More In-Depth Details on the Davis-Bacon Act Overhaul
November 06, 2023 —
Seth C. Wiseman & Angela M. Richie - Construction ExecutiveThe U.S. Department of Labor’s finalization of a
rule updating the Davis-Bacon Act, the federal law that governs how prevailing wages for federal construction projects can be determined, will have a significant impact on contractors and workers alike in the construction industry. The new rule, in effect, adopts the 30% rule, meaning that the prevailing wages must be equal to the wage paid to at least 30% of workers of a particular classification in a particular area. The new rule also implements a new anti-retaliation provision, specifically protecting construction workers who raise concerns about payment practices from adverse employment actions. The timing of this new rule is particularly significant for contractors, as it will likely raise the cost of labor for contractors at a time when the Infrastructure Investment and Jobs Act and the CHIPS Act are providing additional funding for federal projects across the country. Thus, it is important for all parties in the construction industry to understand the updated rule in order to evaluate the short-term impacts on their respective projects and long-term impact on their respective businesses.
Reprinted courtesy of
Seth C. Wiseman & Angela M. Richie, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Wiseman may be contacted at swiseman@grsm.com
Ms. Richie may be contacted at arichie@grsm.com
Read the court decisionRead the full story...Reprinted courtesy of
Recent Environmental Cases: Something in the Water, in the Air and in the Woods
July 22, 2019 —
Anthony B. Cavender - Gravel2GavelState of Texas, et al. v. US EPA. The revised regulatory definition of “Waters of the U.S.” continues to generate litigation in the federal courts. On May 28, 2019, the U.S. District Court for the Southern District of Texas held that the 2015 rulemaking proceedings used by EPA and the U.S. Army Corp of Engineers to redefine this important component of the Clean Water Act were flawed in that the notice and comment provisions of the Administrative Procedure Act (APA) were violated because insufficient notice was provided by these agencies that “adjacent” waters newly subject to the regulatory jurisdiction of these agencies, can be determined on the basis of specific distances, which was a change in the agencies’ thinking, and insufficient notice of this change was provided to the public. In addition, the final rule “also violated the APA by preventing interested parties from commenting on the scientific studies that served as the technical basis” for the rule. However, the court did not vacate the new rule, but remanded the matter to the “appropriate administrative agencies” to give them an opportunity to fix this problem.
State of Oklahoma, ex rel. Mike Hunter, Attorney General of Oklahoma v. US EPA and the United States Army Corps of Engineers. A day later, on May 29, 2019, the U.S. District Court for the Northern District of Oklahoma rejected arguments that the new redefinition should be preliminarily enjoined.While this case was filed in 2015, intervening litigation in the federal courts, including the U.S. Supreme Court, caused a substantial delay in the disposition of this case. The court, noting that the tests for granting such an injunction against the federal government are fairly exacting, held that the plaintiffs, the State of Oklahoma and a number of industry groups and associations, failed to convince the court that the harm they would suffer if the rules remained effective would be irreparable. Presumably, this case will be going to trial in the near future.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
The Five-Step Protocol to Reopening a Business
August 03, 2020 —
Amy R. Patton & Rana Ayazi - Payne & FearsOver the past few months, guidance on how to create a safer, low-risk workplace has frequently changed. Fortunately, the state of California has finally reached a point where comprehensive and concrete advice is now available.
On June 24, 2020, the California Statewide Industry Guidance to Reduce Risk website was updated. In addition to providing industry-specific guidance and opening checklists for approximately 40 different industries, the website now unambiguously requires all businesses—regardless of which “phase” they reopen—to follow a five-step protocol (as described in greater detail throughout this article):
- Perform a detailed risk assessment and create a site-specific protection plan.
- Train employees on how to limit the spread of COVID-19. This includes how to screen themselves for symptoms and when to stay home.
- Set up individual control measures and screenings.
- Put disinfection protocols in place.
- Establish physical distancing guidelines
Reprinted courtesy of
Amy R. Patton, Payne & Fears and
Rana Ayazi, Payne & Fears
Ms. Patton may be contacted at arp@paynefears.com
Ms. Ayazi may be contacted at ra@paynefears.com
Read the court decisionRead the full story...Reprinted courtesy of
Design-Build Contracting: Is the Shine Off the Apple?
March 09, 2020 —
John P. Ahlers - Ahlers Cressman & Sleight PLLCThe design-build delivery method offers many benefits to owners. Among the cited benefits are that projects are generally completed faster, at a lower cost, by allowing innovative approaches through early and continual contractor involvement in the design process. The design contractor serves as a single point of contact responsible for both the design and construction of the project.
The Washington State Department of Transportation (“WSDOT”) utilized the design-build procurement method on the largest project ($2 billion) of its type in the state of Washington: the Highway 99 Tunnel, which was finished almost three years late after the tunnel-boring machine (“Bertha”) broke down six years ago. The sorted tale of the SR-99 Tunnel Project was the source of many of this firm’s blog articles.[1] The State of Washington staunchly maintained that the design-build contract protected its taxpayers from covering the repair costs to the tunnel-boring machine when it broke down in 2013. Bertha did not resume tunneling for almost two years, putting on hold removal of the Alaska Way viaduct and rebuilding of the Seattle Waterfront without an elevated highway.
In December 2013, the contractor for the project, Seattle Tunnel Partners (“STP”), contended that a 110-foot long 8” steel pipe which Bertha hit caused the breakdown. That pipe had been installed for groundwater testing by WSDOT in 2002 during its preliminary engineering for the viaduct replacement project. The project’s Dispute Review Board (“DRB”) composed of three tunneling experts found that the pipe constituted a “differing site condition” for which the State was responsible to disclose to contractors. The Board, whose views were non-binding, did not opine about how much damage the undisclosed pipe cost.[2] In other words, the mere fact that a differing site condition occurred did not establish that there was a causal connection between the damages which STP was seeking (in excess of $600 million) and the differing site condition (the 8” steel pipe which WSDOT lawyers at trial derisively referred to as “nothing more than a toothpick for Bertha’s massive cutter head”). STP maintained that Bertha had made steady progress except for three days immediately after hitting the pipe. It didn’t help the contractors’ case that during the discovery phase of the two-month trial, WSDOT lawyers uncovered documents showing that the contractor’s tunnel workers encountered and logged the pipe before digging began.[3]
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers Cressman & Sleight PLLCMr. Ahlers may be contacted at
john.ahlers@acslawyers.com
U.K. Puts Tax on Developers to Fund Safer Apartment Blocks
March 08, 2021 —
Emily Ashton & Olivia Konotey-Ahulu - BloombergThe U.K. announced an extra 3.5 billion pounds ($4.8 billion) toward the cost of stripping dangerous cladding from apartment blocks in England, with a new tax on developers from next year to help cover the costs.
Housing Secretary Robert Jenrick said the new cash will add to a previously announced 1.6 billion-pound “safety fund” to remove the material, which was blamed for the deaths of 72 people in a catastrophic fire at London’s Grenfell Tower in 2017.
A new tax will be introduced for U.K. residential developers in 2022 to raise at least 2 billion pounds over the next decade to ensure homebuilders “make a fair contribution” to solving the problem, Jenrick told the House of Commons on Wednesday.
Reprinted courtesy of
Emily Ashton, Bloomberg and
Olivia Konotey-Ahulu, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Brazil World Cup Soccer Crisis Deepens With Eighth Worker Death
May 13, 2014 —
Tariq Panja – BloombergBrazil’s troubled World Cup staging efforts suffered another setback today following the electrocution death of a worker at one of the stadiums still under construction.
Mohammed Ali, 32, was killed while working in the Arena Pantanal in Cuiaba, said Renata Martins, a spokeswoman for the state of Mato Grosso, where the venue is located.
Ali’s death is the eighth construction related fatality at Brazil’s 12 World Cup venues and comes 35 days before the tournament opens on June 12 in Sao Paulo’s Corinthians Arena, another facility where work remains. The Cuiaba stadium, which will host four games starting with Chile playing Australia on June 13, is still missing 5,000 seats.
Read the court decisionRead the full story...Reprinted courtesy of
Tariq Panja, BloombergMr. Panja may be contacted at
tpanja@bloomberg.net
Summary Judgment in Construction Defect Case Cannot Be Overturned While Facts Are Still in Contention in Related Cases
September 09, 2011 —
CDJ STAFFThe Alabama Court of Civil Appeals has dismissed an appeal of a summary judgment in the case Bella Investments, Inc. v. Multi Family Services, Inc. MFS was hired by Bella to be the general contractor for a hotel in Gardendale, Alabama. MFS hired various subcontractors, including the architect for the project. After completion of the hotel in April, 2006, Bella made requests for MFS to repair cracked floor tiles.
In August, 2008, Bella sued MFS, the architect, and various fictitiously named defendants. Subsequently, Bella amended its complaint, naming some of the fictitiously named defendants.
MFS in turn claimed that Bella’s claims were void under the statute of limitations and that Bella was in beach of contact by failing to pay MFS the full amount owed. MFS moved for summary judgment under the statute of limitations, which was granted by the court.
Bella requested that the court “alter, amend, or vacate its summary judgment order.” When this was denied, Bella appealed to the Alabama Supreme Court, which transferred the appeal to the Court of Civil Appeals. The Court of Appeals refused to vacate the summary judgment as claims that form part of the case against MFS are also part of Bella’s claims against the other defendants. For this reason, the court upheld the summary judgment.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Construction Injuries Under the Privette Doctrine. An Electrifying, but Perhaps Not Particularly Shocking, Story . . .
January 05, 2017 —
Garret Murai – California Construction Law BlogWe’ve talked about the Privette doctrine before (see
here,
here, and
here). The Privette doctrine, named after the court case Privette v. Superior Court (1993) 5 Cal.4th 689, provides in general that project owners and contractors are not responsible for worksite injuries suffered by employees of lower-tiered contractors they have hired, the rationale being that such workers should already be covered under their employers’ workers’ compensation insurance policies.
In the twenty years since Privette was decided, however, several exceptions have evolved that have narrowed the doctrine. One exception, known as the retained control exception, allows a contractor’s employees to sue the “hirer” of the contractor (that is, the higher-tiered party who “hired” the lower-tiered party whose employee is injured) when the hirer retains control over any part of the work and negligently exercises that control in a manner that affirmatively contributes to the employee’s injury. Hooker v. Department of Transportation (2002) 27 Cal.4th 198.
Another exception, known as the nondelegable duty exception, permits an injured worker to recover against a hirer when the hirer has assumed a nondelegable duty, including statutory and regulatory duties, that it breaches in a manner that affirmatively contributes to the injury. Padilla v. Pomona College (2008) 166 Cal.App.4th 661.
In a recently decided case, Khosh v. Staples Construction Company, Inc., Case No. B268937 (November 17, 2016), the California Court of Appeals for the Second District examined the application of the Hooker and Padilla exceptions where a general contractor was contractually responsible for overall site safety.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com