Construction Defect Claim Must Be Defended Under Florida Law
February 15, 2018 —
Tred R. Eyerly – Insurance Law HawaiiThe Eleventh Circuit found that the insured caused property damage to areas beyond its own work, obligating the insurer to defend. Addison Ins. Co. v. 4000 Island Blvd. Condo. Ass'n, 2017 U.S. App. LEXIS 26870 (11th Cir. Dec. 28, 2017).
The condominium association contracted with Poma Construction Corp. to replace the building's aging concrete balcony railings with new aluminum and glass railings. Poma subcontracted with Windsor Metal Specialties, Inc. to paint the new railings. Work was completed on February 24, 2012. Poma issued a 10-year warranty covering its installation of the railings. Windsor issued a 20-year limited warranty covering the paint job.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Pennsylvania Supreme Court Adopts New Rule in Breach-of-the-Consent-to-Settle-Clause Cases
August 19, 2015 —
Sean Mahoney – White and Williams LLPIn Babcock & Wilcox Company, et al. v. America Nuclear Insurers, et al., the Pennsylvania Supreme Court recently held that where a liability insurer has agreed to provide a defense to its insured in an underlying tort action subject to a reservation of rights but refuses to consent to a settlement in that action, the insured may nevertheless accept the settlement over the insurer’s objection where the settlement is “fair, reasonable, and non-collusive” from the perspective of a reasonably prudent person in the insured’s position in light of the totality of the circumstances and is covered. Babcock & Wilcox Company v. America Nuclear Insurers, No. 2 WAP 2014, 2015 WL 4430352 (Pa. Jul. 21, 2015). This decision fills an important gap in Pennsylvania precedent addressing the rules applicable when an insurer refuses to consent to an insured’s settlement of a lawsuit.
In Babcock, the underlying plaintiffs sued Babcock & Wilcox Company and Atlantic Richfield Company (“the Insureds”) alleging that the Insured’s nuclear facilities caused bodily injury and property damage. The Insureds’ liability insurers agreed to defend the Insureds subject to a reservation of rights. The insurers later refused to consent to an offer to settle the underlying action for a total of $80 million because they believed the Insureds were likely to succeed on the merits. Nevertheless, in 2009, the Insureds accepted that offer and settled the underlying action for $80 million, notwithstanding the insurer’s refusal. The Insureds then sought reimbursement of the $80 million settlement from their insurers, who rejected that request on the ground that the Insureds had breached the consent-to-settlement/cooperation provisions of the implicated policies.
Read the court decisionRead the full story...Reprinted courtesy of
Sean Mahoney, White and Williams LLPMr. Mahoney may be contacted at
mahoneys@whiteandwilliams.com
David A. Frenznick Awarded Multiple Accolades in the 2020 Edition of The Best Lawyers in America
September 23, 2019 —
David A. Frenznick - Wilke FleuryWilke Fleury congratulates attorney David A. Frenznick on his inclusion in the 26th Edition of The Best Lawyers in America© for his work in: Litigation – Real Estate!
In addition, David was also acknowledged as a 2020 “Lawyer of the Year” award recipient. He received this accolade for his work in Litigation – Real Estate in Sacramento. Only a single lawyer in each practice area and community is honored with a “Lawyer of the Year” award.
Since it was first published in 1983, Best Lawyers® has become universally regarded as the definitive guide to legal excellence. Best Lawyers lists are compiled based on an exhaustive peer-review evaluation. Almost 94,000 industry leading lawyers are eligible to vote (from around the world), and have received over 11 million evaluations on the legal abilities of other lawyers based on their specific practice areas around the world. For the 2020 Edition of The Best Lawyers in America©, 8.3 million votes were analyzed, which resulted in more than 62,000 leading lawyers being included in the new edition. Lawyers are not required or allowed to pay a fee to be listed; therefore inclusion in Best Lawyers is considered a singular honor. Corporate Counsel magazine has called Best Lawyers “the most respected referral list of attorneys in practice.”
Read the court decisionRead the full story...Reprinted courtesy of
David A. Frenznick, Wilke FleuryMr. Frenznick may be contacted at
dfrenznick@wilkefleury.com
Court Bars Licensed Contractor From Seeking Compensation for Work Performed by Unlicensed Sub
June 06, 2022 —
Garret Murai - California Construction Law BlogIt all started with a tree.
A eucalyptus tree to be exact.
What followed is one of the more important cases to be decided under Business and Professions Code section 7031 in recent years. Yes, that Section 7031. The statute variously described by the state’s courts as “harsh[ ],” draconian” and “unjust,” but, importantly, nevertheless valid.
Under Section 7031, an unlicensed contractor is barred from seeking compensation for work requiring a contractor’s license. This has been called the “shield.” However, in addition to the “shield,” project owners can also employ Section 7031’s “sword,” and seek disgorgement of all monies paid to an unlicensed contractor. Section 7031’s “shield” and “sword” applies even if the project owner knew that the contractor was unlicensed. They also apply even if the unlicensed contractor’s work was flawless. And they also apply even if a contractor was unlicensed during a portion of its work. This is because, as courts have stated, Section 7031 is a consumer protection statute intended to protect the public from unlicensed contractors and applies irrespective of the equities.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Alabama Limits Duty to Defend for Construction Defects
October 10, 2013 —
CDJ STAFFWhile supreme courts in several states have expanded what is covered under a commercial general liability policy, Alabama has bucked the trend. Martha P. Brown and David L. Brown discuss this in a post on the site of their firm, Nelson Levine de Luca & Hamilton. They note that in a recent case, Owners Insurance Company v. Jim Carr Homebuilders, “the court held that liability for defective construction resulting in water intrusion damage to otherwise properly constructed component parts is not covered under a general contractor’s commercial general liability (CGL) policy because such damages are not caused by an ‘occurrence.’”
The background of Owners v. Jim Carr was that the work of the subcontractors was found not only to be defective, but responsible for damage to correctly performed work. The court held, however, that it was all part of the same project. The court “distinguished the present case from a situation where the insured’s work results in damages to other property outside the scope of the insured’s work,” which they noted could be covered under a CGL policy.
Read the court decisionRead the full story...Reprinted courtesy of
Application of Set-Off When a Defendant Settles in Multiparty Construction Dispute
January 05, 2017 —
David Adelstein – Florida Construction Legal UpdatesThe defense of set-off is an important defense in construction disputes, particularly multiparty disputes. For more information on this defense, please check out this
article as it explains the application of set-off in civil disputes in detail.
The issue of set-off will come up in a multiparty dispute when a plaintiff settles with one or more of the defendants. The remaining defendant(s) wants the benefit of that settlement to set-off and reduce any judgment against it. An example of this scenario can be found in Escadote I Corp. v. Ocean Three Limited Partnership, 42 Fla. L. Weekly D23a (Fla. 3d DCA 2016).
In this case, an owner of a condominium unit sued the condominium association, the developer, and the general contractor for water intrusion and mold infestation. The claim against the condominium association was the only claim that entitled the owner to attorney’s fees pursuant to its lawsuit (thus, attorney’s fees were isolated to only that claim against the association). During trial, the owner settled with the association. In entering a settlement, the owner smartly allocated the settlement amount such that $500 was allocated to its principal damages and $374,500 was allocated to its attorney’s fees. The owner then obtained a jury verdict against the contractor and developer for approximately $2M, jointly and severally, and the contractor and developer wanted the entire $375,000 settlement amount with the association to be set-off from the $2M verdict. The trial court set-off the entire $375,000 from the jury verdict when entering judgment. The appellate court reversed.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dma@katzbarron.com
The ALI Restatement – What Lies Ahead?
July 30, 2018 —
Adam M. Berardi & Sara C. Tilitz - Complex Insurance Coverage ReporterThe American Law Institute voted on May 22, 2018 to approve the final draft of its “Restatement of the Law of Liability Insurance.” This was the culmination of an eight-year project that evolved through 29 drafts resulting in a nearly 500-page final product. At least nine courts cited to the Restatement while it was still in draft form. On June 28, 2018, White and Williams LLP had the privilege of hosting a seminar about the Restatement, chaired by the Reporter for the Restatement, University of Pennsylvania Law Professor Tom Baker, and Randy Maniloff of White and Williams, author of “General Liability Insurance Coverage, Key Issues In Every State.” The seminar was geared toward assisting members of the liability insurance community in navigating the key provisions of the Restatement, including how they compare and contrast with existing case law and the role the Restatement may play in courts’ decision-making processes going forward.
Reprinted courtesy of
Adam M. Berardi , White and Williams, LLP and
Sara C. Tilitz, White and Williams, LLP
Mr. Berardi may be contacted at berardia@whiteandwilliams.com
Ms. Tilitz may be contacted at tilitzs@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
The Private Works: Preliminary Notice | Are You Using the Correct Form?
August 20, 2019 —
William L. Porter, Esq. - Porter Law GroupThe Private Works – Preliminary Notice form which contractors, subcontractors and suppliers had become accustomed to using for many years changed in 2004. Despite this change in law, many in the construction industry have still not started using the correct new form. Changes in the law, championed by the American Subcontractors’ Association, gave a significant new benefit to subcontractors and suppliers by giving the subcontractor or supplier some expectation of actually receiving notice of when a Notice of Completion or a Notice of Cessation has been recorded on many private works projects. The law also changed the language of the California Preliminary Notice that subcontractors and suppliers must use to protect their mechanics’ lien, bond claim and stop payment notice rights. If Owners do not send out the Notice of Completion as required by law they incur a diminishing of the protections afforded to them when they record a Notice of Completion or Notice of Cessation on many private works projects.
The revised law requires private project owners to notify all subcontractors and suppliers within 10 days after recording a Notice of Completion or Notice of Cessation that a Notice of Completion or a Notice of Cessation has actually been recorded. In order to receive such notice, the subcontractor or supplier must properly serve the new form of Preliminary Notice. If this properly occurs and the private project owner provides the required notice, then the subcontractor or supplier will have 30 days to record a Mechanics’ Lien. However, if an owner under such circumstances fails to properly notify a subcontractor or supplier within 10 days after recording a Notice of Completion or Notice of Cessation, then the Subcontractor or supplier will have 90 days to record a Mechanics’ Lien. The details of the law can be found in California Civil Code sections 8190, 8414 and 8416.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Esq., Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com