A Primer on Insurance for Construction Projects
November 30, 2020 —
Garret Murai - California Construction Law BlogPeople who live in glass houses should have insurance (in addition to not throwing stones). So too should your construction project.
The risks inherent on a construction project are many and varied, ranging from property damage to personal injury to pollution remediation costs, and wise contractors and project owners know that one of the best ways to mitigate these risks is through insurance. So, here’s a primer on what you need to know about insurance on construction projects.
Commercial General Liability Insurance (CGL)
What it Covers:
- Property damage.
- Bodily injury.
- Personal and advertising injury (e.g., libel and slander).
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Patagonia Will Start Paying for Homeowners' Solar Panels
October 15, 2014 —
Caroline Winter – Bloomberg BusinessweekPatagonia plans to use state and federal tax credits to invest $13 million in the construction of solar panels on 1,000 homes in Hawaii, turning the eco-conscious retailer into the financial backer of a green electrical utility.
With the announcement on Wednesday, Patagonia hopes companies across America will follow suit with similar efforts. “Any U.S. public or private company who pays their fair share of taxes can use this strategy to speed up the development of new energy infrastructure,” Rose Marcario, Patagonia’s chief executive, said in an interview. “And they can make money doing it and create jobs.”
Patagonia is joining forces with a tiny solar-financing company, Kina’ole Capital Partners, as well as a local Hawaiian bank to create a $27 million fund to pay for rooftop installation and upkeep. Starting in Hawaii makes sense because of its abundant sunshine and sky-high electrical rates; Hawaiians currently pay three times the U.S. average for electricity.
Read the court decisionRead the full story...Reprinted courtesy of
Caroline Winter, Bloomberg BusinessweekMs. Winter may be contacted at
cwinter10@bloomberg.net
The Advantages of Virtual Reality in Construction
August 20, 2019 —
Spivey Lipsey - Construction ExecutiveVirtual realty provides an unparalleled spatial sense for visualization at a lower cost than full-scale replicas. Today, VR is being used heavily in preconstruction to align owner expectations and educate design team stakeholders. For those already employing BIM solutions, coordination can be made much more effective by leveraging existing design models with very little added cost.
As anyone who has tried a VR headset before can attest, the ability to accurately perceive spatial relationships in design cannot be replicated through traditional 2D media such as screens or paper. VR solutions also have the ability to iterate rapidly. These technologies are linked to BIM, providing real-time feedback as the design changes. This is in stark contrast to traditional full-scale mockups and offline renders, which are cumbersome and time-consuming to update with design changes.
Substantial benefits without a hefty price tag
Budget limitations and ROI are always a concern with emerging technology. Fortunately, VR comes cheaply with BIM production. These solutions are significantly less expensive than full-scale mockups and far more efficient when compared to longhand sequencing explanations and esoteric detailing of complex designs. Even the most elaborate VR setups are a fraction of overall construction cost, ranging from a few hundred to a few thousand dollars depending on the level of adoption.
Reprinted courtesy of
Spivey Lipsey, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Practical Pointers for Change Orders on Commercial Construction Contracts
December 31, 2014 —
John E. Bowerbank - Newmeyer & DillionConstruction projects pose unique challenges, including keeping costs within budget, meeting project deadlines, and coordinating the work of numerous contractors and subcontractors in the wake of inevitable design revisions and changes to the plans. Anticipating potential project challenges and negotiating contract provisions before commencing work on a project is critical for all parties. Careful planning should reduce the number of contract disputes. This, in turn, can facilitate the completion of a project within budget and on schedule.
“Changes” Clauses in Construction Contracts
Most commercial construction contracts have a clause addressing changes to the contract. A “changes” clause typically requires the mutual agreement of the parties on the scope of any modifications to the contract, as well as the effect on the contract price and timeframe for the work to be performed. This results in what is generally referred to as a “change order.” Many projects have a large number of change orders, which can result in significant cost overruns and delays to the project if the contract contains a complicated change order process. Therefore, in order to minimize cost overruns and project delays, it is crucial to keep the change order process as simplified and streamlined as possible.
In the most basic terms, change orders memorialize modifications to the original contract, and typically alter the contract's price, scope of work, and/or completion dates. A typical change order is a written document prepared by the owner or its design professional, and signed by the owner, design professional, and affected contractors and subcontractors. An executed change order indicates the parties’ agreement as to what changes are taking place, including approval for additional costs and schedule impacts.
While the reasons for change orders and the parties initiating them may vary, all change orders have one feature in common. Effective change orders alter the original contract and become part of the contract. Therefore, from a legal standpoint, change orders must be approached with the same caution and forethought as the original contract.
Practice Pointers for Change Orders
In light of the foregoing, some practice pointers for change orders in commercial construction contracts are as follows:
- Carefully Negotiate and Draft Change Order Provisions in the Original Contract.
A carefully negotiated and drafted “changes” clause that accounts for “unexpected circumstances” or “hidden conditions” can protect the parties from downstream costly disputes.
- Immediately Address Changes by Following the Change Order Process, Including Obtaining Necessary Signatures.
Regardless if you are an owner, general contractor or subcontractor, you should address any proposed change order immediately. Even if a decision maker gives “verbal” approval to go ahead with changed work, the work should not proceed without following the change order process in the original contract. This includes making sure to obtain any necessary signatures for the change order, if at all possible.
- Analyze the Plans and Specifications to Determine Whether “Changes” are Within the Scope of the Original Contract, or Whether They are Extra Work.
Prior to entering an original contract, it is imperative that the parties review the plans and specifications for ambiguities regarding work included in the original contract, versus potential extra work that would require a change order. This is important because a careful review of the plans and specifications sometimes reveals that work believed to be a change order is, in fact, original work, or vice versa.
- Make Sure Requests and Approvals for Change Orders are Done by an Authorized Representative.
When a party requests or gives its approval to a change order, it is important to confirm the request or approval came from an authorized representative.
- Avoid Vague and Open-Ended Change Orders.
Indeed, the vaguer a change order, the more likely it can lead to a dispute. Vague and open-ended change orders, including change orders that provide for payment on a time and materials basis, can be difficult for an owner to budget and schedule. This can lead to disputes as to cost and/or time extensions.
- Oral Assurances for Payment Without a Signed Change Order May Not Be Recoverable.
When a party provides verbal assurances to another party for extra work without following the change order process, there is a much higher likelihood that disputes will occur. Although there is case law that may allow a contractor to recover for extra work in private contracts based on oral promises, the parties should avoid placing themselves in such a legal position. Notably, in public contracts, a contractor may not be able to recover for any extra work without a signed changed order, even with verbal assurances of payment from the owner.
About the Author:
John E. Bowerbank, Newmeyer & Dillion
Mr. Bowerbank is a partner in the Newport Beach office and practices in the areas of business, insurance, real estate, and construction litigation. You can reach John at john.bowerbank@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Billionaire Behind Victoria’s Secret Built His Version of the American Heartland
June 25, 2019 —
Sophie Alexander - BloombergBeyond emerald-green golf links, over snow-white fences, and past tree-lined cul-de-sacs rises the American fantasyland of billionaire Les Wexner.
Here in the middle of Ohio, of all places, Wexner—the man behind Victoria’s Secret and its push-up-bra notions of female beauty—has brought to life his singular vision of the heartland.
Read the court decisionRead the full story...Reprinted courtesy of
Sophie Alexander, Bloomberg
Fifth Circuit Rules that Settlements in Underlying Action Constitute "Other Insurance"
April 17, 2019 —
Tiffany Casanova - Saxe Doernberger & Vita, P.C.The Fifth Circuit ruled that settlements between an insured and its subcontractors qualified as “other insurance” to the extent those settlements were used to pay for damages covered by an excess insurance policy. Policyholders should note the outcome of this case as it demonstrates the significant impact that settlements can have on coverage.
Satterfield & Pontikes Construction, Inc. v. Amerisure Mutual Ins. Co.1 was the result of a construction project gone wrong. Zapata County, Texas hired Satterfield & Pontikes (“S&P”) as a general contractor for the construction of a courthouse building. When the project did not go as planned, Zapata County terminated S&P, hired new subcontractors to complete the project, and sued S&P.
S&P, in turn, sought indemnification from its subcontractors, who were contractually obligated to indemnify S&P and procure insurance for any damage the subcontractors caused at the project. S&P also sought coverage from its own primary insurers, American Guarantee and Liability Insurance Company (“AGLIC”) and Amerisure Mutual Insurance Company (“Amerisure”), and its excess insurer, U.S. Fire Insurance Company (“U.S. Fire”) who provided liability coverage for S&P’s potential liabilities at the project. The policies contained exclusions for losses arising from mold and did not provide coverage for attorney’s fees or similar legal costs.
Read the court decisionRead the full story...Reprinted courtesy of
Tiffany Casanova, Saxe Doernberger & Vita, P.C.Ms. Casanova may be contacted at
tlc@sdvlaw.com
Domingo Tan Receives Prestigious Ollie Award: Excellence in Construction Defect Community
May 28, 2024 —
Wood Smith Henning & Berman(Anaheim, CA.) - Wood Smith Henning & Berman is thrilled to announce that
Domingo Tan, a partner in the Los Angeles office, has been awarded the prestigious Jerrold S. Oliver Award of Excellence. Fondly known as the "Ollie", this esteemed accolade is presented annually to a standout professional in the construction defect community who has demonstrated exceptional contributions and unwavering dedication to the field.
The exciting announcement of Tan's victory took place during the 30th Anniversary of the West Coast Casualty Construction Defect Seminar in Anaheim. Widely recognized as the nation's largest conference for professionals handling construction defect matters, the event drew a remarkable gathering of general counsel, risk managers, claim professionals, and attorneys who actively participated in the nomination and voting process.
The Ollie award pays tribute to the late Judge Jerrold S. Oliver, a highly respected legal professional renowned for his groundbreaking work in alternate dispute resolution methods for construction defect disputes. It celebrates individuals who embody the values of loyalty, commitment, and trust within the industry.
Read the court decisionRead the full story...Reprinted courtesy of
Wood Smith Henning & Berman
Unlicensed Contracting and Florida Statute S. 489.128
February 03, 2025 —
David Adelstein - Florida Construction Legal UpdatesFlorida Statute s. 489.128 is a statute that provides a remedy against unlicensed contracting. However, keep in mind that this argument—the unlicensed contractor argument—is a technical statutory argument. In other words, it’s not so much of a fact-based merits argument, but an argument that’s solely based on the technicality of the statute. This, by no means, is not a recommendation that the argument should not be raised. In instances, it absolutely should be and could have legitimate traction. However, when deciding whether to or how to pursue a dispute, including settlement, you want to keep in mind whether this is an argument you want to bank your outcome on because there are always costs (attorney’s fees, court costs, etc.) that should get factored into any business decision regarding a dispute.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at