Enforcement Of Contractual Terms (E.G., Flow-Down, Field Verification, Shop Drawing Approval, And No-Damage-For-Delay Provisions)
May 04, 2020 —
David Adelstein - Florida Construction Legal UpdatesWhat you contractually agree to matters, particularly when you are deemed a sophisticated entity. This means you can figuratively live or die by the terms and conditions agreed to. Don’t take it from me, but it take it from the Fourth Circuit’s decision in U.S. f/u/b/o Modern Mosaic, Ltd. v. Turner Construction Co., 2019 WL 7174550 (4th Cir. 2019), where the Court started off by stressing, “One of our country’s bedrock principles is the freedom of individuals and entities to enter into contracts and rely that their terms will be enforced.” Id. at *1.
This case involved a dispute between a prime contractor and its precast concrete subcontractor on a federal project. The subcontractor filed a Miller Act payment bond lawsuit. The trial court ruled against the subcontractor based on…the subcontract’s terms! So, yes, what you contractually agree to matters.
Example #1 – The subcontractor fabricated and installed precast concrete panels per engineering drawings. However, the parking garage was not built per dimensions meaning the panels it fabricated would not fit. The subcontractor had to perform remedial work on the panels to get them to fit. The subcontractor pursued the prime contractor for these costs arguing the prime contractor should have field verified the dimensions. The problem for the subcontractor, however, was that the subcontract required the subcontractor, not the prime contractor, to field verify the dimensions. Based on this language that required the subcontractor to field verify existing conditions and take field measurements, the subcontractor was not entitled to its remedial costs (and they were close to $1 Million). Furthermore, and of importance, the Court noted that the subcontract contained a flow down provision requiring the subcontractor to be bound by all of the terms and conditions of the prime contract and assume those duties and obligations that the prime contractor was to assume towards the owner. While this flow-down provision may often be overlooked, here it was not, as it meant the subcontractor was assuming the field verification duties that the prime contractor was responsible to perform for the owner.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Ignoring Employee ADA Accommodation Requests Can Be Costly – A Cautionary Tale
March 29, 2021 —
Peter Shapiro - Lewis BrisboisAs all employers should well know by now, the Americans with Disabilities Act (ADA) and many state and local counterparts may require employers to engage in an interactive process in response to a disabled employee’s request for a workplace accommodation. A recent ruling by the First Circuit Court of Appeals illustrates why employers have a very strong financial incentive to be proactive in adopting and rigorously enforcing their disability accommodation policies.
In Burnett v. Ocean Properties, decided on February 2, 2021, a wheelchair user employed by a hotel chain call center complained internally that the office’s entrance was not accessible to him. It had heavy doors beyond which was a downward slope that caused the plaintiff’s wheelchair to roll backwards as the door closed on him, requiring him to exert greater force as he struggled to enter. He asked that push-button automatic doors be installed. The employer did not take any meaningful steps to address the complaint with the plaintiff. Eventually he was injured as he tried to open the door. Still, the employer did not follow up on his accommodation request. The plaintiff eventually filed an administrative charge with the Maine Human Rights Commission. The employer met with the plaintiff at that time, but claimed lack of familiarity with ADA compliance requirements and took no action to address the complaint. The plaintiff eventually resigned and filed suit in federal court when the administrative process was completed.
Read the court decisionRead the full story...Reprinted courtesy of
Peter Shapiro, Lewis BrisboisMr. Shapiro may be contacted at
Peter.Shapiro@lewisbrisbois.com
COVID-19 Business Interruption Lawsuits Begin: Iconic Oceana Grill in New Orleans Files Insurance Coverage Lawsuit
April 20, 2020 —
Jeffrey J. Vita & William S. Bennett - Saxe Doernberger & Vita, P.C.On Monday, the iconic New Orleans restaurant, Oceana Grill, filed the first Coronavirus-related business interruption insurance coverage lawsuit in a US jurisdiction. The declaratory judgment action styled Cajun Conti, LLC, et. al. d/b/a Oceana Grill v. Certain Underwriters at Lloyd’s, London was filed in Louisiana state court for the Parish of Orleans. As a direct result of the government-mandated closures and restrictions on public gatherings implemented by the City of New Orleans and State of Louisiana, Oceana Grill’s petition anticipates a significant loss of business income.
Based on allegations in the petition, there are several aspects of Oceana Grill’s policy that make this a good test case for business interruption coverage stemming from the Coronavirus. Although the specific policy language is not quoted in the petition, coverage provisions are categorically identified throughout.
As a preliminary matter, the policy at issue appears to be written on an “all risks” basis, meaning the insuring agreement of the policy would likely be triggered generally by all risks of “physical loss or damage” unless specifically excluded. This basis for coverage, which is common in property policies, is advantageous to policyholders, as it limits the insured’s burden of proof to establishing that there was physical loss or damage while leaving the burden of applying any more specific exclusion to the insurance company.
Reprinted courtesy of
Jeffrey J. Vita, Saxe Doernberger & Vita, P.C. and
William S. Bennett, Saxe Doernberger & Vita, P.C.
Mr. Vita may be contacted at jjv@sdvlaw.com
Mr. Bennett may be contacted at wsb@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Labor Under the Miller Act And Estoppel of Statute of Limitations
May 08, 2023 —
David Adelstein - Florida Construction Legal UpdatesIf you want a case that goes into history of the federal Miller Act, check out the Fourth Circuit Court of Appeal’s opinion in U.S. ex rel. Dickson v. Fidelity and Deposit Company of Maryland, 2023 WL 3083440 (4th Cir. 2023). While I am not going to delve into this history, it’s a worthwhile read. It is also a worthwhile read for two other points.
First, it discusses what constitutes “labor” under the Miller Act.
Second, it discusses doctrine of estoppel to prevent a surety from raising the statute of limitations to bar a Miller Act payment bond claim, which is a doctrine you do NOT want to rely on, as this case reinforces.
Both of these points applicable to Miller Act claims are discussed below.
This case dealt with a prime contractor renovating staircases that was terminated by the federal government. The prime contractor hired a professional engineer as its subcontractor to serve as its project manager and supervise labor on the project. The engineer/subcontractor also had “logistical and clerical duties, taking various field measurements, cleaning the worksite, moving tools and materials, and sometimes even watering the concrete himself.” Dickson, supra, at *1.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
VOSH Jumps Into the Employee Misclassification Pool
February 23, 2016 —
Christopher G. Hill – Construction Law MusingsThe proper classification of workers by construction companies has been on the radar of the Department of Labor for both the US and Virginia governments for quite a while. While most of the misclassification is innocent and not done to create issues, there have been enough instances of purposeful misclassification of certain workers as independent contractors (thus avoiding workers comp and other payroll expenses) that innocent contractors have born the brunt of these issues through increased payroll costs over those that misclassify (in the form of necessarily higher bids, higher overhead, etc.).
As an additional deterrent to improper classification of workers, the Virginia Department of Labor and Industry has issued guidelines for what will occur in Virginia Department of Safety and Health (VOSH) cases.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
What You Need to Know to Protect the Project Against Defect Claims
October 28, 2024 —
Scott L. Baker - Los Angeles Litigation BlogIf a property owner claims there is a construction defect, that not only brings the project’s integrity into question but also your business’s reputation. So, how can you take steps to prevent these claims from causing such damage?
Here are three things to know before beginning a project to effectively protect it and
manage construction defect claims.
1. Documentation is key
California and Los Angeles County require certain permits and documents in order for a construction project to move forward. Los Angeles County
will also conduct plan checks to ensure everything is up to code. Detailed documentation will be important while making your plans.
However, keeping notes throughout every step of the project will also be essential. Documenting all aspects of the project helps you:
- Stay updated and aware of the project’s progress
- Proactively catch and handle issues that could result in disputes
- Create a record of evidence that can help manage defect claims
Read the court decisionRead the full story...Reprinted courtesy of
Scott L. Baker, Baker & AssociatesMr. Baker may be contacted at
slb@bakerslaw.com
Colorado homebuilders target low-income buyers with bogus "affordable housing" bill
March 05, 2015 —
Jesse Howard Witt – Acerbic Witt“Affordable housing” is the latest catchphrase for Colorado homebuilders seeking immunity from warranty claims and repair requests.
In 2013, the homebuilders’ lobby said it was about public transportation. In 2014 they said it was about community building. Now it’s 2015, and the lobbyists are claiming that a lack of affordable housing is the reason why politicians should eliminate consumer protections for homebuyers.
The Colorado Senate recently announced the introduction of SB 15-177. If passed, the bill will make it illegal for homeowner associations to hire construction experts or lawyers unless they can first satisfy a complicated disclosure and voting process. Although sponsors portray the bill as an innocuous measure that merely requires more community involvement, its provisions have actually been tailored to take advantage of recent court decisions that make it difficult for homeowner associations to vote on measures outside of a meeting or act quickly to resolve construction defect disputes. The intent is to make it nearly impossible for homeowners to retain construction experts or legal representation before the statute of limitations period expires, thereby making homebuilders immune from any potential claims. The bill will also eliminate the right to a jury trial in many cases, forcing any disputes that overcome the procedural hurdles into costly, private arbitration proceedings. The sponsors argue that these measures are necessary to encourage builders to erect more cheap condominiums.
Read the court decisionRead the full story...Reprinted courtesy of
Jesse Howard Witt, The Witt Law FirmMr. Witt welcomes comments at www.acerbicwitt.com
New York Appellate Team Obtains Affirmance of Dismissal of Would-Be Labor Law Action Against Municipal Entities
August 12, 2024 —
Lewis Brisbois NewsroomNew York, N.Y. (July 11, 2024) - In Charlot v. City of New York, ___ A.D.3d ___, 2024 NY Slip Op 03161 (2d Dep’t 2024), New York Associate Dean Pillarella, a member of the Appellate Practice, recently obtained an affirmance of the lower court’s dismissal of the plaintiff’s action against the City of New York (“the City”) for failure to timely serve a notice of claim. New York Partner Meghan Cavalieri, a member of the Construction Practice, and her team authored and argued the initial motion to dismiss.
The plaintiff alleged to have sustained injuries as a result of a construction-site accident on December 8, 2020, on City-owned property in the course of the construction of a school by the New York City School Construction Authority. N.Y. General Municipal Law (“GML”) § 50-e(1)(a), requires service of a notice of claim within 90 days after the claim arises as a condition precedent to the commencement of a tort action. The plaintiff served no notice of claim until June 2021 and commenced an action in January 2022, alleging violations of N.Y. Labor Law §§ 240(1), 241(6), and 200. Given the plaintiff’s failure to comply with GML § 50-e(1)(a), Meghan and her team rejected the notices of claim as untimely. The plaintiff then moved for leave to deem the notices of claim timely served nunc pro tunc. In response, Meghan and her team opposed the motion and cross-moved to dismiss the action.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois