Court of Appeal Shines Light on Collusive Settlement Agreements
October 21, 2015 —
Kristian B. Moriarty & R. Bryan Martin – Haight Brown & Bonesteel LLPIn Diamond v. Reshko, (filed 8/20/2015, No. A139251) the California Court of Appeal, First District, held that a defendant was entitled to introduce evidence at trial reflecting amounts paid by co-defendants in settlement of a plaintiff’s claim.
Plaintiff, Christine Diamond, was injured during an automobile accident that occurred while she was a passenger in a taxi driven by Amir Mansouri. Christine, and her husband Andrew, filed suit against Mr. Mansouri, the Yellow Cab Collective (“Yellow Cab”), and the driver of the vehicle that collided with the taxi, Serge Reshko. Before trial, Mansouri and the Yellow Cab Collective settled with Plaintiffs, but agreed to appear and participate as defendants at the jury trial of the action. Mansouri and Yellow Cab paid a total of $400,000 to Plaintiffs in settlement.
Reshko filed a pre-trial motion seeking an order permitting Reshko to admit evidence of the settlement between Plaintiffs and the other defendants. The trial court refused to rule on the motion before trial. Ultimately, evidence of the settlement between Plaintiffs, Mansouri and Yellow Cab was excluded during trial. The jury returned a verdict in favor of Plaintiffs in the total amount of $745,778, finding Mansouri 40 percent at fault, and Reshko 60 percent at fault. The Trial Court entered judgment against Reshko in the sum of $406,698.
Reshko appealed the judgment. The First District Court of Appeal reversed, holding that evidence of the settlement should have been admitted at trial because the settling defendant’s position should be revealed to the court and jury to avoid committing a fraud on the court, and in order to permit the trier of fact to properly weigh the settling defendant’s testimony.
Reprinted courtesy of
Kristian B. Moriarty, Haight Brown & Bonesteel LLP and
R. Bryan Martin, Haight Brown & Bonesteel LLP
Mr. Moriarty may be contacted at kmoriarty@hbblaw.com
Mr. Martin may be contacted at bmartin@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
The Private Works: Preliminary Notice | Are You Using the Correct Form?
August 20, 2019 —
William L. Porter, Esq. - Porter Law GroupThe Private Works – Preliminary Notice form which contractors, subcontractors and suppliers had become accustomed to using for many years changed in 2004. Despite this change in law, many in the construction industry have still not started using the correct new form. Changes in the law, championed by the American Subcontractors’ Association, gave a significant new benefit to subcontractors and suppliers by giving the subcontractor or supplier some expectation of actually receiving notice of when a Notice of Completion or a Notice of Cessation has been recorded on many private works projects. The law also changed the language of the California Preliminary Notice that subcontractors and suppliers must use to protect their mechanics’ lien, bond claim and stop payment notice rights. If Owners do not send out the Notice of Completion as required by law they incur a diminishing of the protections afforded to them when they record a Notice of Completion or Notice of Cessation on many private works projects.
The revised law requires private project owners to notify all subcontractors and suppliers within 10 days after recording a Notice of Completion or Notice of Cessation that a Notice of Completion or a Notice of Cessation has actually been recorded. In order to receive such notice, the subcontractor or supplier must properly serve the new form of Preliminary Notice. If this properly occurs and the private project owner provides the required notice, then the subcontractor or supplier will have 30 days to record a Mechanics’ Lien. However, if an owner under such circumstances fails to properly notify a subcontractor or supplier within 10 days after recording a Notice of Completion or Notice of Cessation, then the Subcontractor or supplier will have 90 days to record a Mechanics’ Lien. The details of the law can be found in California Civil Code sections 8190, 8414 and 8416.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Esq., Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Federal Contractors – Double Check the Terms of Your Contract Before Performing Ordered Changes
July 08, 2019 —
Jonathan Schirmer - Ahlers Cressman & Sleight PLLCAs federal contractors may be aware, the general rule when performing a contract for the federal government is that only the contracting officer (“CO”) can bind the government. Often, the CO delegates responsibility to a contracting officer’s representative (“COR”). While in some cases a COR may be able to bind the federal government, the contract may limit that ability exclusively to the CO.
Important for our clients, it is the responsibility of the contractor to determine whether the COR can legally bind the federal government when ordering changes to the scope of work. [1] This is true even when a COR possesses apparent authority to order changes to the work, and when the project is almost exclusively overseen by COR’s. [2]
A recent case highlights the dangers of a contractor relying on the orders of a COR when performing work outside the scope of a contract. In Baistar Mechanical Inc., a contractor was awarded a maintenance and snow removal contract with the federal government. The contract expressly stated that only the CO had contracting authority regarding additional or changed work. [3] However, Baistar, the contractor, argued it was directed by the contracting officer’s representatives to perform work outside of the contract.
Read the court decisionRead the full story...Reprinted courtesy of
Jonathan Schirmer, Ahlers Cressman & Sleight PLLCMr. Schirmer may be contacted at
jonathan.schirmer@acslawyers.com
Lead Paint: The EPA’s Renovation, Repair and Painting Rule
September 09, 2019 —
Christopher G. Hill - Construction Law MusingsFor this week’s Guest Post Friday here at Musings, we welcome Joshua Glazov for the first time. Josh has been a construction lawyer since 1995. He practices at Much Shelist in Chicago and focuses on negotiating and preparing design and construction contracts for owners, contractors, and lenders, as well as preparing for, and confronting, construction related insolvency when a project participant goes bankrupt or a lender goes into FDIC receivership. Josh publishes on these topics at his blogs: Construction Law Today and the Bank Failure Blog.
Last month the EPA finally issued their Renovation, Repair and Painting Rule (PDF), the one that sets up new requirements for work on projects that may involve lead paint. The requirements are many complex. You’ll need to become familiar with this rule if you do any renovation , repair, or painting work, especially of your work is on buildings built before lead paint was banned in 1978.
- You’ll need to become a certified by the EPA as a Certified Renovation Firm
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Mutual Or Concurrent Delay Caused By Subcontractors
March 23, 2020 —
David Adelstein - Florida Construction Legal UpdatesHow are delay damages treated when two subcontractors cause a mutual or concurrent delay to the project?
Assume multiple subcontractors concurrently contributed to an impact to the critical path resulting in a delay to the project. The delay caused the prime contractor to: (1) be assessed liquidated damages from the owner and (2) incur extended general conditions. The prime contractor will be looking to the subcontractors for reimbursement for any liquidated damages it is assessed along with its extended general conditions costs.
There is really no great case that addresses this point when two (or more) subcontractors mutually or concurrently delay the project. It is also not uncommon, and frankly expected, that a subcontractor will point the finger at another subcontractor for the cause of the delay or that another subcontractor was concurrently delaying the project.
The prime contractor should absolutely, without any exception, undertake efforts with a scheduling consultant to allocate the delay caused by subcontractors. Taking an approach that joint and several liability applies between multiple subcontractors and/or not trying to apportion delay because the subcontractors concurrently delayed the critical path at the same time is probably not the best approach. The prime contractor should have an expert render an opinion as to the allocation of the delay period amongst responsible subcontractors that delayed the critical path. Not doing so, in my opinion, is a mistake.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Delays and Suspension of the Work Under Fixed Price Government Contract
July 22, 2024 —
David Adelstein - Florida Construction Legal UpdatesHere is an interesting fact pattern and case decided by the Civilian Board of Contract Appeals dealing with (1) force majeure type events and epidemics (Covid-19); (2) suspension of the work; and (3) delays. These are three topics important to all contractors including federal contractors.
In Lusk Mechanical Contractors, Inc. v General Services Administration, 2024 WL 1953697, CBCA 7759 (CBCA 2024), a contractor entered into a fixed price contract with the government to repair, replace, and modernize site and building systems at a federal building. The contractor commenced work right before Covid-19. When Covid-19 hit, the government issued the contractor a two-week suspension of work notice on March 27, 2020. The suspension of work allowed off-site administrative work to continue but suspended on-site physical work. The government extended the suspension of work three more times. The contractor could resume work on the exterior on June 1, 2020, but was not permitted to resume work on the interior until July 20, 2020. On the same date that the contractor was able to commence interior work, it submitted a modification for delay caused by the suspension – 64 days for the time period the entire site shutdown, and 51 days for the interior work shutdown.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
It’s a COVID-19 Pandemic; It’s Everywhere – New Cal. Bill to Make Insurers Prove Otherwise
August 17, 2020 —
Scott P. DeVries & Andrea DeField - Hunton Andrews KurthOn June 29, in a development that may fundamentally change the landscape for California businesses which have sustained COVID-19 related business interruption loss, two California legislators amended pending legislation to address several of the most hotly contested issues regarding insurance recovery for these devastating losses.
The bill, Assembly Bill 1552, focuses on All-Risk property insurance policies. As amended, it would create a “rebuttable presumption” that COVID-19 was present on and caused physical damage to property which was the direct cause of business interruption. A similar rebuttable presumption would apply to orders of civil authority coverage and to ingress/egress coverage. The bill would further prohibit COVID-19 from being construed as a pollutant or contaminant for purposes of any policy exclusion unless the exclusion specifically referred to viruses. The bill would apply to any All-Risk policy in effect on or after March 4, 2020 and is written to satisfy the standards for an “urgency” statute, taking effect immediately upon being signed into law.
Reprinted courtesy of
Scott P. DeVries , Hunton Andrews Kurth and
Andrea DeField, Hunton Andrews Kurth
Mr. DeVries may be contacted at sdevries@HuntonAK.com
Ms. DeField may be contacted at adefield@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
California Bullet Train Clears Federal Environmental Approval
June 30, 2014 —
Michael B. Marois – BloombergThe U.S. Federal Railroad Administration has approved an environmental review needed to begin building a portion of a $68 billion California high-speed rail line that has been mired in lawsuits.
The agency, part of the Transportation Department, said in a release that it cleared a 114-mile (183-kilometer) stretch of the project in the Central Valley.
The California High-Speed Rail Authority has been blocked from selling bonds to begin construction of the first U.S. bullet train until a court decides whether details of the financing were adequately disclosed.
Read the court decisionRead the full story...Reprinted courtesy of