Commencing of the Statute of Repose for Construction Defects
November 08, 2021 —
David Adelstein - Florida Construction Legal UpdatesFlorida has a ten-year statute of repose which applies predominantly to construction defect claims. This can be found in Florida Statute s. 95.11(3)(c). After ten years, any rights relative to a construction defect claim are time-barred. However, the statute of repose date has been watered down and can be made to be more of a factual question due to the lack of objectivity as to the date that starts the ten-year repose clock. The watering down of the statute of repose date benefits parties asserting construction defect claims provided they strategically appreciate the question of fact that can be created when up against the statute of repose. Stated differently, when up against the clock to assert a construction defect claim, strategically develop those facts, evidence, and arguments to maximize creating a question of fact as to when the statute of repose clock commenced. Conversely, as a defendant sued for construction defects, you want to maximize the facts, evidence, and arguments to fully establish the date the statute of repose clock had to commence for purposes of a statute of repose defense.
The recent opinion in Spring Isle Community Association, Inc. v. Herme Enterprises, Inc., 46 Fla. L. Weekly D2306b (Fla. 5th DCA 2021) demonstrates the factual question associated with the clock that starts the statute of repose date. This factual question is created by Florida Statute s. 95.11(3)(c) that provides:
[T]he action [founded on the design, planning, or construction of an improvement to real property] must be commenced within 10 years after the date of actual possession by the owner, the date of the issuance of a certificate of occupancy, the date of abandonment of construction if not completed, or the date of completion or termination of the contract between the professional engineer, registered architect, or licensed contractor and his or her employer, whichever date is latest.
Spring Isle Community Association, supra. (Note, see also current s. 95.11(3)(c) version in effect per hyperlink above.)
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Around the State
March 27, 2019 —
Richard Glucksman & Chelsea Zwart – Construction Claims MagazineIn late 2018, Governor Jerry Brown signed two potentially impactful Senate bills relating to the construction of apartment buildings. These bills, discussed further below, were introduced, in part, in response to the Berkeley balcony collapse in June 2015, which was determined by the California Contractors State License Board to have been caused by the failure of severely rotted structural support joists—the repairs of which were deferred by the property manager despite indications of water damage.
In addition, 2018 saw the passage of California’s updated 2019 Building Energy Efficiency Standards. The new standards, which take effect in 2020, require, in part, the installation of solar systems on certain homes. The goal of the standards is to significantly decrease the energy usage in new homes while contributing to California’s greenhouse gas emissions reduction plans. Relatedly, new legislation, effective in 2019, aims to increase consumer protections for homeowners purchasing solar energy systems.
Reprinted courtesy of
Richard H. Glucksman, Chapman, Glucksman, Dean, Roeb & Barger and
Chelsea Zwart, Chapman, Glucksman, Dean, Roeb & Barger
Mr. Glucksman may be contacted at rglucksman@cgdrblaw.com
Ms. Zwart may be contacted at czwart@cgdrblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Las Vegas HOA Conspiracy & Fraud Case Delayed Again
September 17, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to the Las Vegas Review-Journal, “[T]he federal trial of former construction company boss Leon Benzer and five others in a massive scheme to take over Las Vegas-area homeowners associations” has been delayed to February 2015 by U.S. District Judge James Mahan.
Defense attorneys “argued they needed more time to review thousands of pages of new documents provided by prosecutors.” The prosecutors did not object to the delay.
Benzer and the other defendants face conspiracy and fraud charges in an HOA takeover scheme that allegedly occurred between 2003 and 2009.
Read the court decisionRead the full story...Reprinted courtesy of
$5 Million Construction Defect Lawsuit over Oregon Townhomes
January 06, 2012 —
CDJ STAFFA homeowners’ association in Lake Oswego, Oregon has filed a $5 million lawsuit against the developers of the luxury townhomes. The homeowners of Sunset Crossing are suing Centurion Homes and Aspen Townhomes over claims that construction defects have lead to water intrusion and structural damages. The townhomes were built in 2005.
Andy Burns, the lawyer for Phillip and Patricia Gentelmann, the owners of both Centurion Homes and Aspen Townhomes, said the Gentelmanns were “taking these allegations very seriously.” The suit says that the construction violated state and local building codes and that the firms did not repair damage caused by water intrusion.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Ohio Court of Appeals Affirms Judgment in Landis v. Fannin Builders
April 20, 2011 —
Beverley BevenFlorez CDJ STAFFThe Ohio Court of Appeals affirmed the judgment in Landis v. William Fannin Builders. Landis contracted Fannin Builders to build their home. The case involved staining problems on the T1-11 siding chosen by the plaintiffs.
After a year and a half of discussion on how to resolve the problem of uneven staining on the siding, Landis filed suit “against Fannin Builders, alleging claims for breach of contract, breach of the express limited warranty, and violation of the Ohio Consumer Sales Practices Act (“OCSPA”). Fannin Builders, in turn, filed a third-party complaint against 84 Lumber, alleging claims for breach of contract and indemnification. With the trial court’s leave, Fannin Builders also later amended its answer to add a counterclaim against appellees for breach of contract and unjust enrichment. In the counterclaim, Fannin Builders alleged that appellees still owed it $3,908.98 for the construction of appellees’ home.”
“In its decision, the trial court found in appellees’ favor on their breach of contract claim and against appellees on their claims for breach of the express limited warranty and violation of the OCSPA. Additionally, the trial court found in Fannin Builders’ favor on its counterclaim for breach of contract and against Fannin Builders on its third-party claims for breach of contract and indemnity. The trial court determined that appellees’ damages amounted to $66,906.24, and after setting off the $3,908.98 that appellees owed Fannin Builders under the construction contract, the trial court awarded appellees $62,997.26. The trial court reduced its decision to judgment on May 18, 2010.”
Fannin Builders appealed this judgment and assigned the following errors:
[1.] The Trial Court Erred as a Matter of Law by Concluding that Appellant Breached its Contract with Appellees when it provided a Semi-Transparent Oil-Based Stain that Simply did not Meet their Approval.
[a.] The Contract does not Contain a Satisfaction Clause.
[b.] Even if the Court Implies a Satisfaction Clause, the Court Should Apply an Objective Standard.
[2.] The Trial Court Erred as a Matter of Law by Failing to Consider Appellant’s Right to Cure.
[3.] The Trial Court committed Reversible Error by not Assessing Damages Using “Diminished Value Standard,” and by Creating a Remedy that Constitutes Economic Waste.
[4.] The Trial Court Erred as a Matter of Law by Concluding that Appellant is Barred from Seeking Indemnification When 84 [Lumber] Never Fulfilled its Obligations Pursuant to the Settlement Agreement Entered on August 2, 2005.
In response to the first assigned error, the Court of Appeals stated: “Because the failure to provide siding of a uniform color, not appellees’ displeasure, breached the contract, we reject Fannin Builders’ contention that the trial court implied a satisfaction clause into the contract and found a breach of that clause. Accordingly, we overrule Fannin Builders’ first assignment of error.”
The Court of Appeals overruled the second assignment of error and provided the following reasoning: “Although Fannin Builders depends upon a term of the limited warranty for its right to cure, the trial court concluded that no breach of the limited warranty occurred. Fannin Builders breached the duty of workmanlike conduct implicit in the construction contract, not the limited warranty requiring it to satisfy the BIA’s Quality Standards. Consequently, the limited warranty does not apply to this case, and thus, it does not prevent appellees’ recovery of damages.”
The Appeals Court found “the trial court’s award of damages” was “both reasonable and supported by competent, credible evidence,” and therefore concluded “that the trial court did not err in setting appellees’ damages at $62,997.26.” The Fannin Builders third assignment of error was overruled.
The fourth and final assignment of error was also overruled by the Court of Appeals. “While Fannin Builders correctly asserts that 84 Lumber never installed the replacement siding, it ignores the fact that it ordered 84 Lumber to remove the replacement siding from appellees’ property. Thus, Fannin Builders precluded 84 Lumber from completely performing under the August 2, 2005 letter agreement. […] Consequently, Fannin Builders cannot now claim that the letter agreement is unenforceable or that it is entitled to indemnification from 84 Lumber. Because Fannin Builders assumed all liability for the defective siding in the letter agreement, it is responsible for appellees’ damages.”
James A. Zitesman, Columbus, Ohio Business Attorney, compared the case to Jones v. Centex (Ohio App. 2010), which had a different verdict:
“The common thread is the implied warranty of good workmanship. In the Jones case, the Court found that the buyers had in fact waived all implied warranties, including the implied warranty of good workmanship. In the contract between Jones and Centex, the builder stated that it “…would not sell the property to Purchasers without this waiver.” Probably should have been a sign to the buyers.
In the Landis case, the Court stated, “Contracts for the future construction of a residence include a duty, implied by law, that the builder must perform its work in a workmanlike manner.” The Court gave significant weight to the concept of the implied warranty of good workmanship. The builder relied upon the BIA Warranty which limits builders’ liability and exposure to legal issues. The trial court concluded there was no breach of the limited warranty, rather the builder “breached the duty of workmanlike conduct implicit in the construction contract, not the limited warranty requiring it to satisfy the BIAs Quality Standards.”
The Supreme Court of Ohio has accepted the Jones v. Centex Homes case for review.
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
OSHA Investigating Bridge Accident Resulting in Construction Worker Fatality
October 29, 2014 —
Beverley BevenFlorez-CDJ STAFFSI Live reported that “[t]he federal Occupational Safety and Health Administration has opened a probe into an early-morning truck accident at the Verrazano-Narrows Bridge that left a construction worker dead Wednesday.” The accident occurred in New York “when a truck laying asphalt backed into [the worker] and crushed him.”
Ted Fitzgerald, OSHA spokesman, stated, “OSHA did respond and has opened an inspection to determine whether or not there were violations of workplace safety standards in connection with this fatality,” as quoted by SI Live.
Read the court decisionRead the full story...Reprinted courtesy of
Hawaii Supreme Court Says Aloha to Insurers Trying to Recoup Defense Costs From Policyholders
January 02, 2024 —
Lara Degenhart Cassidy & Yosef Itkin - Hunton Insurance Recovery BlogThe Hawaii Supreme Court emphatically rejected insurer efforts to seek reimbursement of defense costs absent a provision in the policy providing for such reimbursement in St. Paul Fire & Marine Insurance Company v. Bodell Construction Company, No. SCCQ-22-0000658, 2023 WL 7517083, (Haw. Nov. 14, 2023). The state high court’s well-reasoned decision rests on bedrock law regarding insurance policy construction and application, follows the nationwide trend of courts compelling insurers to satisfy their contractual obligations in full, and should carry great weight as other jurisdictions continue to debate the same issue.
In Bodell, the Hawaii Supreme Court joined the swelling ranks of courts recognizing that an insurer may not use a reservation of rights to create the extra-contractual “right” to recoup already paid defense costs for a claim on which the insurer ultimately owes no coverage. See, e.g., Am. & Foreign Ins. Co. v. Jerry’s Sport Ctr., Inc., 2 A.3d 526 (Pa. 2010). Other jurisdictions, such as California, will permit an insurer to seek reimbursement from a policyholder for defense costs incurred in defending claims later determined to be uncovered. See Buss v. Superior Court, 16 Cal.4th 35 (1997) (holding insurers have a right to reimbursement of defense costs incurred for noncovered claims).
Reprinted courtesy of
Lara Degenhart Cassidy, Hunton Andrews Kurth and
Yosef Itkin, Hunton Andrews Kurth
Ms. Cassidy may be contacted at lcassidy@HuntonAK.com
Mr. Itkin may be contacted at yitkin@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Hunton Insurance Recovery Lawyers Ranked by Chambers as Top Insurance Practitioners
May 27, 2019 —
Michael S. Levine - Hunton Andrews KurthHunton Andrews Kurth insurance recovery partner,
Lorie Masters, received a top “Band 1” ranking by Chambers and Partners in the Insurance: Policyholder category for the District of Columbia, and a “Band 2” ranking in the Insurance: Dispute Resolution: Policyholder – USA – Nationwide category.
Hunton Andrews Kurth insurance recovery associate,
Andrea DeField, also was recognized by Chambers in the Associate to Watch: Insurance: Florida category.
Read the court decisionRead the full story...Reprinted courtesy of
Michael S. Levine, Hunton Andrews KurthMr. Levine may be contacted at
mlevine@HuntonAK.com