Enforceability of Contract Provisions Extending Liquidated Damages Beyond Substantial Completion
April 15, 2024 —
Stu Richeson - The Dispute ResolverThis post takes a look at the enforceability of contract provisions providing for liquidated delay damages after substantial completion. Typically, the assessment of liquidated delay damages ends at substantial completion of a project. However, various standard form contracts, including some of the ConsensusDocs and EJCDC contracts, contain elections allowing for the parties to agree on the use of liquidated damages for failing to achieve substantial completion, final completion, or project milestones. The standard language in the AIA A201 leaves it up to the parties to define the circumstances under which liquidated damages will be awarded.
Courts are split on the enforceability of provisions that seek to assess liquidated damages beyond substantial completions. Courts in some jurisdictions will not impose liquidated damages after the date of substantial completion on the ground that liquidated damages would otherwise become a penalty if assessed after the owner has put the project to its intended use. Perini Corp. v. Greate Bay Hotel & Casino, Inc., 129 N.J. 479, 610 A.2d 364 (1992). When the terms are clear, other jurisdictions will enforce contract terms providing for liquidated damages until final completion, even if the owner has taken beneficial use of the facility. Carrothers Const. Co. v. City of S. Hutchinson, 288 Kan. 743, 207 P.3d 231 (2009).
Read the court decisionRead the full story...Reprinted courtesy of
Stu Richeson, PhelpsMr. Richeson may be contacted at
stuart.richeson@phelps.com
HOA Has No Claim to Extend Statute of Limitations in Construction Defect Case
October 28, 2011 —
CDJ STAFFThe California Court of Appeals ruled on September 20, 2011 in the case of Arundel Homeowners Association v. Arundel Green Partners, a construction defect case involving a condominium conversion in San Francisco. Eight years after the Notice of Completion was filed, the homeowners association filed a lawsuit alleging a number of construction defects, including “defective cabinets, waterproofing membranes, wall-cladding, plumbing, electrical wiring, roofing (including slope, drainage and flashings), fire-rated ceilings, and chimney flues.” Three years of settlement negotiations followed.
Negotiations ended in the eleventh year with the homeowners association filing a lawsuit. Arundel Green argued that the suit should be thrown out as California’s ten-year statute of limitations had passed. The court granted judgment to Arundel Green.
The homeowners then filed for a new trial and to amend its complaint, arguing that the statute of limitations should not apply due to the doctrine of equitable estoppel as Arundel Green’s actions had lead them to believe the issues could be solved without a lawsuit. “The HOA claimed that it was not until after the statute of limitations ran that the HOA realized Arundel Green would not keep its promises; and after this realization, the HOA promptly brought its lawsuit.” The trial court denied the homeowners association’s motions, which the homeowners association appealed.
In reviewing the case, the Appeals Court compared Arundel to an earlier California Supreme Court case, Lantzy. (The homeowners also cited Lantzy as the basis of their appeal.) In Lantzy, the California Supreme Court set up a four-part test as to whether estoppel could be applied. The court applied these tests and found, as was the case in Lantzy, that there were no grounds for estoppel.
In Arundel, the court noted that “there are simply no allegations that Arundel Green made any affirmative statement or promise that would lull the HOA into a reasonable belief that its claims would be resolved without filing a lawsuit.” The court also cited Lesko v. Superior Court which included a recommendation that the plaintiffs “send a stipulation?Ķextending time.” This did not happen and the court upheld the dismissal.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Insured's Expert Qualified, Judgment for Coverage Affirmed
December 15, 2016 —
Tred R. Eyerly – Insurance Law HawaiiAddressing a host of issues on appeal, the Texas Court of Appeals affirmed the trial court's judgment against the insurer for property damage caused by Hurricane Ike. Nat'l Sec. Fire & Cas. Co. v. Henriquez, 2016 Tex. App. LEXIS 11391 (Tex. Ct. App. Oct. 20, 2016), withdrawn and substituted by 2016 Tex. App. LEXIS 12766 (Tex. Ct. app. Dec. 1, 2016).
The insureds alleged property damage to their home caused by the hurricane. The roof was damaged, resulting in interior water damage. Sheetrock, exterior bricks, windows, walls cabinets and insulation throughout the entire home were damaged. The insureds also alleged that the home shifted during the storm, causing the foundation to not be level and the ceilings and walls to crack. Personal property within the dwelling was also damaged.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
MTA’S New Debarment Powers Pose an Existential Risk
July 15, 2019 —
Steven M. Charney, Gregory H. Chertoff & Paul Monte - Peckar & Abramson, P.C.The normal project and contractual risks faced by contractors, consultants and suppliers to the Metropolitan Transportation Authority are considerable. A new law and regulations mandating that the MTA debar contractors, consultants and suppliers for unexcused schedule and cost overruns creates a new and unfair existential risk.
The new law, Public Authorities Law Section 1279-h, slipped into the New York State budget bill and passed without public comment, was enacted on April 12, 2019. Implementing regulations were issued on June 5, 2019, and mandate that the MTA debar contractors (defined to include consultants, vendors and suppliers) if they: (1) fail to achieve substantial completion of their contractual obligations within 10% of the adjusted contract time; or (2) present claims for additional compensation that are denied in an amount that exceeds the total adjusted contract amount by 10% or more.[1]
To say that your business and your livelihood are at risk is not an overstatement. The MTA umbrella includes the New York City Transit Authority, MTA Capital Construction, Bridges & Tunnels, Long Island Railroad and Metro North, among others. A debarment by one of these authorities will lead to a debarment by all of them, and then to a debarment by all New York State agencies and authorities,[2] and possibly debarment across state lines. Public and major private owners, as part of their RFP and procurement processes, routinely inquire regarding a bidding contractor’s debarment history.
The risk is to new contracts and, because the MTA has decided to give retroactive effect to the law and regulations, to contracts that are already ongoing (even though these risks could not have been considered, priced or agreed to by contractors or their sureties).
Reprinted courtesy of Peckar & Abramson, P.C. attorneys
Steven M. Charney,
Gregory H. Chertoff and
Paul Monte
Mr. Charney may be contacted at scharney@pecklaw.com
Mr. Chertoff may be contacted at gchertoff@pecklaw.com
Mr. Monte may be contacted at pmonte@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Tarriffs, a Pandemic and War: Construction Contracts Must Withstand the Unforeseeable
May 16, 2022 —
Brett Moritz, Adrian Bastianelli III & Adam Handfinger - Construction ExecutiveSince the tariffs on steel and the first wave of the COVID-19 pandemic, the construction industry has been reeling from the impact of material shortages and price increases, labor shortages, breakdowns in the supply chain and the inflationary effect of these issues. Unfortunately, the war in Ukraine has only exacerbated the situation.
International conflicts can constrain supply, resulting in delays and price increases for contractors, subcontractors and suppliers. The disruption caused by the war is expected to be particularly acute due to the role that Russia and Ukraine play in the world economy and the effect of the economic sanctions that have been imposed on Russia by the United States and other countries. Russia controls approximately 10% of the global copper reserves and is estimated to produce about 10% of the world’s nickel supply. It also provides at least 30% of Europe’s oil and natural gas. Ukraine is a significant source of raw materials, such as iron. Thus, the war will cause significant shortages and price increases to the global construction industry. There are already reports of delays and cost increases for commodities such as nickel, aluminum, copper and—most importantly—steel, which have resulted in impacts to construction costs and schedules. Suppliers are especially sensitive to the volatile markets caused by these conditions. Some are insisting on automatic price increases in their purchase orders.
All of this, not to mention the anticipation of what may come next, points to the necessity for a new paradigm to achieve a successful project. It is more important today than ever that owners, contractors, subcontractors and suppliers reasonably address the economic and time impacts of these unforeseeable events in preparing contracts for future work and in administering existing contracts. Otherwise, the risk of a default on more than one level may put projects in jeopardy, to no one’s benefit.
Reprinted courtesy of
Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Contract Not So Clear in South Carolina Construction Defect Case
November 07, 2012 —
CDJ STAFFThe South Carolina Court of Appeals has reversed a partial summary judgment issued by one of the lower courts in the case of The Retreat at Edisto Co-Owners Association v. The Retreat at Edisto. The underlying issues of the case deal with a construction defect complaint.
The lower court had concluded “Developer’s ‘First Amendment’ to the Master Deed required the Developer to satisfy the provision in the paragraph labeled ‘Master Deed Amendment or Phase II’ as a condition precedent to its election to proceed with the development of Phase II.”
The appeals court found that “the language of the First Amendment to the Master Deed is susceptible to more than one interpretation.” The court additionally concluded that the “Developer presented the requisite scintilla of evidence on the question of its intent in order to establish a genuine issue of material fact. As the material facts were in dispute, the appeals court reversed the summary judgment and remanded the case to the circuit court for further proceedings.
Read the court decisionRead the full story...Reprinted courtesy of
Workers Hurt in Casino Floor Collapse
February 10, 2012 —
CDJ STAFFMore than a dozen construction workers fell about thirty feet when a floor collapsed in a Cincinnati casino. The workers were pouring cement on the second-floor level when the accident happened. The area in question will be the gaming area in the completed casino. Scott Allen, OSHA’s regional spokesperson, said their investigation of the accident would probably take about a month to complete.
The cause of the collapse is still undetermined. Although the weather has been wet in the area, experts thought it unlikely to be the cause. A construction forensics professor at Ohio State University said that “concrete pouring is very common” and that “you cannot go wrong unless something happens with the connection.” Engineering experts said it was more likely an issue with the metal decking.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Navigating the Construction Burrito: OCIP Policies in California’s Construction Defect Cases
November 16, 2023 —
Alexa Stephenson & Ivette Kincaid - Kahana FeldIn the early 2000’s, Owner-Controlled Insurance Programs (OCIP) or WRAPS, were traditionally used in large commercial projects of over $50 million in construction costs. As construction defect lawsuits became more prevalent, subcontractors found themselves unable to meet the insurance requirements of their contracts with developers and general contractors because they could not find insurance companies that were willing to insure the risk. This presented a problem for developers and general contractors and left them with no option but to look into new insurance products that would insure them and all subcontractors who worked on the project. OCIPs became in some instances the only insurance option for developers, general contractors, and subcontractors to build single-family or multi-family projects in California and other western states.
OCIPS or WRAPS, often likened to the layers of a savory burrito, offer both enticing benefits and potential pitfalls. Just as a burrito’s ingredients can harmonize or clash, OCIP policies can shape the outcome of legal battles, impacting contractors, developers, and insurers alike.
Pros – Savoring the OCIP Burrito:
1. Wrapped Protection: Much like a well-folded burrito envelops its contents, OCIP policies offer comprehensive coverage for construction projects. Developers, general contractors, and subcontractors find comfort in knowing that their liability risks are bundled into a single policy, ensuring all enrolled parties have coverage in the event of a claim.
Reprinted courtesy of
Alexa Stephenson, Kahana Feld and
Ivette Kincaid, Kahana Feld
Ms. Stephenson may be contacted at astephenson@kahanafeld.com
Ms. Kincaid may be contacted at ikincaid@kahanafeld.com
Read the court decisionRead the full story...Reprinted courtesy of