property damage claims accrued or were discovered prior to September 11, 2007, which is within the limitations period and was after La Tierra purchased the property; (2) even if the property was damaged before La Tierra acquired ownership of the Ballard tract, standing exists based on the assignments of interest from the Ballard Estate heirs, and the discovery rule tolls limitations until the injury was discovered on September 11, 2007; (3) limitations does not bar La Tierra's request for injunctive relief; (4) La Tierra's water code claim against Main Event and M.E.E.P. is viable based on their control over the drainage system, which makes them necessary and indispensable parties for injunctive relief; (5) La Tierra presented more than a scintilla of evidence to raise a fact issue on damages, causation, and other essential elements of its causes of action; and (6) the trial court abused its discretion when it sustained the defendants' objections to La Tierra's summary-judgment evidence.”
The appeals court concluded that La Tierra’s second claim was irrelevant to standing, as La Tierra “obtained assignments from the Ballard Estate heirs ? nearly one year after the lawsuit was initially filed.” Nor did the court accept their first point. The water system had been operating unaltered since January, 2004, with monthly maintenance and inspection to maintain its designed operation. Further, a feasibility report La Tierra received stated that “over sixteen acres drain into those ponds, and thus onto this site.” The court noted that “the underlying facts giving rise to a cause of action were known before La Tierra acquired ownership of the Ballard tract.”
The court concluded that the drainage issue is a permanent injury, but that it “accrued before La Tierra acquired an ownership interest in the property.” As La Tierra has standing, the appeals court ruled that it was improper for the trial court to rule on the issues. The appeals court dismissed the questions of whether the case was barred under the statute of limitation and also the question of whether or not La Tierra had damages.
As the issue of standing would not allow La Tierra to bring the suit, the appeals court found for the defendants, dismissing the case for this single reason, and otherwise affirming the ruling of the lower court.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
White and Williams Recognizes Women’s History Month: Remembering Virginia Barton Wallace
April 08, 2024 —
White and Williams LLPMarch is Women’s History Month – a month dedicated to the accomplishments and history of women in the United States. The theme for
International Women’s Day, which is this Thursday March 7, is “Inspire Inclusion.” White and Williams LLP is dedicated to understanding, valuing and inspiring inclusion in the field of law
White and Williams is proud of the women who have become leaders in the firm’s history, starting with Virginia “Ginny” Barton Wallace, an extraordinarily accomplished pioneer among female attorneys. She joined the firm immediately after graduating from University of Pennsylvania School of Law in 1950, and in 1961, Ginny became the first woman to become the first female partner not only at White and Williams but also at any law firm in Philadelphia.
Read the court decisionRead the full story...Reprinted courtesy of
White and Williams LLP
Chutes and Ladders...and Contracts.
November 25, 2024 —
Daniel Lund III - LexologyA contractor which designed and constructed a hydroelectric plant in Guatemala sued under the Federal Arbitration Act in federal court in Florida to overturn a project-related arbitration decision, “on the basis that the Tribunal had exceeded its powers.” That petition was denied based upon Eleventh Circuit precedent which foreclosed that challenge under the FAA for an arbitration conducted “under the Convention on the Recognition and Enforcement of Foreign Arbitral Awards,” a.k.a., the “New York Convention.”
The U. S. 11th Circuit initially affirmed the lower court decision, but then upon an en banc rehearing reversed: holding that in a New York Convention case where the arbitration seat is in the U. S., or where United States law governs the arbitration conduct, “Chapter 1 of the FAA provides the grounds for vacatur of the arbitral award. … § 208 of the FAA provides that ‘Chapter 1 applies to actions and proceedings brought under [Chapter 2] to the extent that chapter is not in conflict with [Chapter 2] or the [New York] Convention as ratified by the United States.’ …Chapter 1 of the FAA… thus acts as a gapfiller and provides the vacatur grounds for an international arbitration award otherwise governed by Chapter 2.”
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com