Investigation Continues on Children Drowning at Construction Site
August 13, 2014 —
Beverley BevenFlorez-CDJ STAFFTwo months ago, in Hobart, Illinois, two young boys (brothers) “drowned in an unsecured, excavated pit that filled with water” on a site owned by Goldschmidt Construction Services LLC of Hobart. The Post-Tribune reported that “Police Chief Richard Zormier said the department is waiting on reports from other agencies as it continues to investigate circumstances surrounding” the accident.
“We want to be thorough. The young boys deserve it. Their family deserves it,” Zormier told the Post-Tribune.
The family of the victims has filed a $60 million lawsuit against Goldschmidt Construction.
Read the court decisionRead the full story...Reprinted courtesy of
Colorado Court of Appeals Defines “Substantial Completion” for Subcontractors’ Work so as to Shorten the Period of Time in Which They Can Be Sued
October 20, 2016 —
David M. McLain – Colorado Construction Litigation BlogOver the past few years, there has been a battle raging on in district courts and arbitration hearing rooms throughout Colorado regarding when a subcontractor’s work is to be deemed “substantially complete,” for purposes of triggering Colorado’s six-year statute of repose. C.R.S. § 13-80-104 states, in pertinent part:
Notwithstanding any statutory provision to the contrary, all actions against any architect, contractor, builder or builder vendor, engineer, or inspector performing or furnishing the design, planning, supervision, inspection, construction, or observation of construction of any improvement to real property shall be brought within the time provided in section 13-80-102 after the claim for relief arises, and not thereafter, but in no case shall such an action be brought more than six years after the substantial completion of the improvement to the real property, except as provided in subsection (2) of this section.
* * *
(2) In case any such cause of action arises during the fifth or sixth year after substantial completion of the improvement to real property, said action shall be brought within two years after the date upon which said cause of action arises.
C.R.S. § 13-80-104 (emphasis added).
As the battle raged on at the trial court level, subcontractors and design professionals argued that their work should be deemed “substantially complete” when they finished their discrete scope of work within a project. Developers and general contractors, seeking to maintain third-party claims against the subcontractors and design professionals, typically argued either that the subcontractors’ and design professionals’ work should be deemed “substantially complete” upon the issuance of the final certificate of occupancy on the project, or upon the issuance of the final certificate of occupancy for the last building within a project on which the subcontractor or design professional worked. Trial court judges and arbitrators have been split on this issue, with perhaps a slight majority favoring one or the other approaches advocated by developers and general contractors, that the subcontractors’ and design professionals’ work is “substantially complete” upon the issuance of the last certificate of occupancy in a project (the minority view) or upon the issuance of the last certificate of occupancy for the last building within a project on which the subcontractor of design professional worked (the majority view).
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Construction Litigation Roundup: “Indeed, You Just Design ‘Em”
April 29, 2024 —
Daniel Lund III - LexologySeeking to be extracted from personal injury litigation initiated by a laborer on a project in New Orleans, an architect sued for negligence filed a motion for summary judgment.
The plaintiff had “testified in his deposition that after demolishing most of one of the side walls of the vault and a smaller section of the front wall, he was instructed to stand on top of the vault's concrete ceiling in order to demolish it with a hydraulic jackhammer.” One court noted that: “Shortly after beginning that task, the entire vault structure collapsed.” Claims against the architect included assertions of “failure to monitor and supervise the execution of the plans to ensure safety at the jobsite.”
The architect urged in support of its MSJ that it did not owe a duty to oversee, supervise, or maintain the construction site, or have any responsibility for the plaintiff’s safety. Summary judgment was granted to the architect by the trial court, and an appeal ensued, whereupon the appellate court reversed. That intermediate court found that potential intervening knowledge of the architect of a potentially unsafe demolition practice created an issue of material fact.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Court Exclaims “Enough!” To Homeowner Who Kept Raising Wrongful Foreclosure Claims
April 01, 2015 —
Krsto Mijanovic and Annette F. Mijanovic – Haight Brown & Bonesteel LLP“There are no free houses,” began the decision issued by the Court of Appeal on March 23, 2015 in Boyce v. T.D. Service Company (B255958). Examining three years of litigation in bankruptcy court, unlawful detainer court, and the superior court, and each of their respective appellate courts, the Court of Appeal held that the plaintiff’s wrongful foreclosure claims were barred by res judicata and collateral estoppel.
Plaintiff was a borrower who purchased a home subject to a deed of trust. After plaintiff defaulted on the loan, nonjudicial foreclosure proceedings were initiated. To avoid foreclosure, plaintiff engaged in a series of stall tactics, including filing an emergency bankruptcy petition, appealing the bankruptcy court’s decision to grant the trustee relief of stay, refusing to leave the property following the trustee’s sale thereby causing an unlawful detainer action to be filed, and appealing the granting of summary judgment in favor of the defendants in the unlawful detainer action. Once evicted, plaintiff sued all the entities involved in the foreclosure process for wrongful foreclosure, declaratory relief, violation of Unfair Practices Act, and quiet title. When the trial court sustained the defendants’ demurrers on the grounds of res judicata/collateral estoppel, plaintiff naturally appealed.
Reprinted courtesy of
Krsto Mijanovic, Haight Brown & Bonesteel LLP and
Annette F. Mijanovic, Haight Brown & Bonesteel LLP
Mr. Mijanovic may be contacted at kmijanovic@hbblaw.com
Ms. Mijanovic may be contacted at amijanovic@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
New York: The "Loss Transfer" Opportunity to Recover Otherwise Non-Recoverable First-Party Benefits
May 13, 2014 —
Robert M. Caplan – White and Williams LLPNew York’s “no-fault” legislation reflects a public policy designed to make the insurer of first-party benefits absorb the economic impact of loss without resort to reimbursement from its insured or, by subrogation, from the tortfeasor. Country Wide Ins. Co. v. Osathanugrah, 94 A.D.2d 513, 515 (N.Y. 1st Dept. 1983). The no-fault concept embodied in New York’s Insurance Law modifies the common law system of reparation for personal injuries under tort law. Safeco Ins. Co. of Am. v. Jamaica Water Supply Co., 83 A.D.2d 427, 431 (N.Y. 2nd Dept. 1981). “[F]irst party benefits are a form of compensation unknown at common law, resting on predicates independent of the fault or negligence of the injured party.” Id. at 431. The purpose of New York’s no-fault scheme is “to promote prompt resolution of injury claims, limit cost to consumers and alleviate unnecessary burdens on the courts.” Byrne v. Oester Trucking, Inc., 386 F. Supp. 2d 386, 391 (S.D.N.Y. 2005).
New York’s no-fault scheme—contained in Article 51 of its Consolidated Laws (“Comprehensive Motor Vehicle Insurance Reparations”)—requires owners of vehicles to carry insurance with $50,000 minimum limits which covers basic economic loss, i.e., first-party benefits, on account of personal injury arising from the use or operation of a motor vehicle. Basic economic loss includes, among other things: (1) medical expenses; (2) lost earnings up to $2,000 per month for three years; and (3) out-of-pocket expenses up to $25 per day for one year. N.Y. INS. LAW § 5102(a).
Read the court decisionRead the full story...Reprinted courtesy of
Robert M. Caplan, White and Williams LLPMr. Caplan may be contacted at
caplanr@whiteandwilliams.com
Colorado Court of Appeals’ Ruling Highlights Dangers of Excessive Public Works Claims
August 26, 2024 —
David M. McLain – Colorado Construction LitigationIn the case of Ralph L. Wadsworth Construction Company, LLC v. Regional Rail Partners (2024 COA 78), the Colorado Court of Appeals reviewed a complex contract dispute related to the design and construction of a transit rail line. The project, commissioned by the Regional Transportation District (“RTD”), involved a collaboration between Regional Rail Partners and Ralph L. Wadsworth Construction Company (“Wadsworth”) to build the North Metro Rail Line between Denver Union Station and Thornton.
Key Facts:
- Contracts and Payments: Regional Rail Partners contracted with Wadsworth to perform specific construction tasks with a total contract value of $60,210,783. By the time of the trial, Regional Rail had paid almost $58 million of this amount.
- Disputes and Delays: The project faced numerous delays and disputes, leading to Wadsworth claiming significant financial damages attributed to these disruptions. In April 2018, Wadsworth’s expert estimated that Regional Rail owed them $12,408,496.60.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Nine Gibbs Giden Partners Listed in Southern California Super Lawyers 2022
February 14, 2022 —
Gibbs Giden Locher Turner Senet & Wittbrodt, LLPPremiere law firm Gibbs Giden Locher Turner Senet & Wittbrodt, LLP announced that 9 of the firm's partners have been selected by their peers for inclusion in the 2022 Southern California Super Lawyers list.
The Super Lawyers lists are issued by Thomson Reuters. These lists honor no more than 5% of licensed attorneys in each state, based on peer recognition and professional achievements.
The following Gibbs Giden attorneys have been selected to the 2022 Southern California Super Lawyers list:
LOS ANGELES
Barbara Gadbois – Construction Law
Sara Kornblatt – Construction Law and Litigation
William (Bill) Locher - Real Estate and Business Law
Ted Senet – Insurance and Construction Law
Glenn Turner – Construction Law and Litigation
Richard Wittbrodt – Construction Law and Litigation, AAA Mediator/Arbitrator
IRVINE
Philip Zvonicek – Business, Corporate, Construction, Insurance Law
WESTLAKE
Jason Adams – Construction and Insurance Law
Christopher Ng – (Managing Partner) Construction and Business Law
Gibbs Giden understands the complex challenges companies face in today’s competitive business environment. From our roots in construction law to our evolution into a premier law firm serving the diverse needs of the business community, we provide the insight and advice our clients need to position themselves for the future.
www.gibbsgiden.com LOS ANGELES | IRVINE | SAN JOSE | WESTLAKE | LAS VEGAS
Read the court decisionRead the full story...Reprinted courtesy of
Manhattan Developer Breaks Ground on $520 Million Project
November 18, 2011 —
CDJ STAFFRebuilding an area of Midtown West that has been condemned for decades, the Gotham Organization has broken ground on a 1,200-unit project that will include housing for a variety of household incomes and a school. One unit of the project will be affordable housing for families of annual incomes up to $40,000. Another will be for middle-income households. Additionally, there will be a 31-story tower with 550 luxury units.
The site CityBiz quotes Mayor Michael Bloomberg, as saying that the project “will grow our economy by creating 2,900 construction-related jobs.” The president of the Gotham Organization, David L. Picket notes that it will “create hundreds of new jobs, generate millions of dollars in revenue for the construction industry, contribute towards the building of a new primary, and provide homes to thousands of New Yorkers.”
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of