Insurer's Appeal of Jury Verdict Rejected by Tenth Circuit
March 06, 2023 —
Tred R. Eyerly - Insurance Law HawaiiAfter a jury awarded damages related to the insurer's delayed payment under the claim and the insurer's post trial motions to set aside the verdict were denied, the Tenth Circuit affirmed. US General, LLC v. GuideOne Mut. Ins. Co., 2022 U.S. App. LEXIS 34066 (10th Cir. Dec. 12, 2022).
Crossroads American Baptist Church submitted a claim to GuideOne for hailstorm damage. Crossroads hired US General as the general contractor to perform the repairs and later assigned its interest in the insurance policy to US General.
Numerous disputes arose between Crossroads and GuideOne regarding the cost of the repairs. There were delayed payments and portions of the repairs were never paid for. The delayed payments meant GuideOne's ability to begin making the repairs was hindered because it was more expensive to start and stop a project.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Massachusetts Roofer Killed in Nine-story Fall
January 08, 2019 —
Johanna Knapschaefer - Engineering News-RecordA 41-year-old roofer from Haverhill, Mass. fell through a roof hole nine stories to his death on Dec. 18 while working on an apartment building project in Haverhill, a city north of Boston.
Read the court decisionRead the full story...Reprinted courtesy of
Johanna Knapschaefer, ENRENR may be contacted at
ENR.com@bnpmedia.com
Lien Claimant’s Right to Execute against Bond Upheld in Court of Appeals
February 10, 2012 —
Douglas Reiser, Builders Council BlogStonewood v. Infinity Homes is a simple construction dispute over a matter of about $9,000.00. But sometimes these tiny little disputes turn into expensive legal battles over mere procedural quivering. In Stonewood, a small subcontractor won a big victory yesterday when the Divison 1 Court of Appeals upheld its judgment against a lien release bond posted by an owner.
Infinity Homes contracted with Stonewood Design to lay tile in one of its customer’s homes. Stonewood did the work, but Infinity withheld roughly $9,000.00 of the contract sums for what it alleged were trade damages left on the tile. The two parties were unable to come to an agreement over payment and Stonewood proceeded with a lien under RCW 60.04. It then filed an action to enforce the lien against the homeowner, Infinity and its bonding company.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of
Skipping Depositions does not Constitute Failure to Cooperate in New York
March 09, 2020 —
Ryan G. Nelson - Saxe Doernberger & VitaInsurance policies typically impose, on the insured, a duty to cooperate with the insurer during investigation and litigation of a claim. Non-cooperation can be grounds for denying coverage. This begs the question: what constitutes non-cooperation?
Recently, a New York appellate court affirmed a trial court’s decision that failure by an employee of the insured to show up for three court-ordered depositions did not rise to the level of “willful and avowed obstruction” and therefore, the insurer could not deny coverage on the basis of non-cooperation. See Foddrell v. Utica First Insurance Co., 178 A.D.3d 901 (N.Y. App. Div. 2019). In so holding, the Foddrell court applied the Thrasher test: “To effectively deny coverage based upon lack of cooperation, an insurance carrier must demonstrate (1) that it acted diligently in seeking to bring about the insured’s cooperation, (2) that the efforts employed by the insured were reasonably calculated to obtain the insured’s cooperation, and (3) that the attitude of the insured, after his or her cooperation was sought, was one of willful and avowed obstruction.” Id.; see Thrasher v. U. S. Liab. Ins. Co., 19 N.Y.2d 159, 167 (1967).
Thomas Foddrell’s suit against Utica First Insurance Company (“Utica First”) stemmed from his personal injury suit against Janey & Rana Construction Corporation (“J&R” (Utica First’s insured). During that lawsuit, J&R’s principal, Gardeep Singh, failed to appear for two court-ordered depositions. After his failure to appear at those depositions, Utica First sent an investigator to inform Singh that he was scheduled for a third deposition. Singh responded to the investigator that he would speak with J&R’s attorneys about the matter. Ultimately, Singh did not appear for the third court-ordered deposition. In response to Singh’s repeated failure to appear for the depositions, Utica First sent Singh a letter advising him that because of his lack of cooperation, Utica would no longer agree to indemnify J&R.
Read the court decisionRead the full story...Reprinted courtesy of
Ryan G. Nelson, Saxe Doernberger & VitaMr. Nelson may be contacted at
rgn@sdvlaw.com
Arizona Court Determines Statute of Limitations Applicable to a Claim for Reformation of a Deed of Trust (and a Related Claim for Declaratory Judgment)
October 16, 2018 —
Kevin J. Parker - Snell & Wilmer Real Estate Litigation BlogIn a recent Arizona Court of Appeals case, Deutsche Bank National Trust Co. v. Pheasant Grove LLC, 798 Ariz. Adv. Rep. 15 (August 23, 2018), the Court of Appeals addressed the question of what statute of limitations was applicable to a declaratory judgment claim. In that case, a bank’s deed of trust inadvertently omitted one of the lots that was supposed to secure that bank’s loan. The deed of trust should have covered lots 8 and 9, but by its terms covered only lot 8. A different bank subsequently recorded a deed of trust that encumbered lot 9. In connection with the second bank’s foreclosure of its deed of trust, the first bank sought reformation and a declaratory judgment with regard to its deed of trust, seeking to have that deed of trust cover both lots 8 and 9, as intended. The trial court determined that the first bank’s reformation claim was filed too late, and also determined that the declaratory judgment claim was filed too late, beyond the applicable statute of limitations.
Read the court decisionRead the full story...Reprinted courtesy of
Kevin J. Parker, Snell & WilmerMr. Parker may be contacted at
kparker@swlaw.com
Building a Case: Document Management for Construction Litigation
October 07, 2019 —
Robert A. Gallagher, Jane Fox Lehman, & Michael I. Frankel, Pepper Hamilton LLP - ConsensusDocsSuccess in construction litigation often turns less on counsel’s ability to craft legal arguments and more on counsel’s ability to gather, master and present the often complex set of facts underlying the case. In construction matters, most of the key facts are found in documents: contract documents, drawings, plans and specifications, schedules, submittals, progress reports, daily logs, change orders, invoices and payment records. Nowadays, these documents will almost certainly be created, exchanged and stored electronically; many will never exist in hard copy. As such, timely collection, organization and analysis of electronically stored information (ESI) is crucially important in construction litigation.
The construction industry has always involved a large quantity of records. Today, the majority of those records exist only as ESI: Design professionals use computer-aided design (CAD) software to create construction plans. Construction managers use Primavera or similar software to create schedules and workflows. Estimators use job cost control programs. Innovative firms capture digital photos of the project, from mobilization through the punch process.
Because ESI is created and exchanged at a higher rate than hard-copy documents, ESI has facilitated a dramatic increase in the volume of records associated with construction projects. Further compounding the increase is the proliferation of mobile devices. With a smartphone in every pocket, ESI creation has moved out of the home office and the site trailer and onto the site itself. As the volume of ESI expands, so too does the time and expense associated with storing, processing, reviewing and producing these records. This article will cover strategies for balancing time and expense with the requirements of the rules and the needs of the case.
Reprinted courtesy of Pepper Hamilton LLP attorneys
Robert A. Gallagher,
Jane Fox Lehman and
Michael I. Frankel
Mr. Gallagher may be contacted at gallagherr@pepperlaw.com
Ms. Lehman may be contacted at lehmanj@pepperlaw.com
Mr. Frankel may be contacted at frankelm@pepperlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Big League Dreams a Nightmare for Town
April 03, 2013 —
CDJ STAFFThe town of Gilbert, Arizona had their own big dreams for Big League Dreams Gilbert, which the town was convinced would bring in financial benefits. Now the amateur sports complex is plagued by defects and failing infrastructure. The town was wondering how to create sufficient recreation facilities when Big League Dreams made a proposal that would bring tax revenue from a new stadium complex.
Ten years later, Gilbert says it’s not getting enough of the revenue from the parks. The proposal, created by Big League Dreams, estimated an economic benefit of $40 million over 30 years with a construction cost of $22.7 million. Instead, construction ran to $42.7 million and over the last two years the town has received only $250,570.
Then there are the construction defects. The structure was warranteed for only one year. That warrantee long over, the complex has problems with various concrete surfaces and has generated injury claims. The town did not inspect the park after Big League Dreams started operating it. They later found out that some parts did not conform to code, with 39 problem areas referenced in a report. Some of these included safety issues like missing handrails.
Read the court decisionRead the full story...Reprinted courtesy of
Want to Use Drones in Your Construction Project? FAA Has Just Made It Easier.
March 01, 2017 —
Masaki J. Yamada – Ahlers & Cressman PLLCThe new Part 107 FAA Rules took effect on Monday, August 29, 2016. Unlike the previous requirements for flying a drone commercially, the new rules are much more simplistic and permissive of a broad amount of commercial drone usage.
The following is the basic knowledge you need to legally use a drone on your future projects. To fly a drone commercially, there are now four major requirements:
- You must be at least sixteen years old;
- You must register your drone online;
- You must pass an aviation knowledge test administered at an FAA-approved testing center; and
- You must pass review by the Transportation Security Administration.
Read the court decisionRead the full story...Reprinted courtesy of
Masaki J. Yamada, Ahlers & Cressman PLLCMr. Yamada may be contacted at
myamada@ac-lawyers.com