CDJ STAFFThe California Court of Appeals in Stanislaus County has reversed the decision of the lower court in Greg Opinski Construction Inc. v. City of Oakdale. The earlier court had awarded the city of judgment of $54,000 for late completion, $3,266 for repair of construction defects and interest, and $97,775 in attorneys’ fees. The late completion of the project was due to actions by the City of Oakdale, however, the court rejected Opinski’s argument that the California Supreme Court decision in Kiewit did not allow this, as his contract with the city established a procedure for claiming extensions.
The appeals court noted that the Kiewit decision has been “criticized as an unwarranted interference in the power of contracting parties to shift the risk of delays caused by one party onto the other party by forcing the second party to give the first notice of any intention to claim an extension of time based on delays caused by first.” They cited Sweet, a professor at Boalt Hall, UC Berkeley’s law school, that Kiewit “gutted” the “provision that conditions the contractor’s right to claim an extension of time for delays beyond his control.”
Further changes in California law in response to the Kiewit decision lead to the current situation which the court characterized as “if the contractor wished to claim it needed an extension of time because of delays caused by the city, the contractor was required to obtain a written change order by mutual consent or submit a claim in writing requesting a formal decision by the engineer.”
Opinski also argued that the lower court misinterpreted the contract. The Appeals court replied that “Opinski is mistaken.” He cited parts of the contract regarding the increase of time, but the court rejected these, noting that “an inability to agree is not the same as an express rejection.”
The court also rejects Opinski’s appeal that “the evidence the project was complete earlier than September 30, 2005, is weightier than the evidence to the contrary,” which they describe as “not a winning appellate argument.” The court points out that the role of an appeals court is not to reweigh the evidence, but to determine “whether the record contains substantial evidence in support of the judgment.”
The court did side with Opinski on one question of the escrow account. They rejected most of his arguments, repeating the line “Opinski is mistaken” several times. They decided that he was mistaken on the timing of the setoff decision and on whether the city was the prevailing party. However, the appeals court did find that Opinski was not liable for interest on the judgment.
The appeals court rejected the awarding of prejudgment interest to the city as the funds from which the judgment was drawn was held in an escrow account. The court noted that the city had access to the funds and could “access the funds when it determined that Opinski had breached the contract.” The appeals court noted that the judgment exhausted the escrow balance and remanded the case to the lower court to determine the amount own to Opinski.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Insurer Must Cover Construction Defects Claims under Actual Injury Rule
March 01, 2012 —
Tred R. Eyerly - Insurance Law HawaiiThe Texas Court of Appeals held that the insured need not prove the exact dates physical damage occurred in order to trigger defense and indemnity coverage. Vines-Herrin Custom Homes, LLC v. Great Am. Lloyds Ins. Co., 2011 Tex. App. LEXIS 10027 (Tex. Ct. App. Dec. 21, 2011).
In 1999, the insured built a home. He was insured under a CGL policy issued by Great American from November 9, 1998 to November 9, 2000. Thereafter, the insured held a CGL policy issued by Mid-Continent from November 9, 2000 to September 18, 2002.
After construction was completed, the insured sold the house to the buyer in May 2000. After moving in, the buyer found numerous construction defects in the home, including water entering cracks in the home, and sinking and sagging of parts of the house. The buyer sued the insured, who sought coverage under the two policies. When the insurers refused to defend the underlying suit, the insured sued for a declaratory judgment.
The underlying case went to arbitration and an award of $2.4 million was granted to the buyer. The insured assigned to the buyer his claims against the insurers.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
New Mexico Holds One-Sided Dispute Resolution Provisions Are Unenforceable
November 05, 2024 —
Bill Wilson - Construction Law ZoneDispute resolution provisions that grant one party the unilateral right to choose either litigation or arbitration to resolve disputes are common in the construction industry. The main difference between the two forums is that courts are more likely to strictly enforce contract terms as written as well as the applicable law, while arbitrators make decisions on more equitable considerations, untethered to the contract terms and—to some degree—the law. The party with the sole discretion to select the dispute resolution procedure can select the process most beneficial to its interests based on the nature of the dispute, regardless of who brings the claims. In Atlas Electrical Construction, Inc. v. Flintco, LLC, 550 P.3d 881 (N.M. Ct. App. 2024), the Court of Appeals of New Mexico recently held that an arbitration provision in a subcontract, under which the contractor retained the exclusive right to choose whether disputes arising under the subcontract were litigated in court or arbitrated was unreasonably one-sided, substantively unconscionable, and unenforceable.
The Atlas Electrical case involved two sophisticated entities with equal bargaining strength to negotiate the terms of a subcontract. The parties agreed to a subcontract provision which provided in the relevant part:
In the event [contractor] and [subcontractor] cannot resolve the dispute through direct discussions or mediation … then the dispute shall, at the sole discretion of [contractor], be decided either by submission to (a) arbitration … or (b) litigation …
Read the court decisionRead the full story...Reprinted courtesy of
Bill Wilson, Robinson & Cole LLPMr. Wilson may be contacted at
wwilson@rc.com
Lasso Needed to Complete Vegas Hotel Implosion
February 18, 2015 —
Beverley BevenFlorez-CDJ STAFFThe Miami Herald reported that “demolition workers used an Old West method on Tuesday to finish an incomplete casino implosion in Las Vegas.”
The Clarion Hotel and Casino owner Lorenzo Doumani told the Miami Herald that “[t]hey lassoed the building with steel cables, got a crane, and pulled and pulled and pulled.”
Burke Construction used a 2-ton explosive punch to bring the structure down, however, the concrete building dropped four stories but remained upright.
Burke Construction’s corporate safety coordinator, Anthony Schlect, told the Miami Herald that he was investigating the incident.
Read the court decisionRead the full story...Reprinted courtesy of
Jury Trials and Mediation in Philadelphia County: Virtually in Person
July 27, 2020 —
Andrew F. Susko, Robert G. Devine & Daniel J. Ferhat - White and Williams LLPWhen will the trial court in Philadelphia County be open for jury trials in civil actions? While a precise prediction, given the current state of our trial courts in the middle of the COVID-19 pandemic, is difficult to make, what is known is that the use of virtual technology is likely permanently changing the landscape of civil litigation, including depositions, mediation, and other forms of alternative dispute resolution. Even civil jury trials, at least in the near term and during the pandemic, are being conducted virtually, either by private agreement, or through the courts, as is occurring in Texas and most recently in Florida with its pilot virtual trial program in five of its trial courts. While it is necessary at present for the parties to consent to a virtual trial, courts may ultimately compel the parties’ participation. Regardless, litigants and their counsel are well advised to understand the complexities and manner of a virtual trial.
Seasoned trial attorneys have long experienced and are comfortable with virtual depositions bringing distant counsel, parties and witnesses together through technology to present testimony. The use of virtual technology as a means for court arguments and hearings, mediation, and alternative dispute resolution, while novel and emerging as the new normal, is territory where a comfort level can be achieved. And while distinctions most assuredly exist, recent experience has demonstrated that court arguments, mediations and depositions can be conducted effectively remotely and virtually. Legal issues certainly do remain in the context of the deposition of parties to a civil action regarding whether a lawyer’s physical presence in the same room with a party-witness can be demanded, and whether courts would compel a virtual deposition during the COVID-19 pandemic where such physical presence of a party and their attorney could not be achieved. Undoubtedly these issues will be resolved, likely sooner than later, given the scope of the pandemic in certain areas.
Reprinted courtesy of White and Williams LLP attorneys
Andrew F. Susko,
Robert G. Devine and
Daniel J. Ferhat
Mr. Susko may be contacted at suskoa@whiteandwilliams.com
Mr. Devine may be contacted at deviner@whiteandwilliams.com
Mr. Ferhat may be contacted at ferhatd@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Contractors Can No Longer Make Roof Repairs Following Their Own Inspections
July 02, 2018 —
Jason Feld & Alex Chazen - Kahana & Feld LLPCalifornia law mandates that any person who conducts roof inspections for a fee can no longer effectuate the actual repairs to the same property. Effective January 1, 2018, Business & Professions Code Section 7197 (Unfair Business Practices) deems it to be an unfair business practice for a home inspector who charges a homeowner a monetary fee for inspecting the property, to perform or offer to perform additional repairs due to the inherent financial interest and conflict raised by identifying alleged defects necessitating repairs. The new law is a result of California AB 1357, which was signed into law on October 5, 2017. The goal of the new law is to disincentivize a roof inspector from creating a report for the sole purpose of obtaining a bid to perform those documented repairs. The roof contractor can perform repairs identified in their report only after a twelve month “cooling period” which provides the homeowner an opportunity to obtain multiple bids/estimates for repairs based upon the inspector’s report. The new law also discourages home inspectors from providing a list of contractors who provide monetary referral fees back to the home inspector upon receiving repair work from the homeowner based exclusively on the home inspection report.
The California Business & Professions Code Section 7195(a)(1) defines a “home inspection” as a “non-invasive, physical examination, performed for a fee in connection with the transfer…of the real property…or essential components of the residential dwelling.” Home inspection includes “any consultation regarding the property that is represented to be a home inspection or any confusingly similar term.” Business & Professions Code section 7195(a)(2) further defines a “home inspection” as including energy efficiency and solar. A “home inspection report” is a written report prepared for a fee issued after an inspection. Business & Professions Code section 7195(c). It is noted that a home inspector does not have to be a licensed architect, professional engineer, or general contractor with a Class “B” license issued by the California Contractors State License Board, but “it is the duty of a home inspector who is not licensed as a general contractor, structural pest control operator, or architect, or registered as a professional engineer to conduct a home inspection with the degree of care that a reasonably prudent home inspector would exercise. Business & Professions Code section 7196.
Reprinted courtesy of
Jason Feld, Kahana & Feld LLP and
Alex Chazen, Kahana & Feld LLP
Mr. Feld may be contacted at jfeld@kahanalaw.com
Mr. Chazen may be contacted at achazen@kahanafeld.com
Read the court decisionRead the full story...Reprinted courtesy of
Report: Construction Firms Could Better Protect Workers From Noise Hazards
April 17, 2019 —
Joanna Masterson - Construction ExecutiveGiven that about three-quarters of construction workers are exposed to noise levels above the recommended limit, 83 percent of the 237 contractors surveyed for a new Dodge Data & Analytics SmartMarket Brief say they’ve purchased quieter equipment, yet well over half of those firms report their company could do better.
Additionally, 85 percent of contractors report using hearing protection onsite more than 50 percent of the time, yet less than half say they always use it, suggesting a significant opportunity for improvement in the industry. Digging deeper, the survey determined small companies lag behind large and midsize ones in the use of hearing protection. Also, half of general contractors report always using hearing protection, compared to about one-third of trade contractors.
Reprinted courtesy of
Joanna Masterson, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick Haggerty Promoted to Counsel
May 24, 2021 —
Patrick Haggerty - White and Williams LLPWhite and Williams is pleased to announce the promotion of Patrick Haggerty to the position of Counsel. Pat is a member of the Real Estate and Finance groups and practices in the Philadelphia office.
Pat focuses his practice on a wide range of commercial real estate transactions and financings. He represents real estate developers, owners, and investors, international and domestic banks, private equity firms, hedge funds, and insurance companies in the financing, acquisition, development, repositioning and disposition of commercial real estate assets.
“Pat’s unique skillset and impressive experience enhances the services which we can provide to our real estate and finance clients. We are proud to promote such a talented lawyer,” said Tim Davis, Chair of the Business Department. “We look forward to his continued success.”
Read the court decisionRead the full story...Reprinted courtesy of
Patrick Haggerty, White and Williams LLPMr. Haggerty may be contacted at
haggertyp@whiteandwilliams.com