The United States Court of Appeals, Fourth Circuit, Finds Wrap-Up Exclusion Does Not Bar Coverage of Additional Insureds
February 18, 2020 —
Callie E. Waers - Florida Construction Law NewsThe United States Court of Appeals, Fourth Circuit, recently took a close look at the application of a “controlled insurance program exclusion” (wrap-up exclusion) to additional insureds on a commercial general liability policy. In Cont’l Cas. Co. v. Amerisure Ins. Co., 886 F.3d 366 (4th Cir. 2018), the Fourth Circuit examined the interplay of an enrolled party’s additional insured status on an unenrolled party’s commercial general liability (“CGL”) policy with a wrap-up exclusion. The court applied North Carolina law and found that pursuant to the policy’s own language, the exclusion only applied to the original named insured, not the additional insureds.
The case arose out of an injury incurred by an employee of a second-tier subcontractor during the construction of a hospital. On this particular project, the owner maintained a “rolling owner controlled insurance program” (wrap-up insurance program) in which all tiers of contractors were required to enroll, but enrollment was not automatic. The general contractor was enrolled in the owner’s wrap-up policy, but neither the steel manufacturer subcontractor nor its sub-subcontractor, the steel installation company, were enrolled. The underlying plaintiff was injured while he was an employee of the steel installation company, but he did not name his employer in his personal injury lawsuit.
The Cont’l Cas. Co. case was instituted by Continental Casualty Company (“Continental”) after it defended and settled the underlying plaintiff’s claims against its insured and additional insured, the steel manufacturer and general contractor, respectively. Continental sought to be reimbursed for the $1.7 million settlement and attorneys’ fees and costs incurred for the defense and indemnity of the underlying lawsuit.
Continental alleged that Amerisure Insurance Company (“Amerisure”) breached its duty to defend and Amerisure’s policy provided the primary coverage for both the general contractor and steel manufacturer, who were additional insureds on the Amerisure policy. Amerisure denied a duty to defend the additional insureds based on the presence of the wrap-up exclusion.
Read the court decisionRead the full story...Reprinted courtesy of
Ryan M. Charlson, Cole, Scott & Kissane, P.A.Mr. Charlson may be contacted at
Ryan.Charlson@csklegal.com
Who Is To Blame For Defective — And Still LEED Certified — Courthouse Square?
September 01, 2011 —
Douglas Reiser, Builders Council BlogRemember Courthouse Square? I sure do. We have talked about the closed and evacuated LEED certified building a couple of times here on Builders Counsel. Well, it’s back in the news. This time building professionals are pointing fingers — but there is some talk about a fix. Still, its LEED certification remains.
If you read my past articles about Courthouse Square, you can get caught up on this mess. The short of it is that Salem, Oregon had the five-story government building and bus mall completed in 2000 for $34 Million. It was awarded LEED certification during the USGBC’s infancy. Last year, it became public that the building had significantly defective concrete and design. The Salem-Keizer Transit District worked with the City of Salem to shut the building down, and it has not been occupied since.
Last fall, Courthouse Square failed thorough forensic testing leading to a lengthy bout with a number of insurers. The contractors and designers had been hauled into court, but the Transit District was able to settle with the architect and contractors. The only remaining party involved in the lawsuit appears to be the engineering firm, Century West Engineering. Most expert reports have pinned the responsibility for the poor design and materials on Century West’s shoulders.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of
Broker Not Negligent When Insured Rejects Additional Coverage
January 31, 2018 —
Tred R. Eyerly – Insurance Law HawaiiThe broker was not negligent when it proposed additional coverage that was rejected by the insured. Cromer v. Rosenzweig Ins. Agency Inc., 2017 N.Y. App Div. LEXIS 8969 (N.Y. App. Div. Dec. 21, 2017).
Plaintiff was injured while employed as a painter at property owned by Allen Skriloff. Coverage was denied because injuries to employees, contractors and employees of contractors were excluded. Plaintiff sued Skriloff and obtained a jury verdict of $6.1 million. Skirloff assigned to plaintiff all rights and claims held against the insurer and insurance brokers.
Read the court decisionRead the full story...Reprinted courtesy of
Tred Eyerly, Insurance Law Hawaii
Emotional Distress Damages Not Distinct from “Annoyance and Discomfort” Damages in Case Arising from 2007 California Wildfires
November 21, 2017 —
Kirsten Lee Price & Lawrence S. Zucker II - Haight Brown & Bonesteel LLPOriginally published by CDJ on February 16, 2017
In Hensley v. San Diego Gas & Elec. Co., (No. D070259, filed 1/31/17), the California Court of Appeal for the Fourth Appellate District held that emotional distress damages are available on claims for trespass and nuisance as part of “annoyance and discomfort” damages.
In Hensley, plaintiffs sustained fire damage to their home and property during the 2007 California wildfires. The Hensleys were forced to evacuate as the fires advanced. Although their home was not completely destroyed, it sustained significant damage and they were not able to return home permanently for nearly two months. Thereafter, the Hensleys filed suit against San Diego Gas and Electric Company (“SDG&E”) asserting causes of action for trespass and nuisance, among others. Mr. Hensley, who had suffered from Crohn’s disease since 1991, further claimed that as a result of the stress from the fire, he experienced a substantial increase in his symptoms and his treating physician opined that “beyond a measure of reasonable medical certainty... the stress created by the 2007 San Diego fires caused an increase of [Mr. Hensley’s] disease activity, necessitating frequent visits, numerous therapies, and at least two surgeries since the incident.” SDGE moved, in limine, to exclude evidence of Mr. Hensley’s asserted emotional distress damages arguing he was not legally entitled to recover them under theories of trespass and nuisance. The trial court agreed and excluded all evidence of such damages.
Reprinted courtesy of
Kirsten Lee Price, Haight Brown & Bonesteel LLP and
Lawrence S. Zucker, Haight Brown & Bonesteel LLP
Ms. Price may be contacted at kprice@hbblaw.com
Mr. Zucker may be contacted at lzucker@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Endorsements Preclude Coverage for Alleged Faulty Workmanship
December 30, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe court found coverage for alleged faulty workmanship was barred by the Combination Construction Related Endorsement and Roofing Endorsement. Evanston Ins. Co. v. A&S Roofing, 2019 U.S. Dist. LEXIS 142828 (W.D. Okla. Aug. 22, 2019).
In 2010, A&S entered into a subcontract with the contractor to replace roofs on three buildings owned by Oklahoma Property Investors (OPI). Eagle was a subcontractor of A&S that installed the roofing. After the roofs were replaced, OPI filed suit against A&S, alleging that A&S provided 15-year warranties for the roofing work performed on the three buildings and that A&S breached each warranty by performing the work in a poor manner, resulting in failures to each of the roofs. OPI sought monetary relief including damages to its properties, of its tenants, and costs of repairs to its properties.
A&S's insurer, Evanston, denied coverage. Evanston pointed to the"legally obligated to pay" language of the CGL policy and argued coverage only extended to tort-based claims. Evanston argued the OPI lawsuit did not allege any tort claims, only warranty claims arising from contract. Second, Evanston contended the alleged "poor craftsmanship" giving rise to the claims in the OPI lawsuit that did not constitute an "occurrence" under the policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
A Loud Boom, But No Serious Injuries in World Trade Center Accident
March 01, 2012 —
CDJ STAFFThe Wall Street Journal reports that nearly twenty tons of steel fell forty stories at the World Trade Center site on February 16. One person was checked by medical personnel. One person who works in the Financial District said it was “almost like thunder.” Frank Pensabene, one of the ironworkers on the site said that after “loud boom,” “all hell broke loose.” The steel beams and cables fell onto a flatbed truck, which was not occupied at the time.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
California Supreme Court Finds Negligent Supervision Claim Alleges An Occurrence
July 21, 2018 —
Tred R. Eyerly - Insurance Law HawaiiAnswering a question posed by the Ninth Circuit, the California Supreme Court found that a suit against a employer for negligent hiring, retention and supervision of a employee who intentionally injures a third party alleges an occurrence under a CGL policy. Liberty Surplus Co. Corp. v. Ledesma & Meyer Construction Co., 2018 Cal. LEXIS 4063 (Cal. June 4, 2018)
Ledesma & Meyer Construction Company (L&M) contracted with the school district to manage a construction project at a middle school. L&M hired Darold Hecht as an assistant superintendent on the project. In 2010, Jane Doe, a 13-year-old student at the school, sued alleging that Hecht had sexually abused her. Doe’s claims included a cause of action against L&M for negligent hiring, retaining, and supervising Hecht.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
When Is a Project Delay Material and Actionable?
January 11, 2022 —
Rick Erickson - Snell & Wilmer Real Estate Litigation BlogWelcome to 2022! This year, the construction industry will undoubtedly reflect on the last two years as unprecedented times plagued by construction project delays. The COVID-19 pandemic contributed to suspension of work and closure of construction projects worldwide in 2020. The end of 2021 brought additional delays caused by an inexplicable clog in the supply chain of construction materials. The combined impact of these events on project milestones and completion deadlines led our clients to ask, with unusual and particular urgency, who is liable for such delays and how do contracting parties lessen the consequences from such unexpected and uncontrollable delays.
Granted that project delays are nothing new or unusual. They were common enough before inflation caused shipping complications and pandemic decimated the construction labor force. All delays, whatever the source, variably cause loss to all players on a construction project. But not all delays matter when it comes to claims and remedies available to the contracting parties in dispute resolution, where the determinative focus is on material delays impacting the entire project and on delays the claimant can credibly prove.
Most, if not all, jurisdictions interpret actionable delays from the contract documents for the project. The contract is definitely where you should start before pursuing any delay remedies. Delay remedies may be a time extension only, or a time extension plus your additional general conditions. Some delay remedies may be barred by the contract’s express terms and may be enforced adversely by the courts when such contract terms are indisputable. See Quinn Constr. v. Skanska USA Bldg., Inc., 730 F. Supp. 2d 401, 411 (D.C. Pa. 2010) (enforcing the subcontractor’s contractual waiver of claims for delay and disruption damages). On the other hand, delay damages that are expressly allowed by the contract—like overtime necessitated by the delays—are usually actionable and recoverable. Id. However, not only the contract terms, but applicable law, may affect the outcome.
Read the court decisionRead the full story...Reprinted courtesy of
Rick Erickson, Snell & WilmerMr. Erickson may be contacted at
rerickson@swlaw.com