Tennessee Court: Window Openings Too Small, Judgment Too Large
November 18, 2011 —
CDJ STAFFThe Tennessee Court of Appeals has issued a ruling in the case of Dayton v. Ackerman, upholding the decision of the lower court, even as they found that the award was incorrectly computed. The Daytons purchased a house that had been designed and built by the Ackermans, who operated a construction business. The court noted that the warranty with the house promised that “for a period of 60 days, the following items will be free of defects in materials or workmanship: doors (including hardware); windows; electric switches; receptacles; and fixtures; caulking around exterior openings; pluming fixtures; and cabinet work.”
Soon, the Daytons began to experience problems with the house. Many were addressed by the Ackermans, but the Daytons continued to have problems with the windows. Neither side could specify a firm date when the Ackermans were contacted by the Daytons about the window problems. The Ackermans maintained that more than two years passed before the Daytons complained about the windows. The lower court found the Daytons more credible in this.
Initially, the Daytons included the window manufacturer in their suit, but after preliminary investigations, the Daytons dropped Martin Doors from their suit. Martin Doors concluded that the windows were improperly installed, many of them “jammed into openings that were too small for them.”
After the Daytons dismissed Martin Doors, the Ackermans sought to file a third party complaint against them. This was denied by the court, as too much time had elapsed. The Ackermans also noted that not all of the window installations were defective, however, the courts found that the Daytons ought not to have mismatched windows.
Unfortunately for the Daytons, the window repair was done incorrectly and the windows were now too small for the openings. The firm that did the repair discounted the windows and Daytons concealed the problem with plantation shutters, totalling $400 less than the original lowest estimate. However, the appeals court noted that it was here that the trial court made their computation error. Correcting this, the appeals court assessed the Ackermans $12,016.20 instead of $13,016.20.
Finally, the Ackerman’s expert was excluded as he had changed his testimony between deposition and trial. The trial reviewed the expert’s testimony and had it been admissible, it would not have changed the ruling.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Construction Litigation Roundup: “A Less Than Valiant Effort”
June 21, 2024 —
Daniel Lund III - LexologyA Miller Act claimant in federal court in New Jersey in relation to a VA medical center project found itself on the wrong end of the law and was sent packing by the court.
The claimant had supplied products for the project to general contractor Valiant Group, LLC, pursuant to a purchase order from the GC. The general contractor allegedly refused to pay the supplier, leading to the claim against the GC and its payment bond surety in the amount of $126,900. The supplier also sought recovery under the federal Prompt Payment Act, 31 U.S.C. §§ 3901-07. State law claims were asserted as well.
Chipping away at the federal law claims – the claims forming the asserted basis for federal court jurisdiction for the case – the court first dispensed with the Prompt Payment Act claim. According to the court, allegations that the general contractor had “wrongfully and improperly withheld remuneration… despite [having] ‘received payment from the U.S. Department of Veterans Affairs’" – whether or not accurate – did not trigger the Act. The court wrote:
“The Prompt Payment Act was enacted ‘to provide the federal government with an incentive to pay government contractors on time by requiring agencies to pay penalties . . . on certain overdue bills . . . [and] was later amended to include provisions applicable to subcontractors.’… Absent from the Act, however, are ‘any explicit provisions for subcontractor enforcement if the prime contractor fails to make timely payment.’… This is because the Act ‘merely requires that the prime contractor's contract with the subcontractor include the specified payment clause. [It] does not require the prime contractor to actually make payments to the subcontractor[.]’… The Act, therefore, does not ‘give subcontractors an additional cause of action for an alleged breach by a general contractor of a subcontract.’”
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Illinois Supreme Court Announces Time Standards for Closing Out Cases
April 11, 2022 —
Zachary Shelton - Lewis Brisbois(April 4, 2022) - Beginning July 1, 2022, Illinois trial courts will begin imposing new time standards for closing out pending cases. This change follows the Illinois Supreme Court’s March 25, 2022 announcement setting new time standards for case closure in trial courts. This announcement will apply to all cases filed in the State of Illinois on or after January 1, 2022.
According to the recent announcement, the purpose of the new Time Standards Order (the Order) is to assist Illinois circuit courts with “meeting their fundamental obligation to resolve disputes fully, fairly, and promptly” by establishing a uniform, statewide expectation for parties, attorneys, and judges regarding the status of cases that will require each court to evaluate its actual performance compared to a statewide expectation.
Read the court decisionRead the full story...Reprinted courtesy of
Zachary Shelton, Lewis BrisboisMr. Shelton may be contacted at
Zachary.Shelton@lewisbrisbois.com
In a Win for Design Professionals, California Court of Appeals Holds That Relation-Back Doctrine Does Not Apply to Certificate of Merit Law
December 20, 2017 —
Garret Murai - California Construction Law BlogThe year was 1995. The old guard was still in power in Sacramento. “Button-Down” Pete Wilson was Governor. Willie Brown, the self-nicknamed “Ayatollah of the Assembly,” was Speaker of the Assembly. And Bill “Huggy” Lockyer was Senate Pro Tem. Names that, for many reasons as of late, seem . . . well . . . let’s just say, “quaint.”
Their time, however, was coming to an end. Three years earlier, California voters approved Proposition 140, which instituted term limits for the first time in California. And by 1996, the first slate of legislators would be “termed out.” The immediate impact: It was the time for making deals because you didn’t know who would be keeping house next.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel, Rosen, Black, Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Don’t Sign a Contract that Doesn’t Address Covid-19 (Or Pandemics and Epidemics)
December 14, 2020 —
David Adelstein - Florida Construction Legal UpdatesDo yourself a favor: Don’t sign a construction contract that doesn’t address COVID-19 or any pandemic or epidemic from this point forward!
As the number of COVID-19 numbers rise, it would be reasonable to think this could have an impact on ongoing or future construction projects. For this reason, I want to revisit the subject of addressing COVID-19 (and any pandemic or epidemic) in your construction contract.
The potential impact caused by COVID-19 could result from governmental regulations that impact construction of the project, shutdowns due to affected workers, owners’ decisions to suspend performance or adjust the way the project is being constructed, increased deep cleaning requirements, and increased measures associated with social distancing and re-sequencing of shifts. This all plays into the timeliness of performance and the productivity of manpower and equipment usage. When submitting a price, a lot of these considerations may not be factored in because doing so could lead to a price that will never get accepted.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Wildfire Is Efficient Proximate Cause of Moisture Reaching Expansive Soils Under Residence
November 05, 2014 —
Tred R. Eyerly - Insurance Law HawaiiThe court considered whether a wildfire (covered risk) or moisture in the soils (excluded risk) was the cause of damage to the insureds' home. Encompass Ins. Co. v. Berger, 2014 U.S. Dist. LEXIS 142870 (C.D. Cal. Oct. 7, 2014).
In May 2009, the Jesusita Fire caused damage to the insureds' home and surrounding area. The west wall of the house was burned, causing damage to a bedroom. A shed, hot tub, wooden decks and some vegetation, including eucalyptus trees, were damaged.
The insureds submitted a claim to Encompass. Eventually, Encompass spent $400,000 repairing the property.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
State Audit Questions College Construction Spending in LA
August 17, 2011 —
CDJ STAFFA state audit of the Los Angeles Community College District found many problems with their construction spending. Their report, as described in the Los Angeles Times, found construction money spent for other purposes, such as promotional photography and public relation tours, $28.3 million spent on projects that were later cancelled, and oversight committees that provided no oversight.
Earlier this year, the LA Times ran a series of articles detailing problems with the Los Angles Community College District’s construction program. The LA Times reported that the State Controller’s audit reached many of the same conclusions.
The Community College District disputed the findings.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
How AI Can Become a Design Adviser
October 02, 2018 —
Aarni Heiskanen - AEC BusinessParametrized design software is not a recent invention. This software is based on predetermined, fixed algorithms, leaving most of the work to the designer. Sweco, a leading engineering consultancy, is now exploring how artificial intelligence (AI) could take design automation in the Architecture, Engineering, and Construction industry to the next level.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi