Charles Carter v. Pulte Home Corporation
October 12, 2020 —
Michael Velladao - Lewis BrisboisIn Carter v. Pulte Home Corp., __Cal.App.5th__(July 23, 2020), the California Court of Appeal affirmed the entry of judgment in favor of subcontractors in connection with a Complaint for Intervention based on equitable subrogation filed by Travelers Property Casualty Company of America (“Travelers”) seeking to recover defense costs incurred in defending Pulte Home Corporation (“Pulte”) in an underlying construction defect lawsuit. The parties’ dispute arose out of Travelers’ defense of Pulte as an additional insured under policies issued to four subcontractors involved in the underlying construction defect lawsuit. Several subcontractors involved in the underlying construction defect lawsuit refused to defend Pulte based on the indemnity clauses in their subcontracts. Such clauses promised to indemnify Pulte as follows:
“all liability, claims, judgments, suits, or demands for damages to persons or property arising out of, resulting from, or relating to Contractor’s performance of work under the Agreement (“Claims”) unless such Claims have been specifically determined by the trier of fact to be the sole negligence of Pulte. . . .”
Pulte eventually settled the construction defect lawsuit and its claims against all of the subcontractors. Travelers ultimately paid $320,491.82 for Pulte’s defense and recovered $164,400 from some of the subcontractors. Travelers’ intervention in the underlying lawsuit was intended to recover the remaining $156,091.82 from the subcontractors that refused to indemnify Pulte for the defense of the construction defect lawsuit. In the underlying trial, Travelers argued that the subcontractors were obligated to pay defense costs on a joint and several basis (minus what Travelers had already recovered). The trial court did not agree and held that Travelers was not entitled to equitable subrogation for the remaining defense costs.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Velladao, Lewis BrisboisMr. Velladao may be contacted at
Michael.Velladao@lewisbrisbois.com
Broken Buildings: Legal Rights and Remedies in the Wake of a Collapse
October 11, 2021 —
David J. Pfeffer - Construction ExecutiveA tragedy transpired on June 24 in Surfside, Florida, when the Champlain Towers South suddenly fell, becoming one of the country’s most deadly unintentional building collapses. It is imperative that construction industry professionals be aware of the legal issues that are raised by such ill-fated events.
Who Is Held Responsible?
Who can be held responsible for such disasters lies among several possible parties:
- The building’s design professionals, particularly its architects and structural engineers. They are charged with ensuring that the building’s design is safe. They must take many factors into account, including, but not limited to, the materials that are used, the foundation, the weight and the height.
- General contractors and the subcontractors. General contractors implement the design created by the architects and engineers and are responsible for appropriate materials. The general contractor also supervises the subcontractors aiding with multiple areas of the building’s construction and which also share the responsibility of executing the design and maintaining the building’s structural integrity.
Reprinted courtesy of
David J. Pfeffer, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Pfeffer may be contacted at
dpfeffer@tarterkrinsky.com
Lawmakers Strike Deal on New $38B WRDA
January 09, 2023 —
Tom Ichniowski - Engineering News-RecordKey Senate and House leaders have reached a bipartisan agreement on a new Water Resources Development Act (WRDA) that would authorize more than $37 billion in federal funds for 25 new and five modified Army Corps of Engineers flood and hurricane protection, harbor dredging and other civil works projects across the U.S.
Reprinted courtesy of
Tom Ichniowski, Engineering News-Record
Mr. Ichniowski may be contacted at ichniowskit@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Homeowner Has No Grounds to Avoid Mechanics Lien
September 01, 2011 —
CDJ STAFFThe California Court of Appeals has rejected a motion by a homeowner in a dispute with the contractor who built an extension to his home. In McCracken v. Pirvulete, Mr. McCracken filed a mechanics lien after Mr. Pirvulete failed to complete payment. The matter went to trial with a series of exhibits that showed “the contractual relationship was strained and the parties disagreed over performance and payment.” As a result of the trial, the court awarded Mr. McCracken, the contractor, $1,922.22.
Mr. Pirvulete appealed, contending that the court had not allowed his daughter to act as a translator, that the court had failed to give him sufficient time to present his case, that the mechanics lien should have been dismissed, and several other claims, all before a formal judgment was issued. After the court formalized its judgment and rejected the appeal, Mr. Pirvulete appealed again.
The appeals court found that Mr. Pirvulete did not provide an adequate record for review. The court dismissed Mr. Pirvulete’s claims. The court notes that Mr. Pirvulete claimed that a request for a discovery period was denied, however, he has provided neither the request nor the denial. The trial court has no record of either.
Nor was there a record of a request that Mr. Pirvulete’s daughter provide translation. The court notes, “so far as we can glean from the record provided, the Register of Actions states, ‘Trial to proceed without Romanian Interpreter for Defendant; Daughter present to interpret if needed.’” Additionally, the court found that “there has been no showing that his facility with the English language is or was impaired in any way or that there was any portion of any proceeding, which he did not understand.”
Further, the appeals court found there were no grounds for a new trial, despite Mr. Pirvulete’s filings. The court concluded, “The owner has failed to provide a record adequate for review of most, if not all, of the claims of error. Some issues are not cognizable because they relate to entirely separate proceedings, and not the trial below. To the limited extent that the claims are examinable, the owner has made no showing of error.” The court affirmed the judgment of the lower court against Mr. Pirvulete.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Musk’s Cousins Battle Utilities to Make Solar Rooftops Cheap
April 15, 2015 —
John Lippert and Christopher Martin – BloombergIn September 2013, Hawaiian Electric Co. told thousands of customers they couldn’t connect their new solar panels to its distribution grid. In some neighborhoods, HECO said, its system couldn’t absorb any more unused energy from home solar arrays. The moratorium, which lasted 13 months, made Hawaii a central battleground in the effort by utilities to control the rapid growth of independent solar companies across the U.S. And it was a big deal to people such as Robert Gould, a retired Northwest Airlines pilot living near Honolulu. He’d just paid $53,000 to have solar panels installed.
Gould and other customers protested loudly to state officials. They finally got help from Lyndon Rive, the CEO of SolarCity. The San Mateo, California, company is the biggest installer of rooftop solar panels in the U.S. and has 10,000 Hawaiian customers, Bloomberg Markets magazine reports in its May issue. Rive studied the situation and zeroed in on a key fact: HECO had never directly measured how much solar its grid could handle, relying on computer simulations instead. “Because the technology is brand-new, no one had ever done this in the field before,” says Colton Ching, HECO’s vice president for energy delivery.
Reprinted courtesy of
John Lippert, Bloomberg and
Christopher Martin, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Submitting Claims on Government Projects Can Be Tricky
March 19, 2015 —
Craig Martin – Construction Contractor AdvisorThe Federal Circuit Court of Appeals opinion in K-Con Building Systems, Inc. v. United States illustrates the difficulties a contractor may face when pursuing a claim before a Contracting Officer. After nearly 10 years of litigation, the court found that the contractor’s claim to the Contracting Officer did not contain enough detail to allow the claim to proceed. That’s a lot of time and resources wasted on a claim that was dead from the start.
K-Con was awarded a $582,000 job to design and build a Coast Guard support building in Michigan. K-Con was unable to complete the project by the finish date and the Coast Guard assessed liquidated damages of $109,554. K-Con contested the assessment of liquidated damages by submitting a one paragraph letter asserting that it was not the sole cause of the alleged delays; that the government was at fault for the delay; and the liquidated damages were an impermissible penalty. The Contracting Officer ultimately denied K-Con’s claim and K-Con appealed to the Court of Claims.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Beyond Inverse Condemnation in Wildfire Litigation: An Oregon Jury Finds Utility Liable for Negligence, Trespass and Nuisance
July 10, 2023 —
Marisa Miller, John Yacovelle & Kazim Naqvi - Sheppard MullinOn June 10, 2023, a jury in Portland, Oregon found PacifiCorp and Pacific Power (collectively, “PacifiCorp”) liable for negligence, trespass, and nuisance based on a series of four wildfires that occurred during Labor Day weekend in 2020. PacifiCorp prevailed against the plaintiffs on the claim of inverse condemnation. With respect to the tort-based claims, the jury awarded approximately $72 million in compensatory damages to 17 plaintiffs. The jury later found PacifiCorp liable for $18 million in punitive damages, or one quarter of the compensatory damages that the jury awarded to the 17 plaintiffs. The jury’s liability findings apply to a broader class of owners, whose damages will need to be individually proven in a yet-to-be defined second phase of proceedings. Post-verdict motion practice and appeals may affect the jury’s findings.
Reprinted courtesy of
Marisa Miller, Sheppard Mullin,
John Yacovelle, Sheppard Mullin and
Kazim Naqvi, Sheppard Mullin
Ms. Miller may be contacted at mmiller@sheppardmullin.com
Mr. Yacovelle may be contacted at jyacovelle@sheppardmullin.com
Mr. Naqvi may be contacted at knaqvi@sheppardmullin.com
Read the court decisionRead the full story...Reprinted courtesy of
Designers “Airpocalyspe” Creations
May 19, 2014 —
Beverley BevenFlorez-CDJ STAFFBlaine Brownell in Architect Magazine discussed how recently some designers have created items to deal with urban pollution, however, the creations themselves are more politically-charged than practical.
Brownell lists recent examples of architects and designers “perverse” creations: “Notable smog-inspired works include the Aegis Parka, a protective jacket created by Dutch design studio Nieuwe Heren; a palladium dichloride coat that changes color in the presence of carbon dioxide emissions and is designed by London-based artist Lauren Bowker; and R&Sie(n)’s ‘Dustyrelief’ building in Bangkok, designed to collect atmospheric dust via an electrostatically-charged facade.”
“Perhaps such proposals—and the disarming irony they conjure—will motivate the changes necessary to clean up our act,” Brownell concluded.
Read the court decisionRead the full story...Reprinted courtesy of