Rip Rapson - BloombergAmerican cities stand at a precipice. Burdened by an overwhelming public health crisis, drained of resources by economic stagnation and torn apart by racial injustice and unrest, cities are confronting the reality that conventional formulas of municipal finance and practices of working cannot sustain our urban places.
The significance of this moment was not lost on the Biden-Harris administration, which quickly advanced an ambitious mandate commensurate with the challenge: a domestic Marshall Plan called Build Back Better. Already, the first prong — the $1.9 trillion American Rescue Plan — has helped shore up city budgets, restore desperately needed funding for public transportation and keep businesses open and families in homes. The second leg, the $2 trillion American Jobs Plan, represents a bold shift from short-term recovery to long-term transformation.
Read the court decisionRead the full story...Reprinted courtesy of
Rip Rapson, Bloomberg
Construction Delays: Which Method Should Be Used to Calculate Delay?
July 25, 2021 —
David Adelstein - Florida Construction Legal UpdatesIf you need to prove and allocate construction project delays, you should engage a scheduling consultant qualified with CPM (critical path method) analysis. You should also engage counsel to assist in preserving your rights, as well as presenting and maximing your arguments for delay.
There are numerous methodologies used to quantify and allocate delay. You want to discuss the most effective analysis for your case and facts including whether you want/should use a forward-looking prospective analysis or a backward-looking retrospective analysis that factors in as-built data. In doing so, you want to make sure you understand the pros and cons of each methodology including the bases to attack the methodology that will be subject to cross-examination. The five primary CPM methodologies are as follows:
- As-Planned Versus As-Built. This methodology compares the as-planned baseline schedule to an as-built schedule reflecting progress to assign delay. An as-built schedule that reflects progress includes actual start dates, finish dates, and durations. The actual dates and durations are compared with the as-planned dates and durations on the baseline schedule to determine delay. Under this methodology, the delay impact is determined retrospectively.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Withholding Payment or Having Your Payment Withheld Due to Disputes on Other Projects: Know Your Rights to Offset
January 04, 2021 —
Christopher C. Broughton, Jones Walker LLP - ConsensusDocsIntroduction
The right to offset refers to the common sense ability to reduce or eliminate your payment obligations to a party who owes you money on another contract. With offsets, common law largely tracks common sense. The right of offset is recognized by statute and court decisions in many states as well as under federal law and the U.S. Bankruptcy Code. The right to offset can also be established in the contract or subcontract.
But like many things that may seem simple, the right to offset can easily become complex. This article provides an overview of the extent and limits of the right to offset varies from state to state and with federal government contracts about the extent and limits of the right of offset. Construction trust fund statutes add another layer of complications.
These variations may not be obvious or intuitive, but they have a tremendous impact on your right to get paid or your right to withhold payment. Because of the variations, you must always confirm the law applicable to your contract or subcontract, which may not be where the project or you are located.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher C. Broughton, Jones Walker LLPMr. Broughton may be contacted at
cbroughton@joneswalker.com
Seven Proactive Steps to Avoid Construction Delay Disputes
September 29, 2021 —
Michael Pink - Construction ExecutiveDelays, cost overruns and disputes have long been part of the commercial construction industry, making the work of reactive forensic analysis by consultants and attorneys a necessary component. Yet many internal practices and issues within construction companies strongly correlate with projects that result in legal disputes and financial losses. There are seven proactive steps that can help companies minimize losses and claims.
Prepare a Cost- and Resource-Loaded Critical Path Method Schedule
This is the first step any contractor can take to establish and document a manpower plan, a timeline and an intended flow for its work. Doing so is beneficial for two reasons: it will become the basis for measuring impacts and variances to both cost and schedule in a delay, dispute or claim setting; and it will serve as a great project management resource or tool. Without thinking through manpower, durations and workflow in great detail at the beginning of the project, contractors put themselves at risk of becoming delayed and blowing the budget.
Reprinted courtesy of
Michael Pink, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
The Sky is Falling! – Or is it? Impacting Lives through Addressing the Fear of Environmental Liabilities
March 30, 2016 —
John Van Vlear and Karl Foster – Newmeyer & Dillion, LLPSix months ago, a couple anxiously relayed to N&D lawyers how the sky was falling – with environmental liabilities at the center of their seemingly real Chicken Little fears. The couple owned two properties in a central California town, one being a former gas station which an oil company had abandoned alleging the lease was void given partial eminent domain actions. Before interviewing us, the couple had spent in excess of $100,000 in legal fees with another law firm trying to force the oil company to take responsibility for potential environmental impacts under the disputed lease.
Reprinted courtesy of
John Van Vlear, Newmeyer & Dillion, LLP and
Karl Foster, Newmeyer & Dillion, LLP
Mr. Van Vlear may be contacted at john.vanvlear@ndlf.com.
Mr. Foster may be contacted at karl.foster@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Federal Contractors Should Request Debriefings As A Matter Of Course
May 30, 2018 —
Scott MacDonald - Ahlers Cressman & Sleight BlogFederal Contractors—especially those engaging in FAR Part 15 direct contract negotiations—should make it a routine practice to timely request debriefings after the Contracting Agency excludes the bidder from the competitive range (“pre-award debriefing”) or after the Agency issues the award (“post-award debriefing”). Debriefings allow the Contractor to understand the evaluation process used by the Contracting Agency and to receive an assessment of how it fared in that evaluation. This is not a one-sided presentation as Contracting Agencies are required to answer the contractor’s relevant questions about the decision-making process. Properly run debriefings can be used to better tailor future bids and negotiations, as further marketing to the Contracting Agency for future awards, and, occasionally, to unearth grounds for a potential protest if any part of the evaluation process is out of sync with the FARs. In the event the contractor learns of a basis for protest at the debriefing, the deadline to file a protest begins running from the date of the debriefing—whether it was required or not.
Read the court decisionRead the full story...Reprinted courtesy of
Scott MacDonald, Ahlers Cressman & Sleight PLLCMr. MacDonald may be contacted at
scott.macdonald@acslawyers.com
“Other Insurance” and Indemnity Provisions Determine Which Insurer Must Cover
September 01, 2011 —
Tred R. Eyerly - Insurance Law HawaiiA policy’s “other insurance” clause and a contractual indemnity provision were at the root for determining which of two insurers had to cover for injuries at a construction site. Valley Forge Ins. Co. v. Zurich Am. Ins. Co., 2011 U.S.Dist. LEXIS 76061 (N.D. Calif. July 14, 2011).
Hathaway was the general contractor at a demolition and construction project. Hathaway was insured by Zurich. Reinhardt Roofing was the roofing subcontractor. Reinhardt was insured by Valley Forge under a policy which named Hathaway as an additional insured. The subcontract also required Reinhardt to indemnify Hathaway for acts or omissions arising from Reinhardt’s work unless Hathaway was solely negligent.
Four of Reinhardt’s workers were injured when a canopy roof on which they were working collapsed. At the time of the accident, Hathaway’s on-site supervisor was inspecting a gap in the canopy roof, but did not order Reinhardt’s workers to stop working.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
Don’t Let Construction Problems Become Construction Disputes (guest post)
October 01, 2014 —
Melissa Dewey Brumback – Construction Law in North CarolinaTo start our week off right, today we have another important article from guest blogger Christopher G. Hill, LEED AP. Chris is a Virginia Supreme Court certified mediator, construction lawyer and owner of the Richmond, VA firm, The Law Office of Christopher G. Hill, PC. He authors the Construction Law Musings blog where he discusses legal and policy issues relevant to construction professionals. His practice concentrates on mechanic’s liens, contract review and consulting, occupational safety issues (VOSH and OSHA), and risk management for construction professionals. [His blog was also one of the first construction law blogs I found and followed, even if he is a Duke alum!] Take it away, Chris!
First and foremost, thanks to Melissa for inviting me back to post here at her great blog. She continues to invite me back despite my being a Blue Devil (and I try not to hold her Tar Heel status against her).
So much of discussion relating to construction law and construction lawyers centers on the litigation of disputes. This discussion comes in many forms from avoidance of such litigation through the early intervention of good counsel prior to getting into a project to what sort of resolution mechanism to use. Another branch of this discussion is essentially the right way to pursue your claim (or as some may read it start the dispute ball rolling). Sometimes a payment bond claim is the best method while others a straight up contractual suit is the best way to go.
Of course, all of this discussion presumes that there will be disputes. While I agree to some degree that in the Murphy’s Law riddled world of commercial construction, problems will arise. These problems need not rise to the level of a dispute that requires outside (read court or arbitrator) intervention. A few tips that are easy to write, but admittedly hard to practice at times can hopefully keep problems from blossoming into disputes. I’ve listed three big ones here:
1.Use “in house counsel.” Yes, I know that most of you engineers, architects, commercial general contractors and subcontractors out there aren’t big enough to either want or need a full time attorney on the payroll. What I mean by this is that when problems occur (or preferably before doing so), give your friendly local construction lawyer a call. As I learned from my dad, an ounce of prevention and all that. That 10 minute phone call may help avoid many hours of time and bills from your attorney later down the road.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North CarolinaMs. Brumback may be contacted at
mbrumback@rl-law.com