When Does a Claim Against an Insurance Carrier for Failing to Defend Accrue?
November 07, 2012 —
David McLain, Colorado Construction LitigationThe following is an update on our December 20, 2010 article regarding United States Fire Insurance Company v. Pinkard Construction Company, Civil Action No. 09-CV-01854-MSK-MJW, and its underlying dispute, Legacy Apartments v. Pinkard Construction Company, Case No. 2003 CV 703, Boulder County Dist. Ct. That article can be found here.
The present action, St. Paul Fire and Marine Insurance Co., et al. v. The North River Insurance Co., et al., Civil Action No. 10-CV-02936-MSK-CBS, encompasses the coverage battle that ensued between Pinkard’s insurers, Travelers Indemnity Company of America (“Travelers”) and United States Fire Insurance Company (“USFI”), following the settlement of Legacy’s construction defect claims against Pinkard. A short history of the underlying facts is as follows:
In 1995, Pinkard constructed the Legacy Apartments housing complex in Longmont, Colorado. Following construction, Legacy notified Pinkard of water leaks associated with various elements of construction. Legacy ultimately filed suit against Pinkard in 2003, and would go on to clarify and amend its defect claims in 2004, 2006, and again in 2008. Following Pinkard’s notification of Legacy’s claims, USFI provided a defense to Pinkard, but Travelers refused to do so, on the purported basis that Legacy’s allegations did not implicate property damage under the terms of Travelers’ policy.
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain can be contacted at
mclain@hhmrlaw.com
Construction Defects as Occurrences, Better Decided in Law than in Courts
December 09, 2011 —
CDJ STAFFConstruction defect claims are now occurrences for insurance purposes in four states, Arkansas, Colorado, Hawaii, and South Carolina, yet there are still frustrations for commercial general liability policyholders. Business Insurance describes court decisions on whether construction defect claims are covered as “incongruous,” and this drives up coverage and litigation costs. Construction firms often find they are defending themselves on two fronts, both the construction defect claim and also whether their insurance covers it.
Frank Armstrong, the Senior Vice President and National Director of Construction Claims for Willis North America says that the problem starts with the word “occurrence,” as various state courts have different interpretations of the word. “Certain pieces of it don’t fit well, at lest according to some courts in the country, with coverage for construction defect risks.”
Another insurance executive, Julian Ehlich, the Senior Vice President of Claims for Aon Risk Solutions’ construction services group notes that “jurisdictions differ, so policyholders don’t know what they’re going to get.”
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Terms of Your Teaming Agreement Matter
July 30, 2019 —
Christopher G. Hill - Construction Law MusingsThese days in construction, and other pursuits, teaming agreements have become a great method for large and small contractors to work together to take advantage of various contract and job requirements from minority participation to veteran ownership. With the proliferation of these agreements, parties must be careful in how they draft the terms of these agreements. Without proper drafting, the parties risk unenforceability of the teaming agreement in the evewnt of a dispute.
One potential pitfall in drafting is an “agreement to agree” or an agreement to negotiate a separate contract in the future. This type of pitfall was illustrated in the case of InDyne Inc. v. Beacon Occupational Health & Safety Services Inc. out of the Eastern District of Virginia. In this case, InDyne and Beacon entered into a teaming agreement that provided that InDyne as Prime would seek to use Beacon, the Sub, in the event that InDyne was awarded a contract using Beacon’s numbers. The teaming agreement further provided:
The agreement shall remain in effect until the first of the following shall occur: … (g) inability of the Prime and the Sub, after negotiating in good faith, to reach agreement on the terms of a subcontract offered by the Prime, in accordance with this agreement.
InDyne was subsequently awarded a contract with the Air Force and shortly thereafter sent a subcontract to Beacon and requested Beacon’s “best and final” pricing. Beacon protested by letter stating that it was only required to act consistently with its original bid pricing. Beacon then returned the subcontract with the original bid pricing and accepting all but a termination for convenience provision. Shortly thereafter, InDyne informed Beacon that InDyne had awarded the subcontract to one of Beacon’s competitors. Beacon of course sued and argued that the teaming agreement required that InDyne award the subcontract to Beacon.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Colorado Senate Committee Approves Construction Defect Bill
March 19, 2015 —
Jesse Howard Witt – Acerbic WittLate last night, the Colorado Senate Business, Labor, and Technology Committee voted to refer
SB 15-177 to the committee of the whole. The vote followed nearly seven hours of testimony from those in favor of construction defect legislation and those opposed.
As I have
previously discussed, the bill sponsors have argued that their measure will encourage the construction of more affordable housing by giving builders de facto immunity for claims of defective workmanship and property damage in common interest communities. The bill achieves this by establishing difficult voting and disclosure requirements for homeowner associations and requiring costly, private arbitration of any disputes that can overcome the procedural hurdles. During the recent hearing, proponents echoed these statements and testified that insulating homebuilders from claims would lower home prices and rents by increasing the supply of cheaply-built condominiums.
Opponents questioned whether the bill contained any provisions that would actually help the affordable housing market. They also argued that it was improper for the legislature to shift the cost of fixing construction defects onto those homeowners who can least afford to pay for necessary repairs.
Read the court decisionRead the full story...Reprinted courtesy of
Jesse Howard Witt, The Witt Law FirmMr. Witt welcomes comments at www.acerbicwitt.com
Not Remotely Law as Usual: Don’t Settle for Delays – Settle at Remote Mediation
May 25, 2020 —
Victor J. Zarrilli, Robert G. Devine & Michael W. Horner - White and Williams LLPThe emergence and rapid spread of COVID-19 has created extraordinary circumstances that have significantly impacted how we go about living, working and interacting with one another. The practice of law is no exception.
While most cases have been postponed and some extended indefinitely, the issues and disputes that first triggered the litigation remain. In fact, the burdens created by social distancing and other responses to the COVID-19 outbreak have served to only increase these disputes and create an urgent need in some for quick resolution.
In our previous article, we summarized some of the best practices that should be applied when taking and defending depositions in a remote, virtual setting. That technology can also offer the same benefits for alternative dispute resolutions. If planned properly, the use of technology allows remote mediations to be conducted as seamlessly as in-person mediations and, in some circumstances, affords additional benefits that can achieve the best possible resolution for all sides.
This article summarizes the opportunities technology has created by which parties can attempt to resolve their disputes through alternative dispute resolution methods, even in a time of social distancing.
Reprinted courtesy of White and Williams LLP attorneys
Victor J. Zarrilli,
Robert G. Devine and
Michael W. Horner
Mr. Zarrilli may be contacted at zarrilliv@whiteandwilliams.com
Mr. Devine may be contacted at deviner@whiteandwilliams.com
Mr. Horner may be contacted at hornerm@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
White House Seeks $310M To Fix Critical San Diego Wastewater Plant
December 04, 2023 —
James Leggate - Engineering News-RecordThe Biden administration’s $55.9-billion
supplemental funding request to Congress for disaster response and other issues includes $310 million for a project to repair and expand the ailing South Bay International Wastewater Treatment Plant in San Diego, Calif. The plant is part of a
repeatedly overwhelmed wastewater treatment system on the U.S.-Mexico border that has allowed untreated sewage flows to foul area beaches.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
California Case That Reads Like Russian Novel Results in Less Than Satisfying Result for Both Project Owner and Contractors
May 01, 2019 —
Garret Murai - California Construction Law BlogSometimes you can see a train wreck coming a mile away. The next case, Design Built Systems v. Sorokine, Court of Appeal for the First District, Case Nos. A151264 and A152059 (February 26, 2019), is one of those cases. It also happens to read like a Tolstoy novel.
The Beginning of the Train Wreck
Alexei Sorokine and Elena Koudriavtseva, husband and wife, owned a single family home in San Rafael, California. Sorokine had acquired the house prior to his marriage to Koudriavtseva. In 2010, he traveled to Russia and, for reasons unexplained, has not been able to return.
Following a landslide on the property in 2006, Sorokine entered into a construction contract with Design Built Systems to design and build a series of retaining walls. DBS was also retained to remedy a stop work notice issued by the City of San Rafael following work performed by others.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel RosenMr. Murai may be contacted at
gmurai@wendel.com
1st District Joins 2nd District Court of Appeals and Holds that One-Year SOL Applies to Disgorgement Claims
June 14, 2021 —
Garret Murai - California Construction Law BlogWe’re beginning to see a trend.
This past year, the 2nd District Court of Appeals, in Eisenberg Village of the Los Angeles Jewish Home for the Aging v. Suffolk Construction Company, 53 Cal.App.5th 1201 (2020), held for the first time that a one (1) year statute of limitations period beginning upon substantial completion of a project applies to disgorgement claims under Business and Professions Code section 7031. In San Francisco CDC LLC v. Webcor Construction L.P., the 1st District Court of Appeals became the second Court of Appeals in the state to hold that a one (1) year statute of limitations beginning upon completion or cessation of work on a project applies to disgorgement claims under Business and Professions Code section 7031.
The San Francisco CDC LLC Case
The Defect Action
In September 2005, San Francisco CDC LLC entered into a $144 million construction contract with Webcor Construction, Inc. doing business as Webcor Builders to build the InterContinental Hotel in San Francisco, California.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com