Mitigate Construction Risk Through Use of Contingency
April 26, 2021 —
Laurie A. Stanziale - Construction ExecutiveMitigation of risk and costs in a construction project are always priorities for owners. In some contracts, in particular, Guaranteed Maximum Price contracts, some of those monetary risks are shifted to the contractor. Contingency is important because it allows for money to be in the budget for the unexpected and to keep the project moving, which benefits everyone.
WHAT IS CONTINGENCY?
Contingency is an amount of money built into the contractor’s price to complete the project to address unforeseen (although sometimes very common) costs that arise. This sum of money is generally referred to as the contractor’s contingency. The amount of the contingency is a balance struck between having money on hand to address the unexpected while also not unnecessarily tying up money that could otherwise be used for the project. Contingency is typically 5-10% of the hard costs. However, how the money is actually allocated during the project is not always well thought out, which can be the source of problems during the project.
The contractor’s contingency is not to be confused with an owner’s contingency (or reserve) which is outside of the contractor’s budget and generally used for owner driven changes to the project, such as changes to scope, design and schedule.
Reprinted courtesy of
Laurie A. Stanziale, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman Partner Stephen Straus Wins Spoliation Motion in Favor of Defendant
June 05, 2023 —
Stephen D. Straus - Traub LiebermanTraub Lieberman Partner Steve Straus represented a refrigeration installation and service company in a subrogation action filed by a property insurer after paying a claim related to extensive water damage at premises on Long Island, New York.
The premises owner purchased a refrigerator, which was sold without a hose to connect to the water source inside the premises. The defendant retailer retained Traub Lieberman’s client to install the refrigerator. Rather than complete the installation using a new water line, the installer used the existing line from the refrigerator that was being replaced. Approximately one week after installation, the owner’s son discovered water on the floor near the refrigerator, and significant water damage in the basement of the residence. The owner filed a claim with the insurer, which sent an investigator to the premises. The retailer also sent a technician to investigate and replace the water supply line. It was reportedly determined that the original line had failed, causing the water release. After the repair, the owner’s son took possession of the old water line, which he kept for a couple of years and then discarded. The insurer initiated a subrogation action against the retailer and the installation company, alleging that the water release was caused by the defendants’ failure to replace the water line when the new unit was installed. Plaintiff claimed that photographs of the old line established that it had been damaged or defective.
Read the court decisionRead the full story...Reprinted courtesy of
Stephen D. Straus, Traub LiebermanMr. Straus may be contacted at
sstraus@tlsslaw.com
Can Businesses Resolve Construction Disputes Outside of Court?
August 19, 2024 —
Scott L. Baker - Los Angeles Litigation BlogTime is of the essence in any construction project. So, if a dispute arises at any point, business owners generally wish to avoid the chance of a time-consuming case going to court.
Can California construction businesses
manage these disputes effectively outside of court? It is possible in some cases. Business owners should carefully consider these three steps.
1. Go Back to the Contract
Even if the contract is at the center of the dispute, it is important to refer to any details regarding dispute resolution included within the document. It is common for contracts to have some form of a dispute resolution clause. In such a case, both parties should follow the steps outlined in that agreement.
Read the court decisionRead the full story...Reprinted courtesy of
Scott L. Baker, Baker & AssociatesMr. Baker may be contacted at
slb@bakerslaw.com
“You’re Out of Here!” -- CERCLA (Superfund) Federal Preemption of State Environmental Claims in State Courts
October 20, 2016 —
Joshua J. Anderson & John E. Van Vlear – Newmeyer & Dillion LLPThe Comprehensive Environmental Response, Compensation, and Liability Act, 42
U.S.C § 9601 et seq. (“CERCLA”), commonly referred to as “Superfund,” is a federal statute
that provides funding and cost-recovery to address our nation’s worst hazardous-waste
sites. While CERCLA generally vests United States District Courts with exclusive original
jurisdiction over all related controversies, section 113(h) of the Act delays such jurisdiction
while the United States Environmental Protection Agency supervises or undertakes
environmental response action plans. What impact does this delayed federal jurisdiction
have on state law claims brought in state courts? Short answer: “You’re out of here!”
Litigants are precluded from bringing claims in state court that “challenge” environmental
response actions under CERCLA during the pendency of those actions.
Reprinted courtesy of
Joshua J. Anderson, Newmeyer & Dillion LLP and
John E. Van Vlear, Newmeyer & Dillion LLP
Mr. Anderson may be contacted at joshua.anderson@ndlf.com
Mr. Van Vlear may be contacted at john.vanvlear@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Was Jury Right in Negligent Construction Case?
September 30, 2011 —
CDJ STAFFYes, said the South Carolina Court of Appeals in Pope v. Heritage Communities, Inc. Heritage Communities developed Riverwalk, a community in South Carolina. During the earlier trial, HCI “conceded that construction defects existed at Riverwalk, and repairs needed to be made.” The trial court found that the construction was negligent, awarding the property owners association $4.25 million in actual damages and $250,000 in punitive damages, with the class of owners awarded $250,000 in actual damages and $750,000 in punitive damages. HCI appealed on nine issues. All were rejected by the appeals court.
The court rejected HCI’s claim that the judge’s instruction to the jury suggested to the jury that “the court had already determined that Appellants were willful, wanton, and reckless.” But here, the appeals court found “no reversible error.”
The general contractor for Riverwalk was BuildStar. Off-site management and sale were managed by Heritage Riverwalk, Inc., which also owned title to the property. Both these companies were owned by Heritage Communities, Inc. During the trial, an HCI employee testified that “the three corporations shared the same officers, directors, office, and telephone number.” The trial court found that the three entities were amalgamated. This was upheld by the appeals court.
Nor did the appeals agree with the HCI that the trial court had improperly certified a class. The owners were seen as properly constituting a class. Further, the court held that the property owners’ losses were properly included by the trial court. HCI objected at trial to the inclusion of evidence of subsequent remedial measures, however, as they did not object that it was inadmissible, the issue could not be addressed at appeal.
HCI argued on appeal that the trial court should not have allowed evidence of defects at other HCI developments. The appeals court noted that “the construction defects at the other HCI developments were substantially similar to those experienced by Riverwalk.”
The court additionally found that the negligence claims, the estimated damages (since full damage could not be determined until all defective wood was removed), and the award of punitive damages were all properly applied.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Michigan Supreme Court Concludes No Statute of Repose on Breach of Contract
July 19, 2011 —
CDJ STAFFJudge Marilyn Kelly of the Michigan Supreme Court has remanded the case of Miller-Davis Co. v. Ahrens Constr. Inc. (Mich., 2011) to the Court of Appeals, after determining that the court had improperly applied the statute of repose. She reversed their judgment, pending a new trial.
Ahrens Construction was a subcontractor, hired by Miller-Davis to build and install a natatorium room at a YMCA camp in Kalamazoo, Michigan. After its installation, the YMCA discovered a severe condensation problem, causing moisture to “rain” from the roof. The architect, testifying for Miller-Davis, alleged that the problems were due to improper installation by Ahrens. Ahrens claimed that the condensation problem was due to a design error.
When the roof was removed and reconstructed, the moisture problem ended. Ahrens argued that the alleged defects were caused by the removal. Further, in trial Ahrens raised the issue of the statute of repose. The court found in favor of Miller-Davis and did not address the statute of repose.
The Court of Appeals reversed the trial court, determining that the statute of repose had barred the suit. This rendered the other issues moot.
The Michigan Supreme concluded that the issue at hand was “a suit for breach of contract,” and that the Michigan statute of repose is limited to tort actions. They remanded the case to the Court of Appeals to address the issues that had been mooted by the application of the statute of repose.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
No Duty to Defend Construction Defect Claims
May 16, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe court determined the insurer had no duty to defend construction defect claims asserted against the insured. Pa. Nat'l Mut. Cas. Ins. Co. v. River City Roofing, 2022 U.S. Dist. LEXIS 38226 (E.D. Va. March 3, 2022).
Branch Builds, Inc, was the general contractor for Shock Valley View Genesis, LLC ("Genesis") in charge of constructing apartments. River City Roofing was a subcontractor for all roofing, aluminum and composition siding at the project. River City contracted and warranted its materials and work, agreed to indemnify Branch, and agreed to make Branch an additional insured under its CGL policy.
After completion of the project, Genesis reported defects in the construction. The roof, aluminum and composition siding allowed water intrusion and property damage to the apartments. Branch repaired and compensated Genesis for all damage done to the apartments. Branch then sued River City and another subcontractor and demanded judgment of $3,000,000.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
NYC Building Explosion Kills Two After Neighbor Reports Gas Leak
March 12, 2014 —
Michelle Kaske and Henry Goldman, BloombergFifteen minutes after a New York City resident reported the pervasive smell of gas in her East Harlem neighborhood, a massive explosion destroyed two buildings, killing two people and injuring at least 18. Utility workers arrived too late.
The explosion at 1644 and 1646 Park Ave., near 116th Street, reported about 9:30 a.m., was heard miles away and turned into a five-alarm fire. Windows were blown out as far as 10 blocks away, and cars across the street were wrecked. The blast sent debris onto adjacent elevated train tracks, halting commuter rail service in and out of Grand Central Terminal. Minor wounds were too numerous to count, said Frank Gribbon, a spokesman for the New York City Fire Department.
“This is a tragedy of the worst kind,” Mayor Bill de Blasio said during a news conference near the scene. He said residents are still missing from the buildings, which had a total of 15 units, and crews would search for them when the fire is extinguished.
Ms. Kaske may be contacted at mkaske@bloomberg.net; Mr. Goldman may be contacted at hgoldman@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Michelle Kaske and Henry Goldman, Bloomberg