Understand and Define Key Substantive Contract Provisions
March 23, 2020 —
Phillip L. Sampson Jr. & Richard F. Whiteley, Construction ExecutiveThe following contract provisions should be clearly understood before undertaking any construction project commences.
Force Majeure
Often referred to as an “Act of God,” a force majeure is an event, typically beyond the parties’ control, that prevents performance under a contract. To determine if a contractor need a force majeure clause in its contract, it should ask whether there may be instances where events beyond the contractor’s control could impact its contractual performance? If so, it will want this clause.
Courts currently treat force majeure as an issue of contractual interpretation, focusing on the express language in the contract. Consequently, the scope and applicability of a force majeure clause depends on the contract’s terms. Using broad language in a force majeure clause may help protect against unforeseen events. But to the extent possible, parties should describe with particularity the circumstances intended to constitute a force majeure.
The law relating to force majeure also fairly consistently provides that parties cannot avoid contractual obligations because performance has become economically burdensome. Courts have refused to apply force majeure clauses where an event only affects profitability. Recent attempts to categorize tariffs on construction materials as a force majeure have failed. Unless a tariff or tax is specifically listed as a force majeure event, it is unlikely to constitute a force majeure because it only affects profitability.
Reprinted courtesy of
Phillip L. Sampson Jr. & Richard F. Whiteley, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Disappointment on an Olympian Scale After Rio 2016 Summer Games
February 23, 2017 —
Augusto Diniz, O Empreiteiro - Engineering News-RecordThe single word to describe the sports infrastructure created for the Rio 2016 Olympic Games is abandonment. Uncertainty over the future of the dilapidated sports stadiums and arenas threatens the legacy of the Olympics, which ended five months ago.
Read the court decisionRead the full story...Reprinted courtesy of
Augusto Diniz, O Empreiteiro, ENRENR may be contacted at
ENR.com@bnpmedia.com
Chicago Aldermen Tell Casino Bidders: This Is a Union Town
June 13, 2022 —
Shruti Singh - BloombergSeveral Chicago aldermen on Monday sent gaming companies that are bidding on building the city’s first casino a message: this is a union town.
During a special casino committee of the city council hearing on Monday, the aldermen expressed concerns that the three bidders -- Bally’s Corp., Hard Rock International and Rush Street Gaming -- that are seeking to construct and operate a gaming and entertainment complex don’t have a deal with local labor groups. Chicago Chief Financial Officer Jennie Bennett said during the hearing that a deal with labor was part of the requirements laid out in the city’s request for proposals.
None of the three bidders have committed to labor standards, and moving forward without an agreement on items such as a living wage “is a slap in the face,” Robert Reiter Jr., president of the Chicago Federation of Labor, said during the public testimony portion of the meeting. The federation represents 300 affiliated unions and their half a million members.
Read the court decisionRead the full story...Reprinted courtesy of
Shruti Singh, Bloomberg
SCOTUS Opens Up Federal Courts to Land Owners
July 15, 2019 —
Wally Zimolong - Supplemental ConditionsFor nearly 36 years, the United States Supreme Court’s decision in Williamson County Regional Planning Commission v. Hamilton Bank of Johnson City, 473 U.S. 172, 105 S.Ct. 3108, 87 L.Ed.2d 126 (1985) severely frustrated, if not all but foreclosed, a property owner’s right to bring a claim in federal court based on a regulatory taking. Under the Fifth Amendment, a property owner whose land has been “taken” by the government is entitled to just compensation. There are two types of takings direct or “inverse” or regulatory takings. A direct taking is where the government declares that it needs your land for public use and offers to pay you compensation. You might disagree with the amount offered – and that often is the case. But, a mechanism exists whereby a neutral third party – a condemnation board – will arrive at the compensation that is owed. On the other hand, an inverse condemnation or regulatory taking occurs when the government takes some action that restricts the use of the land in such a way as to severely impact it beneficial economic use. For example, if you own a strip of commercial property and intend to develop it and then the municipality comes along and suddenly changes the zoning classification of the parcel such that you can no longer develop it in a beneficial way, then you might have a regulatory takings case.
Under the Court’s Williamson County decision, property owners falling within the later category were required to exhaust state remedies before proceeding to federal court under a claim that their Fifth Amendment rights were violated. The problem with this is that, as the Supreme Court explained, it creates a Catch-22. If property owners exhaust their state remedies and the state remedies result in an unfavorable outcome, the federal court is powerless to overturn that decision under the doctrines of res judicata and the full faith and credit clause of the Constitution.
Well, yesterday, the Court overturned Williamson County, in Knick v. Township of Scott, 588 U.S. _____ (2019). There the Court held unequivocally a “property owner has suffered a violation of his Fifth Amendment rights when the government takes his property without just compensation, and therefore may bring his claim in federal court under Section 1983 at that time.”
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Defining Construction Defects
February 04, 2013 —
CDJ STAFFJoseph M. Junfola has started a series at PropertyCasualty360.com on construction defect, and as is appropriate with an in-depth look, he starts by defining the central terms. What is a construction defect? What is a construction defect claim?
Junfola notes that "there is no one uniform definition in all jurisdictions," and so he looks at the commonalities to "fashion at least a working definition." Nevada says that a construction defect "includes a defect in the design, construction, manufacture, repair or landscaping of a new residence, of an alteration of or an addition to an existing residence, or of an appurtenance." According to Florida it is "a deficiency in, or a deficiency arising of, the design, specifications, surveying, planning, supervision, observation of construction, or construction, repair, alteration, or remodeling of real property."
He continues that a construction defect claim is "a claim for damages, i.e. money, arising out of a defect in construction, including defective design, faulty workmanship, and defective materials," but he notes that this is typically pursuant to the discovery of the problem within a given time.
Read the court decisionRead the full story...Reprinted courtesy of
Beam Fracture on Closed Mississippi River Bridge Is at Least Two Years Old
May 31, 2021 —
Jim Parsons - Engineering News-RecordThe Arkansas Dept. of Transportation (ARDOT) has terminated the employee responsible for inspecting the Interstate-40 Mississippi River bridge after two-year-old drone footage revealed the presence of a tie-beam fracture that forced
last week’s emergency shutdown.
Reprinted courtesy of
Jim Parsons, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
Residential Interior Decorator Was Entitled to Lien and Was Not Engaging in Unlicensed Contracting
August 04, 2021 —
David Adelstein - Florida Construction Legal UpdatesResidential construction disputes can sometimes take nasty turns. This is not attributed to one specific reason, but a variety of factors. Sometimes, there are not sophisticated contracts (or contracts at all). Sometimes, relationships and roles get blurred. Sometimes, parties try to skirt licensure requirements. Sometimes, a party is just unreasonable as to their expectations. And, sometimes, a party tries to leverage a construction lien to get what they want. In all disputes, a party would certainly be best suited to work with construction counsel that has experience navigating construction disputes.
An example of a construction dispute that took a nasty turn involving an interior decorator is SG 2901, LLC v. Complimenti, Inc., 2021 WL 2672295 (Fla. 3d DCA 2021). In this case, a condominium unit owner wanted to renovate his apartment. He hired an interior decorator to assist. As his renovation plans became more expansive, the interior decorator told him he would need to hire a licensed contractor and architect. The interior decorator arranged a meeting with those professionals and, at that meeting, they were hired by the owner and told to deal directly with the interior decorator, almost in an owner’s representative capacity since the owner traveled a lot. The interior decorator e-mailed the owner about status and requested certain authorizations, as one would expect an owner’s representative to do. At the completion of the renovation job, the owner did not pay the interior decorator because he was unhappy with certain renovations. The interior decorator recorded a construction lien and sued the owner which included a lien foreclosure claim. There was no discussion of the contracts in this case because, presumably, contracts were based on proposals, were bare-boned, or were oral.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Approaching Design-Build Projects to Avoid (or Win) Disputes
August 07, 2023 —
Stuart Eisler - Construction ExecutiveStakeholders engage in design-build projects believing the collaborative nature better aligns parties' interests and reduces overall risk exposure. Each of the lead parties bases this belief on different factors—the owner sees an opportunity to reduce change-order exposure and improve delivery times, the design-builder (or contractor) aims to control design volatility by ensuring project components match budgeted projections, and the designer intends to benefit by greater constructability review from the design-builder team and often additional time to detail designs. Rarely do design-build parties contemplate claims arising while initiating a project.
This being said, design-build projects carry unique, inherent risks due to the award of often fixed-price contracts utilizing incomplete, preliminary designs. As scopes creep and costs balloon, previously harmonious parties experience discord and lurking claims. While the majority of design-build projects are completed without major dispute, there are strategies available to further avoid disputes and prevail in those that are unavoidable.