Proposed Florida Construction Defect Act
January 09, 2015 —
Beverley BevenFlorez-CDJ STAFFMichael J. Furbush and Thomas P. Wert of Roetzel & Andress discussed Florida’s House Bill 87, which proposes to “substantially overhaul Florida’s Construction Defect Act, Chapter 558, requiring property owners to provide more detailed notice of the alleged defect and imposing sanctions on property owners who make frivolous claims.”
Representative Kathleen Passidomo sponsored the bill, which “requires claimants to provide additional details about the alleged defect in the notice of claim, including the specific location of each alleged defect, and the specific provisions of the building code, plans, or specifications that serve as the basis of the defect claim. The failure to include this information in the notice of claim would be considered prima facie evidence of a defective notice.”
Read the court decisionRead the full story...Reprinted courtesy of
Congress Considers Pandemic Risk Insurance Act to Address COVID-19 Business Interruptions Losses
May 18, 2020 —
Richard W. Brown & Andres Avila - Saxe Doernberger & Vita, P.C.The draft legislation, entitled the Pandemic Risk Insurance Act of 2020 (“PRIA”), would establish a Federal Pandemic Risk Reinsurance Fund and Program (the “Program”), that is intended to provide a system of shared public and private compensation for business interruption (“BI”) losses resulting from a pandemic or outbreak of communicable disease. PRIA, in its current draft form, is modeled after and in many ways mirrors the Terrorism Risk Insurance Act that was enacted to address catastrophic losses resulting from acts of terrorism.
PRIA effectively mandates that participating insurers provide coverage for any business interruption loss resulting from an outbreak of infectious disease or pandemic that is declared an emergency or major disaster by the President and certified by the Secretary of Treasury (the “Secretary”) as a public health emergency. PRIA would be triggered in the case of certified public health emergencies upon the aggregate industry insured losses exceed $250 million dollars, and include an annual aggregate limit capped at $500 billion dollars. The draft bill provides that the Secretary would administer the Program and pay the Federal share of compensation for insured losses, which would be 95% of losses in excess of an applicable insurer annual deductible, once the Program is triggered. The compensation would benefit those insurers that elect to participate in the Program in exchange for a premium paid by the participating insurer for reinsurance coverage under the Program.
Reprinted courtesy of
Richard W. Brown, Saxe Doernberger & Vita, P.C. and
Andres Avila, Saxe Doernberger & Vita, P.C.
Mr. Brown may be contacted at rwb@sdvlaw.com
Mr. Avila may be contacted at ara@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
CDJ’s #8 Topic of the Year: California’s Board of Equalization Tower
December 31, 2014 —
Beverley BevenFlorez-CDJ STAFFImagine a workplace where bats fly, floors flood, and glass panels randomly pop out of the building to shatter on the sidewalk. Add to that repairs that could total more than twice the purchase price, and you have a story. Especially when it involves a California government facility. Jon Ortiz of the Sacramento Bee shared the story on Insurance News.
Read the court decisionRead the full story...Reprinted courtesy of
Affirmed: Nationwide Acted in Bad Faith by Failing to Settle Within Limits
July 19, 2017 —
Bethany Barrese – Saxe Doernberger & Vita, P.C.The Eleventh Circuit recently affirmed that Nationwide acted in bad faith by refusing to settle a claim against its insured for the policy limits, exposing the policyholder to an excess verdict.1
The case arose out of a 2005 automobile accident where Seung Park, who was insured by Nationwide, struck and killed another driver, Stacey Camacho. Shortly after the accident, Ms. Camacho’s estate issued a time-limited demand for the full limits of the policy Nationwide issued to Mr. Park, $100,000, to settle the case. After the deadline to respond to the demand expired, Nationwide rejected the demand and made a counteroffer. A settlement could not be reached and a wrongful death suit was filed against Mr. Park, resulting in a massive jury verdict of $5.83 million.
Following the jury verdict, Mr. Park assigned his rights against Nationwide to Ms. Camacho’s estate, which then filed claims for negligence and bad faith failure to settle against Nationwide. The case was tried to a jury, which found in favor of the estate.
Read the court decisionRead the full story...Reprinted courtesy of
Bethany Barrese, Saxe Doernberger & Vita, P.C.Ms. Barrese may be contacted at
blb@sdvlaw.com
Contractors: Revisit your Force Majeure Provisions to Account for Hurricanes
September 20, 2017 —
David Adelstein - Florida Construction Legal UpdatesWe now know and can appreciate the threat of hurricanes. Not that we did not appreciate the reality of hurricanes–of course we did–but Hurricane Harvey and Hurricane Irma created the type of actual devastation we fear because they hit close to home. The fear came to life, creating panic, anxiety, and uncertainty. It is hard to plan for a force majeure event such as a hurricane because of the capriciousness of Mother Nature. But, we need to do so from this point forward. No exception! And, I mean no exception!!
A force majeure event is an uncontrollable event that cannot be anticipated with any degree of definitiveness. The force majeure event will excusably delay or hinder performance obligations under a contract. One type of force majeure event is a hurricane—an uncontrollable and unforeseen act of Mother Nature.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Construction Defect Case Not Over, Despite Summary Judgment
November 07, 2012 —
CDJ STAFFThe Supreme Court of Oregon has concluded in an en banc decision that a motion to reconsider a summary judgment is not a motion for a new trial. In coming to their conclusion the court overturned an earlier Oregon Supreme Court case, Carter v. U.S. National Bank. Although the decision does not bear on construction defects, the underlying case did. Due to the decision, these claims can now be evaluated in a trial.
The case, Association of Unit Owners of Timbercrest Condominiums v. Warren, came about after an apartment complex was converted into condominium units. The developers hired Big Al’s Construction for some of the remodeling work. The condominium association later sued the developer and the contractor over claims of construction defects. The defendants filed a motion for summary judgment, which the court granted.
But that wasn’t the end of things. The plaintiff soon filed a “motion to reconsider,” noting that the summary judgment seemed to be in conflict with both law and other recent rulings, and additionally, the grounds for the decision were not in the order. The judge then notified the parties that the court had “pulled the trigger too quickly” and had seven questions for the parties to answer.
The court dismissed all claims against the defendants. The defendants filed their responses, objecting that that “‘there is no such thing’ as a motion for reconsideration.” Further, while “the rules do allow for post-judgment review of pre-judgment rulings through a motion for a new trial,” the plaintiffs had not filed for a new trial. But did they need one? They did file an appeal.
The judge in the case admitted that there was no such thing as a motion to reconsider, and felt bad about prematurely signing the judgment. The case was sent to the Court of Appeals to determine if the motion to reconsider was a request for a new trial. The Court of Appeals concurred.
In reviewing the decision, the Oregon Supreme Court concluded that there were a maximum of three questions to address. Was the motion for reconsideration a motion for a new trial? If so, was the later notice of appeal premature? And if so, was the plaintiff required to file a new appeal? The court determined that the answer to the first question was no.
Prior decisions pointed to the conclusion “that a motion for reconsideration of a summary judgment amounts to a motion for a new trial,” but here the court concluded that “our prior cases erred,” and turned to the summary judgment rule for clarification. The court noted that “the rule contemplates that summary judgment and trial are separate and distinct events.” With this conclusion, the Oregon Supreme Court remanded the case to the Court of Appeals for further proceedings.
Read the court decisionRead the full story...Reprinted courtesy of
No Repeal Process for Rejected Superstorm Sandy Grant Applications
February 12, 2014 —
Beverley BevenFlorez-CDJ STAFFEven though it’s been revealed that “faulty data” was used to reject many New Jersey recovery grants for victims of Superstorm Sandy, the state has announced that it’s too late to appeal, according to The Wall Street Journal.
“The applicants were informed by letter that they weren't eligible,” state officials told The Wall Street Journal, “and it should have been clear that they needed to appeal last year, so the application process won't be reopened.”
The majority of the rejected applicants that did appeal within the open period were found to be eligible for the grant: “Nearly 80% of people who appealed their rejections ended up winning their cases, according to data released by the Fair Share Housing Center, a public-interest law firm critical of the Christie administration. And of the 8,007 applicants rejected from both programs, 5,583 didn't appeal, or 70%, according to Fair Share Housing Center's analysis.”
U.S. Representative Bill Pascrell called for “an independent monitor” to be “appointed to oversee the state’s storm spending ‘to ensure there isn’t further mismanagement.’”
Read the court decisionRead the full story...Reprinted courtesy of
California Federal Court Finds a Breach of Contract Exclusion in a CGL Policy Bars All Coverage for a Construction Defect Action
July 19, 2021 —
Robert Dennison - Traub LiebermanThe Southern District of California published a decision in May 2021 in Associated Industries Ins. Co. v. Mt. Hawley Ins. Co., 2021 WL 1921016 (S.D. Cal. 5/12/21) concerning the scope of a breach of contract exclusion in a general liability insurance policy as applied to a construction defect action.
The suit was filed by Associated Industries Insurance Company against Mt. Hawley Insurance Company for equitable contribution for amounts spent to defend and indemnify the parties co-insured, referred to as JGCI in the decision. JGCI agreed to build a building for a third party pursuant to a written construction contract. The City of Davis issued a certificate of occupancy for the building on May 6, 2005. The City’s permits stated the building was final on that date. Mt. Hawley issued the first of several annual general liability insurance policies in September 2005.
Read the court decisionRead the full story...Reprinted courtesy of
Robert Dennison, Traub LiebermanMr. Dennison may be contacted at
rdennison@tlsslaw.com