Public Contract Code Section 1104 Does Not Apply to Claims of Implied Breach of Warranty of Correctness of Plans and Specifications
October 30, 2023 —
Garret Murai - California Construction Law BlogIt’s the classic tale of two cities. One city is occupied by architects and engineers. The other, by contractors. And while the cities typically co-exist relatively peacefully together, at times, they do not, such as when a defect arises that can either be a design or construction defect.
Sometimes, project owners are pulled into these fights as well. There is a common law rule that when contracting with a contractor the owner impliedly warrants to the contractor that the plans and specifications are sufficiently accurate and correct.
And, if you work on local public works projects, you may be familiar with Public Contract Code section 1104 which provides that, with the exception of design-build projects, local public entities cannot require a bidder to assume responsibility for the completeness and accuracy of architectural or engineering plans and specifications.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
With VA Mechanic’s Liens Sometimes “Substantial Compliance” is Enough (but don’t count on it) [UPDATE]
October 14, 2019 —
Christopher G. Hill - Construction Law MusingsVirginia mechanic’s liens are a powerful and tricky beast that in most cases require absolute precision in their preparation. However, an interesting opinion recently came out of the Virginia Supreme Court that may provide a bit of a “safe harbor” from the total form over function nature of a mechanic’s lien.
In Desai, Executrix v. A.R. Design Group Inc., the Court considered a lien memorandum that had what could be described as technical flaws in the preparation of the mechanic’s lien by A. R. Design Group. The basic facts are that A. R. Design Group used the form of lien found in Va. Code Sec. 43-5 (also found as Form CC-1512 at the Virginia Judiciary website) when it recorded two lien memoranda for two pieces of property owned by a trust. Relating to one of the two properties, the memorandum failed to identify the “Owner” as the trustee of the trust. On the memoranda relating to both properties the affidavit verifying the amounts claimed did not identify the signatory as agent for A. R. Design Group, instead listing the agent as the claimant and further failed to state a date from which interest is claimed or a date on which the debt was due.
Needless to say, the owner argued that each of these technical defects invalidated the memoranda and therefore they should have been released. Somewhat surprisingly the Fairfax, Virginia Circuit Court disagreed and held the liens to be valid. On appeal, the Virginia Supreme Court affirmed the lower court. The held that the failure to add the word “Trustee” after Ulka Desai’s name did not invalidate the lien because the trustee had all of the rights of ownership and furthermore that naming Desai in the memorandum served the purpose of putting third parties on notice of the lien.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Force Majeure, Construction Delays, Labor Shortages and COVID-19
April 06, 2020 —
Elizabeth J. Dye - Gravel2Gavel Construction & Real Estate Law BlogThe global effect of the Coronavirus disease (COVID-19) is still unknown, and the progress of many large-scale construction projects has been affected by “Shelter in Place” orders, although some states and localities have classified construction projects as “essential.” Just last Friday, New York shut down all construction, with few exceptions.
Several states have enacted gathering bans of all sizes (including Michigan, Oregon, New Mexico, Washington, New York, New Jersey, Wisconsin, Illinois, Indiana, Ohio, West Virginia, California) and more people are likely to be quarantined as widespread testing becomes available. These decisions will undoubtedly affect the supply of materials and labor necessary for construction projects.
Officials have turned to increasingly disruptive and measures to control the spread of the virus in addition to event prohibitions and school closures, including restricting people to their homes, and closing businesses that are not “essential.” While many companies have adopted mandatory telecommuting, this is an impossibility on the construction sites. Eventually, supply and labor shortages due to governmental restrictions or quarantines will affect the critical path of construction projects.
Read the court decisionRead the full story...Reprinted courtesy of
Elizabeth J. Dye, PillsburyMs. Dye may be contacted at
elizabeth.dye@pillsburylaw.com
Connecting Construction Project Information: Open Technology Databases Improve Project Communication, Collaboration and Visibility
March 14, 2018 —
Andy Kayhanfar - InEightThe construction industry has been plagued for decades with projects coming in over budget and behind schedule. There are many reasons this happens, but it ultimately comes down to just one thing – a lack of connected information.
Today, gigabytes and even terabytes of data are generated on a project and housed in different systems that do not talk or share information, which creates a closed approach and inhibits collaboration. Data is siloed and only accessible to certain companies, departments or disciplines, which gives each project stakeholder a very limited view into the status of the project as they are making decisions.
To be successful, the construction industry needs to free project data from closed systems. There must be a way to give all project stakeholders access to accurate information within the context of how it applies to the overall project that will empower everyone from owners to engineers to contractors to make timely, fully informed decisions that bring projects in on time and within budget.
INTRODUCING THE OPEN TECHNOLOGY DATABASE
The need for deep visibility into project information across systems and stakeholders has given rise in the construction industry to the open technology database. This approach enables project stakeholders to link the data in their existing software systems and connect that information into one centralized location. Project stakeholders can continue to use and maintain the data in their own systems while still feeding the information to the shared environment, which brings together critical project details, provides context for decisions and makes it easier for all parties to collaborate.
Project stakeholders are now able to connect business data related to estimating, cost control, scheduling, contracts, purchasing, accounting and more. This creates a common data set across the project that can be quickly accessed and can easily be put in the hands of project decision makers.
Innovative companies are taking this connectivity to a new level. They see the potential to use 3D models beyond simply the design aspects of a project and bring them into the activities of construction. Innovators are taking all the project information available in the shared environment and connecting it to the 3D model to create a comprehensive view of the project.
Read the court decisionRead the full story...Reprinted courtesy of
Andy Kayhanfar, Construction Executive, a Publication of Associated Builders and Contractors. All Rights Reserved
A Lot of Cheap Housing Is About to Get Very Expensive
October 21, 2015 —
Patrick Clark – BloombergUrban Institute fellow Erika Poethig has a poster in her office showing 22 apartment buildings along Chicago's Lake Shore Drive. They were all built with U.S. government dollars to provide affordable housing to thousands of low-income households—and have since been converted to market-rate apartments and condominiums.
For Poethig, a former official at the Department of Housing and Urban Development, those apartments are a warning.
There are currently about 1.34 million units of affordable housing created by a HUD program known as Section 8 project-based rental assistance, according to a blog post published on Wednesday by Poethig and her Urban Institute colleague Reed Jordan. More than 30 percent of those units are kept affordable by contracts that are set to expire by the end of 2017.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick Clark, Bloomberg
Pennsylvania Court Extends Construction Defect Protections to Subsequent Buyers
December 20, 2012 —
CDJ STAFFThe Pennsylvania courts have long held that there is an implied warranty of habitability for the initial purchaser of a home. Now, as some defects may not immediately show up, the court has extended that implied warranty to second and subsequent purchasers. As Marc D. Brookman, David I. Haas, and Christopher Bender of Duane Morris note, “this judicially created doctrine shifts the risk of a latent defect in the construction of a new home from the purchaser to the builder-vendor.”
The Pennsylvania Supreme Court concluded that a contractual relationship is not needed for an implied warranty of habitability. The court’s concern was inequalities would result when a home was sold while other homes were protected by being within the statute of repose.
Read the court decisionRead the full story...Reprinted courtesy of
Ninth Circuit Reverses Grant of Summary Judgment to Insurer For Fortuitous Loss
July 01, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe Ninth Circuit reversed the district court's issuance of summary judgment regarding coverage for damages when the insured's plant had to be shut down due to an accident. Ingenco Holdings, LLC v. Ace American Ins. Co., 2019 U.S. App. LEXIS 10946 (9th Cir. April 15, 2019).
Ingenco operated a gas purification plant which converted raw landfill gas into usable natural gas. The final step in the purification process involved the removal of excess nitrogen from the landfill gas. The gas was directed through adsorbent beads, to which nitrogen adhered, contained within pressure vessels.The beads could not withstand the direct pressure of the landfill gas inflow. which, if untreated, could grind the beads down into dust. To reduce the force of the gas flow on the beads, a "diffuser basket" was suspended from the top of each bead-filled pressure vessel. The diffuser basket acted as a shield that prevented the full force of the incoming landfill gas from striking the beads directly.
In 2010, metal brackets securing a diffiuser basket broke. This resulted in damage to other components and an eventual shutdown of the entire facility. The plant remained idle for several months as Ingenco investigated alternative nitrogen filtration options and undertook repairs.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Facebook Posts “Not Relevant” Rules Florida Appeals Court
February 07, 2014 —
Beverley BevenFlorez-CDJ STAFFA Cape Coral, Florida resident is suing the city and construction companies over alleged negligence “for failing to use reasonable care in keeping the construction site safe for pedestrians,” according to News-Press. The lawsuit was filed after a three-year old boy “jumped out of a wagon pulled by his aunt and darted across the construction zone before being” hit and dragged by a vehicle. The boy “suffers neurological problems from the crash.” The defendants wanted to use Facebook posts made by the Plaintiff about the city, contractors, and subcontractors, as evidence. However, the 2nd District Court of Appeals ruled that the Facebook posts were irrelevant to the case.
Todd Robert Falzone, the Plaintiff attorney, said that “it’s becoming more common for defense lawyers to try and introduce social media into any case, but the law is new and there isn’t a lot of guidance for lawyers or judges,” according to News-Press. The defendants’ attorneys did not return News-Press’s calls asking for comments.
Read the court decisionRead the full story...Reprinted courtesy of