NJ Transit’s Superstorm Sandy Coverage Victory Highlights Complexities of Underwriting Property Insurance Towers
February 24, 2020 —
Traub LiebermanIn New Jersey Transit Corp. v. Certain Underwriters at Lloyd’s, London, 2019 WL 6109144 (N.J. App. Div. Nov. 18, 2019), New Jersey Transit (“NJT”) defeated the claim of several of its insurers that a $100 million flood sublimit applied to its Superstorm Sandy damages and recovered the full $400 million limits of its property insurance tower. The decision is a big win for the beleaguered transit agency, and for insurance professionals working with complex insurance towers, the decision highlights critical underwriting issues that can dramatically affect the amount of risk transferred by the policyholder or assumed by the insurer.
In NJ Transit, NJT secured a multi-layered property insurance program providing $400 million in all-risk coverage. The first and second layers provided $50 million each, the third and fourth layers provided $175 million and $125 million, respectively, with several insurers issuing quota shares in each layer. The program contained a $100 million flood sublimit, and “flood” was defined to include a “surge” of water. The program did not contain a sublimit for damage caused by a “named windstorm,” which was defined to include “storm surge” associated with a named storm. After NJT made its Superstorm-Sandy claim, some of the third- and fourth-layer insurers advised NJT that the $100 million flood sublimit applied to bar coverage under their policies. NJT sued these excess insurers and won at the trial and appellate levels.
In holding that the $100 million flood sublimit did not apply, the court applied the rule of construction that the specific definition of “named windstorm,” which included the terms “storm surge” and “wind driven water,” controlled over the policies’ more general definition of “flood.” In ascertaining the parties’ intent, the court noted that the omission of the term “storm surge” in the definition of “flood” evidenced an intention that the flood sublimit would not apply to storm surges. Based on this finding, the court rejected several arguments made by the insurers that other policy provisions evidenced the parties’ intent to apply the flood sublimit to all flood-related losses, regardless of whether the loss was caused by a storm surge.
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman
Quick Note: Discretion in Determining Prevailing Party for Purposes of Attorney’s Fees
January 25, 2021 —
David Adelstein - Florida Construction Legal UpdatesIn prior articles I have discussed that courts apply the significant issues test to determine the prevailing party for purposes of being entitled to attorney’s fees. A party that recovers an affirmative judgement is NOT the de facto prevailing party for purposes of an entitlement to attorney’s fees in a breach of contract action (or a construction lien foreclosure action). This was the issue in a recent appeal discussed here where the party that recovered an affirmative judgment on a breach of contract case was not deemed the prevailing party for purposes of attorney’s fees. While the party prevailed on one of its claims, it did not prevail on others, and it recovered less than half of the damages it originally sought. The appellate court, affirming the trial court, held that the trial court has discretion to determine that the party that recovered an affirmative judgement was not the prevailing party entitled to its attorney’s fees under the signifiant issues test. This was not what the party was expecting when the attorney’s fees it expended far exceeded the judgment it recovered.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Will a Notice of Non-Responsibility Prevent Enforcement of a California Mechanics Lien?
August 06, 2019 —
William L. Porter - Porter Law GroupThe “Notice of Non-Responsibility” is one of the most misunderstood and ineffectively used of all the legal tools available to property owners in California construction law. As a result, in most cases the answer to the above question is “No”, the posting and recording of a Notice of Non-Responsibility will not prevent enforcement of a California Mechanics Lien.
The mechanics lien is a tool used by a claimant who has not been paid for performing work or supplying materials to a construction project. It provides the claimant the right to encumber the property where the work was performed and thereafter sell the property in order to obtain payment for the work or materials, even though the claimant had no contract directly with the property owner. When properly used, a Notice of Non-Responsibility will render a mechanics lien unenforceable against the property where the construction work was performed. By derailing the mechanics lien the owner protects his property from a mechanics lien foreclosure sale. Unfortunately, owners often misunderstand when they can and cannot effectively use a Notice of Non-Responsibility. As a result, the Notice of Non-Responsibility is usually ineffective in protecting the owner and his property.
The rules for the use of the Notice of Non-Responsibility are found in California Civil Code section 8444. Deceptively simple, the rules essentially state that an owner “that did not contract for the work of improvement”, within 10 days after the owner first “has knowledge of the work of improvement”, may fill out the necessary legal form for a Notice of Non-Responsibility and post that form at the worksite and record it with the local County Recorder in order to prevent enforcement of a later mechanics lien on the property.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Construction Litigation Roundup: “Ursinus is Cleared!”
March 11, 2024 —
Daniel Lund III - LexologyUrsinus University in Pennsylvania – a “private, nonprofit liberal arts college” – funded a construction project for a new building utilizing monies loaned by the Montgomery County Health and Higher Education Authority, a public economic development authority “formed by the Board of County Commissioners… authorized to issue bonds relative to projects for eligible educational institution such as Ursinus.”
Loans up to the amount of $23,000,000 became available to the University, and construction proceeded using the loans as construction funds. At issue: whether a project was to be considered publicly funded project such that prevailing wage rates were required to be paid. IBEW filed a related grievance with the Pennsylvania Department of Labor and Industry’s Bureau of Labor Law Compliance, which was refused by the Bureau, on the basis that because work was “financed completely by loans from the Authority, which Ursinus was required to repay in their entirety, the Project was ultimately funded through private sources and exempt from coverage under the [Pennsylvania Prevailing Wage Act].” A grievance to the Prevailing Wage Appeals Board ensued, and the Board took a different position.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Contractor Gets Benched After Failing to Pay Jury Fees
April 11, 2022 —
Garret Murai - California Construction Law BlogTrial by jury is a fundamental right under the U.S. and California Constitutions. However, to avail yourself of this right, you not only have to declare that in advance that you intend to try your case to a jury but post jury fees as well. In TriCoast Builders, Inc. v. Fonnegra, a contractor who failed to timely post jury fees, discovered on the day of trial that it waived the right to insist on a jury trial when the defendant pulled an “I gotcha” and waived his right to a jury trial.
The TriCoast Case
In May 2014, Nathaniel Fonnegra house was damaged by fire. The following month, Fonnegra entered into a construction contract with TriCoast Builders, Inc. to repair the property. Dissatisfied with the work, Fonnegra terminated the contract, and TriCoast in turn filed a complaint against Fonnegra for unpaid work.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
The Status of OSHA’s Impending Heat Stress Standard
May 30, 2022 —
Stephen E. Irving - ConsensusDocsThere has been much talk in the last several months about OSHA’s intent to establish a national standard to prevent heat-related injury and illness. OSHA’s Region VI, covering the states of Texas, Louisiana, Arkansas, Oklahoma, and New Mexico
[1], has had a regional emphasis program dealing with the hazards of heat stress for more than two decades, and much of the talk about a new national standard suggests modeling some aspects of the standard after the Region VI program. Region VI’s long-standing program emphasizes water, rest, and shade; acclimatization; and responding to medical emergencies.
In October 2021, OSHA issued its advance notice of proposed rulemaking (ANPRM) for Heat Injury and Prevention. The ANPRM rulemaking established a new Heat Injury and Illness Prevention Work Group within the National Advisory Committee on Occupational Safety and Health (NACOSH.)
Read the court decisionRead the full story...Reprinted courtesy of
Stephen E. Irving, Peckar & AbramsonMr. Irving may be contacted at
sirving@pecklaw.com
Is it the End of the Lease-Leaseback Shootouts? Maybe.
September 07, 2020 —
Garret Murai - California Construction Law BlogIt’s the case that has turned into a modern day Hatfield versus McCoy – McGee v. Torrance Unified School District, Case No. 8298122, 2nd District Court of Appeals (May 29, 2020) – a series of cases challenging the validity of certain lease-leaseback construction contracts in California.
In shootout number one, James McGee sued the Torrance Unified School District challenging the validity of lease-leaseback contracts the District had entered into with general contractor Balfour Beatty Construction, LLC. Under California’s lease-leaseback statute, a school district can lease property it owns to a developer, who in turns builds a school facility on the property and leases the facility back to the school district. The primary benefit of the lease-leaseback method of project delivery is that a school district does not need to come up with money to build the facility because the district pays for the facility over time through lease payments to the developer. In shootout number one, McGee argued that Torrance Unified School District was required to competitively bid the lease-leasebacks projects. The 2nd District Court of Appeals disagreed.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Suing a Local Government in Land Use Cases – Part 1 – Substantive Due Process
February 16, 2017 —
Wally Zimolong – Supplemental ConditionsBecause of my personal political persuasions (pro-freedom) and success in litigating cases against the government and other media about those cases businesses frequently approach me about bringing claims against local governments and agencies for interfering with their Constitutional rights. Actions by local government agencies that could give rise to a Constitutional violation include: treating a developer’s project differently than a similar project, revoking a previously issued zoning or building permit, disqualifying a contractor from bidding on a government contract, retaliating against a business owner for speaking out against the local agency or one of its members, or unnecessarily delaying the issuance of a permit. The Constitutional rights most typically implicated in these cases are those guaranteed by the 5th and 14th Amendments to the United States Constitution. However, the 1st Amendment is also frequently implicated.
Suing a local government agency for violating your Constitutional rights is not easy. However, the federal statute under which the cases are brought, 42 U.S.C. Section 1983, provides for the award of a successful plaintiff’s attorneys fees. This is true even if the Judge or jury awards a mere $1 is damages. Moreover, sometimes there can be a strategic value in the litigation.
This is the first in a series of blog posts exploring claims available to businesses harassed by local government agencies and officials and the challenges inherent in successfully bringing those claims. We will start with a claim for a substantive due process violation.
Read the court decisionRead the full story...Reprinted courtesy of